A list of references for hearing by a TTP/Timetabling Panel (including those references to the former Timetabling Committee which had not been resolved as at 15.04.05).
The “Date” column indicates, if shown in brackets, the month that the reference was notified for hearing by a Timetabling Panel (Timetabling Committee prior to 15 April 2005); OR, if not in brackets, it indicates the date of the hearing.
References to the Timetabling Committee (which can be found by following the hyperlink) were registered with prefix ‘ttc’. Those which were taken forward on 15 April 2005 for hearing by a Timetabling Panel were re-registered with prefix ‘TTP’. Both registration numbers are shown where appropriate.
References to the Network and Vehicle Change Committee were registered with prefix ‘NV’. Disputes NV75 – NV77 inc and NV79 – NV84 inc were taken forward on 15 April 2005 for consideration by a Timetabling Panel. The Panel recorded its determinations for these references in a single document titled “Panel Decision Number 1”.
Please note that, to comply with GDPR requirements, any submissions that include personal information (i.e. including data in the format firstname.surname@companyname) have been removed from the website. A redacted version can be sought by application to the ADC Secretary. A link to the Committee’s privacy statement can be found here.
Reference Number | PDF Version | Date | Reference From | Subject | Submissions From The Parties |
---|---|---|---|---|---|
TTP2514 | (Sept 24) | GB Railfreight | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2024/25 | ||
TTP2513 | (Sept 24) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2024/25 | ||
TTP2512 | (Sept 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2024/25 | ||
TTP2511 | (Sept 24) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2024/25 | ||
TTP2510 | (Sept 24) | Transport UK East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2024/25 | ||
TTP2509 | (Sept 24) | GB Railfreight | Network Rail’s decisions regarding late notice access in Week 23, 2024 (settled out of court) | ||
TTP2508 | (Aug 24) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 39, 40 & 41, 2025 | ||
TTP2507 | (Aug 24) | GB Railfreight | Network Rail’s decisions regarding late notice access in Weeks 42 & 43, 2025 | ||
TTP2506 | (Aug 24) | London North Eastern Railway | Network Rail’s decisions regarding late notice access in Weeks 42 & 43, 2025 | ||
TTP2505 | (Aug 24) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 42 & 43, 2025 | ||
TTP2504 | (Aug 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2024/25 | ||
TTP2503 | (Aug 24) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2024/25 (settled out of court) | ||
TTP2502 | (Aug 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2024/25 | ||
TTP2501 | (Aug 24) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2024/25 | ||
TTP2500 | (Aug 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2025, Version 4 | ||
TTP2499 | (July 24) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2025, Version 4 | ||
TTP2498 | (Aug 24) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2497 | (Aug 24) | ScotRail Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2496 | (Aug 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2495 | (Aug 24) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2494 | (Aug 24) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2493 | (Aug 24) | Caledonian Sleeper | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2492 | (Aug 24) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2491 | (Aug 24) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2490 | (Aug 24) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2489 | (Aug 24) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2488 | (Aug 24) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2487 | (Aug 24) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2486 | (July 24) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2485 | (July 24) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2484 | (July 24) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2025, Version 4 | ||
TTP2483 | (July 24) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 21 to 30, 2024 (settled out of court) | ||
TTP2482 | (July 24) | Abellio East Anglia | Network Rail’s decisions regarding amendments to Section 4 in 2024 and 2025 | ||
TTP2481 | (July 24) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2024/25 (settled out of court) | ||
TTP2480 | (July 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2024/25 | ||
TTP2479 | (July 24) | Caledonian Sleeper | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2024/25 | ||
TTP2478 | (July 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2024/25 | ||
TTP2477 | (July 24) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2024/25 | ||
TTP2476 | (July 24) | GB Railfreight | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2024/25 | ||
TTP2475 | (July 24) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2024/25 | ||
TTP2474 | (July 24) | XC Trains | Network Rail’s decisions regarding the New Working Timetable Publication for 2025 (settled out of court) | ||
TTP2473 | (July 24) | GB Railfreight | Network Rail’s decisions regarding the New Working Timetable Publication for 2025 | ||
TTP2472 | (July 24) | TfW Rail Services | Network Rail’s decisions regarding the New Working Timetable Publication for 2025 | ||
TTP2471 | (July 24) | Heathrow Express | Network Rail's decisions in relation to the Timetable Offer for Week 27 (settled out of court) | ||
TTP2470 | (July 24) | Heathrow Express | Network Rail's decisions in relation to the Timetable Offer for Week 26 (settled out of court) | ||
TTP2469 | (July 24) | GB Railfreight | Network Rail's rejection of a Train Operator Variation Request (settled out of court) | ||
TTP2468 | 31.07.24 | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding Removal of Train Slots from the Working Timetable | ||
TTP2467 | (June 24) | Freightliner | Network Rail's decisions in relation to the Timetable Offer for Week 25 (settled out of court) | ||
TTP2466 | (June 24) | First Greater Western | Network Rail's decisions in relation to capacity allocation in Week 32, 2024 (settled out of court) | ||
TTP2465 | (June 24) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 (settled out of court) | ||
TTP2464 | (June 24) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 | ||
TTP2463 | (June 24) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 | ||
TTP2462 | (June 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 | ||
TTP2461 | (June 24) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 | ||
TTP2460 | (June 24) | Caledonian Sleeper | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 | ||
TTP2459 | (June 24) | GB Railfreight | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 | ||
TTP2458 | (June 24) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 | ||
TTP2457 | (June 24) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2024/25 | ||
TTP2456 | 01.07.24 | First Greater Western | Network Rail's decisions in relation to capacity allocation in Week 31, 2024 | ||
TTP2455 | 01.07.24 | First Greater Western | Network Rail's decisions in relation to capacity allocation in Week 29, 2024 | ||
TTP2454 | 01.07.24 | First Greater Western | Network Rail's decisions in relation to capacity allocation in Week 25, 2024 | ||
TTP2453 | 01.07.24 | First Greater Western | Network Rail's decisions in relation to capacity allocation for HS2 access in 2024 | ||
TTP2452 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 32, 2024 (settled out of court) | ||
TTP2451 | (May 24) | MTR Corporation (Crossrail) | Network Rail's decisions in relation to the Timetable Offer for Week 18 (settled out of court) | ||
TTP2450 | (May 24) | GB Railfreight | Network Rail’s decisions regarding amended Timetable Planning Rules (Finsbury Park) | ||
TTP2449 | (May 24) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2023/24 | ||
TTP2448 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2023/24 | ||
TTP2447 | (May 24) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2023/24 (settled out of court) | ||
TTP2446 | (May 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2023/24 (settled out of court) | ||
TTP2445 | (May 24) | TfW Rail Services | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2023/24 | ||
TTP2444 | (May 24) | GB Railfreight | Network Rail’s decisions regarding amended access in Week 40, 2024 | ||
TTP2443 | (May 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2023/24 | ||
TTP2442 | (May 24) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2023/24 | ||
TTP2441 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 36, 2024 (settled out of court) | ||
TTP2440 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 35, 2024 (settled out of court) | ||
TTP2439 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 33, 2024 (settled out of court) | ||
TTP2438 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding late notice access in Week 30, 2024 (settled out of court) | ||
TTP2437 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding late notice access in Week 29, 2024 (settled out of court) | ||
TTP2436 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding late notice access in Week 29, 2024 (settled out of court) | ||
TTP2435 | (May 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 34, 2024 | ||
TTP2434 | (May 24) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 04, 2025 | ||
TTP2433 | (May 24) | GB Railfreight | Network Rail’s decisions regarding amended access in Week 24, 2024 | ||
TTP2432 | (May 24) | GB Railfreight | Network Rail’s decisions regarding amended access in Week 04, 2025 | ||
TTP2431 | (Apr 24) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 33, 2024 (settled out of court) | ||
TTP2430 | (Apr 24) | DB Cargo (UK) | Network Rail’s decisions regarding late notice access in Week 27, 2024 (settled out of court) | ||
TTP2429 | (Apr 24) | TfW Rail Services | Network Rail’s decisions regarding late notice access in Week 27, 2024 (settled out of court) | ||
TTP2428 | (Apr 24) | TfW Rail Services | Network Rail’s decisions regarding amended access in Week 33, 2024 (settled out of court) | ||
TTP2427 | (Apr 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2023/24 (settled out of court) | ||
TTP2426 | (Apr 24) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2023/24 | ||
TTP2425 | (Apr 24) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2023/24 (settled out of court) | ||
TTP2424 | (Apr 24) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2023/24 (settled out of court) | ||
TTP2423 | (Apr 24) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2023/24 (settled out of court) | ||
TTP2422 | (Apr 24) | DB Cargo (UK) | Network Rail’s decisions regarding late notice changes to Section 4 of the 2025 EAS (settled out of court) | ||
TTP2421 | (Apr 24) | DB Cargo (UK) | Network Rail’s decisions regarding late notice changes to Section 4 of the 2024 EAS (settled out of court) | ||
TTP2420 | (Apr 24) | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP2419 | (Apr 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Weeks 29-32, 2024 (settled out of court) | ||
TTP2418 | (Mar 24) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2023/24 (settled out of court) | ||
TTP2417 | (Mar 24) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2023/24 (settled out of court) | ||
TTP2416 | (Mar 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2023/24 (settled out of court) | ||
TTP2415 | (Mar 24) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2023/24 (settled out of court) | ||
TTP2414 | (Mar 24) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2023/24 (settled out of court) | ||
TTP2413 | (Mar 24) | GB Railfreight | Network Rail’s decisions regarding late notice access in Week 18, 2024 (settled out of court) | ||
TTP2412 | (Mar 24) | XC Trains | Network Rail’s decisions regarding late notice access in Week 18, 2024 (settled out of court) | ||
TTP2411 | (Mar 24) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2025, Version 2 (settled out of court) | ||
TTP2410 | (Mar 24) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2025, Version 2 (settled out of court) | ||
TTP2409 | (Mar 24) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2025, Version 2 | ||
TTP2408 | (Mar 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2025, Version 2 (settled out of court) | ||
TTP2407 | (Mar 24) | Transpennine Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2406 | (Mar 24) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2405 | (Mar 24) | First Trenitalia West Coast Rail | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2404 | (Mar 24) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2403 | (Mar 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2402 | (Mar 24) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2401 | (Mar 24) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2400 | (Mar 24) | Caledonian Sleeper | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2399 | (Mar 24) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2398 | (Mar 24) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2397 | (Mar 24) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2396 | (Mar 24) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2395 | (Mar 24) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2394 | (Feb 24) | ScotRail Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2393 | (Feb 24) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2392 | (Feb 24) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2391 | (Feb 24) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 (settled out of court) | ||
TTP2390 | (Feb 24) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2025, Version 2 | ||
TTP2389 | (Feb 24) | Northern Trains | Network Rail’s decisions regarding late notice access in Weeks 23 and 25 to 29, 2024 (settled out of court) | ||
TTP2388 | (Feb 24) | GB Railfreight | Network Rail’s decisions regarding late notice access in Week 51 2024 (settled out of court) | ||
TTP2387 | (Feb 24) | XC Trains | Network Rail’s decisions regarding amended access in Week 29, 2024 (settled out of court) | ||
TTP2386 | (Feb 24) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2023/24 (settled out of court) | ||
TTP2385 | (Feb 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2023/24 (settled out of court) | ||
TTP2384 | (Feb 24) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2023/24 (settled out of court) | ||
TTP2383 | (Feb 24) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2023/24 (settled out of court) | ||
TTP2382 | (Feb 24) | XC Trains | Network Rail’s decisions regarding late notice access in Week 09 2024 (settled out of court) | ||
TTP2381 | (Feb 24) | TfW Rail Services | Network Rail’s decisions regarding late notice access with immediate effect, Week 43 2024 (settled out of court) | ||
TTP2380 | (Feb 24) | GB Railfreight | Network Rail’s decisions regarding amended access in Week 04, 2025 | ||
TTP2379 | (Feb 24) | GB Railfreight | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP2378 | (Jan 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding late notice access in Week 52, 2023/24 (settled out of court) | ||
TTP2377 | (Jan 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding late notice access in Week 51, 2023/24 (settled out of court) | ||
TTP2376 | (Jan 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding late notice access in Week 50, 2023/24 (settled out of court) | ||
TTP2375 | (Jan 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding late notice access in Week 49, 2023/24 (settled out of court) | ||
TTP2374 | (Jan 24) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2023/24 (settled out of court) | ||
TTP2373 | (Jan 24) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2023/24 (settled out of court) | ||
TTP2372 | (Jan 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2023/24 (settled out of court) | ||
TTP2371 | (Jan 24) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2023/24 (settled out of court) | ||
TTP2370 | (Jan 24) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2023/24 (settled out of court) | ||
TTP2369 | (Jan 24) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2023/24 (settled out of court) | ||
TTP2368 | (Jan 24) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2024 (settled out of court) | ||
TTP2367 | (Jan 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2024 (settled out of court) | ||
TTP2366 | (Jan 24) | TfW Rail Services | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2024 (settled out of court) | ||
TTP2365 | (Jan 24) | First Greater Western | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2024 (settled out of court) | ||
TTP2364 | (Jan 24) | GB Railfreight | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2024 (settled out of court) | ||
TTP2363 | (Jan 24) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2023/24 (settled out of court) | ||
TTP2362 | (Jan 24) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2023/24 (settled out of court) | ||
TTP2361 | (Dec 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2023/24 (settled out of court) | ||
TTP2360 | (Dec 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2023/24 (settled out of court) | ||
TTP2359 | (Jan 24) | TfW Rail Services | Network Rail’s decisions regarding amended access in Week 43, 2025 (settled out of court) | ||
TTP2358 | (Jan 24) | First Greater Western | Network Rail’s decisions regarding amended access in Week 52, 2025 | ||
TTP2357 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 18, 2024 (settled out of court) | ||
TTP2356 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 02, 2025 (settled out of court) | ||
TTP2355 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 32, 2024 (settled out of court) | ||
TTP2354 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 52, 2025 (settled out of court) | ||
TTP2353 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 43, 2025 (settled out of court) | ||
TTP2352 | (Dec 23) | GB Railfreight | Network Rail’s decisions regarding amended access in Week 18, 2024 (settled out of court) | ||
TTP2351 | (Dec 23) | Northern Trains | Network Rail’s decisions regarding amended access in Week 20, 2024 (settled out of court) | ||
TTP2350 | (Dec 23) | TfW Rail Services | Network Rail’s decisions regarding amended access in Week 36, 2024 (settled out of court) | ||
TTP2349 | (Dec 23) | TfW Rail Services | Network Rail’s decisions regarding amended access in Week 33, 2024 (settled out of court) | ||
TTP2348 | (Dec 23) | TfW Rail Services | Network Rail’s decisions regarding amended access in Week 26, 2024 (settled out of court) | ||
TTP2347 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 34, 2024 (settled out of court) | ||
TTP2346 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 33, 2024 (settled out of court) | ||
TTP2345 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 48, 2025 (settled out of court) | ||
TTP2344 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 47, 2025 (settled out of court) | ||
TTP2343 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 43, 2025 (settled out of court) | ||
TTP2342 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 42, 2025 (settled out of court) | ||
TTP2341 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 41, 2025 (settled out of court) | ||
TTP2340 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 37, 2024 (settled out of court) | ||
TTP2339 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 35 and 36, 2024 (settled out of court) | ||
TTP2338 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 34, 2024 (settled out of court) | ||
TTP2337 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 33, 2024 (settled out of court) | ||
TTP2336 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 32, 2024 (settled out of court) | ||
TTP2335 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 28, 2024 (settled out of court) | ||
TTP2334 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 27, 2024 (settled out of court) | ||
TTP2333 | (Dec 23) | DB Cargo (UK) | Network Rail’s decisions regarding amended access in Week 26, 2024 (settled out of court) | ||
TTP2332 | (Dec 23) | First Greater Western | Network Rail’s decisions regarding amended access in Week 34, 2024 (settled out of court) | ||
TTP2331 | (Nov 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2023/24 (settled out of court) | ||
TTP2330 | (Nov 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2023/24 (settled out of court) | ||
TTP2329 | (Nov 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2023/24 (settled out of court) | ||
TTP2328 | (Nov 23) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 34, 2023/24 (settled out of court) | ||
TTP2327 | (Nov 23) | Transpennine Trains | Network Rail’s decisions regarding late notice access in Week 05, 2023/24 (settled out of court) | ||
TTP2326 | (Nov 23) | DB Cargo (UK) | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP2325 | (Nov 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2023/24 (settled out of court) | ||
TTP2324 | (Nov 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2023/24 (settled out of court) | ||
TTP2323 | (Oct 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2023/24 (settled out of court) | ||
TTP2322 | (Oct 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2023/24 (settled out of court) | ||
TTP2321 | (Oct 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2023/24 (settled out of court) | ||
TTP2320 | 15.11.23 15.02.24 | Freightliner | Network Rail's decisions in relation to the Timetable Offer for Week 40 | ||
TTP2319 | (Oct 23) | GB Railfreight | Network Rail’s decisions regarding a late notice TSR in 2023/24 (settled out of court) | ||
TTP2318 | 15.11.23 15.02.24 | GB Railfreight | Network Rail's decisions in relation to the Timetable Offer for Week 40 | ||
TTP2317 | (Oct 23) | First Greater Western | Network Rail’s decisions regarding late notice access in Week 45, 2023/24 (settled out of court) | ||
TTP2316 | (Oct 23) | Heathrow Express | Network Rail's Old Oak Common Possession Strategy Notice 2023 | ||
TTP2315 | (Oct 23) | First Greater Western | Network Rail's Old Oak Common Possession Strategy Notice 2023 | ||
TTP2314 | (Oct 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2023/24 (settled out of court) | ||
TTP2313 | (Oct 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2023/24 (settled out of court) | ||
TTP2312 | (Oct 23) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2023/24 (settled out of court) | ||
TTP2311 | (Oct 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2023/24 (settled out of court) | ||
TTP2310 | (Sept 23) | GB Railfreight | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP2309 | (Sept 23) | GB Railfreight | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP2308 | (Sept 23) | XC Trains | Network Rail’s decisions regarding late notice access in Week 48, 2023/24 (settled out of court) | ||
TTP2307 | (Sept 23) | Heathrow Express | Network Rail's decisions in relation to the Timetable Offer for Week 36 (settled out of court) | ||
TTP2306 | (Sept 23) | Heathrow Express | Network Rail's decisions in relation to capacity allocation in Weeks 42, 44 and 46 (settled out of court) | ||
TTP2305 | (Sept 23) | Abellio East Anglia | Network Rail’s decisions regarding late notice access in Weeks 41, 42, 46, 47 & 48, 2023/24 (settled out of court) | ||
TTP2304 | (Sept 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2023/24 (settled out of court) | ||
TTP2303 | (Sept 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2023/24 (settled out of court) | ||
TTP2302 | (Sept 23) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2023/24 (settled out of court) | ||
TTP2301 | (Sept 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2023/24 (settled out of court) | ||
TTP2300 | (Sept 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2023/24 (settled out of court) | ||
TTP2299 | (Sept 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2023/24 (settled out of court) | ||
TTP2298 | (Aug 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 41-45, 2023/24 (settled out of court) | ||
TTP2297 | (Aug 23) | XC Trains | Network Rail’s decisions regarding late notice access in Week 48, 2023/24 (settled out of court) | ||
TTP2296 | (Aug 23) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2024, Version 4 (settled out of court) | ||
TTP2295 | (Aug 23) | XC Trains | Network Rail’s Timetable Planning Rules decisions for 2024, Version 4 (settled out of court) | ||
TTP2294 | (Aug 23) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2024, Version 4 (settled out of court) | ||
TTP2293 | (Aug 23) | Abellio East Anglia | Network Rail’s Timetable Planning Rules decisions for 2024, Version 4 (settled out of court) | ||
TTP2292 | (Aug 23) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2024, Version 4 (settled out of court) | ||
TTP2291 | (Aug 23) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2024, Version 4 (settled out of court) | ||
TTP2290 | (Aug 23) | Abellio East Anglia | Network Rail’s decisions regarding late notice access in Week 47, 2023/24 (setlled out of court) | ||
TTP2289 | (Aug 23) | Northern Trains | Network Rail’s decisions regarding amended access in Weeks 51 and 52, 2024 (settled out of court) | ||
TTP2288 | (Aug 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2023/24 (settled out of court) | ||
TTP2287 | (Aug 23) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2023/24 (settled out of court) | ||
TTP2286 | (Aug 23) | Heathrow Express | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2023/24 (settled out of court) | ||
TTP2285 | (Aug 23) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2023/24 (settled out of court) | ||
TTP2284 | (Aug 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2023/24 (settled out of court) | ||
TTP2283 | (Aug 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2023/24 (settled out of court) | ||
TTP2282 | (Aug 23) | Arriva Rail London | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2023/24 (settled out of court) | ||
TTP2281 | (Aug 23) | ScotRail Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2280 | (Aug 23) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2279 | (Aug 23) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2278 | (Aug 23) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2277 | (Aug 23) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2276 | (Aug 23) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2275 | (Aug 23) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2274 | (Aug 23) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2273 | (Aug 23) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2272 | (Aug 23) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2271 | (Aug 23) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2270 | (Aug 23) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2269 | (Aug 23) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2268 | (Aug 23) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 4 (settled out of court) | ||
TTP2267 | (July 23) | XC Trains | Network Rail’s decisions regarding a capacity study in Weeks 51/52, 2023/24 (settled out of court) | ||
TTP2266 | (July 23) | XC Trains | Network Rail’s decisions regarding a capacity study in Weeks 39/40, 2023/24 (settled out of court) | ||
TTP2265 | (July 23) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding the New Working Timetable Publication for 2024 (settled out of court) | ||
TTP2264 | (July 23) | XC Trains | Network Rail’s decisions regarding the New Working Timetable Publication for 2024 (settled out of court) | ||
TTP2263 | (July 23) | GB Railfreight | Network Rail’s decisions regarding the New Working Timetable Publication for 2024 (settled out of court) | ||
TTP2262 | (July 23) | Caledonian Sleeper | Network Rail’s decisions regarding the New Working Timetable Publication for 2024 (settled out of court) | ||
TTP2261 | (July 23) | DB Cargo (UK) | Network Rail’s decisions regarding the New Working Timetable Publication for 2024 (settled out of court) | ||
TTP2260 | 09.08.23 | First Greater Western | Network Rail’s decisions regarding late notice access in Week 37, 2023/24 | ||
TTP2259 | (July 23) | XC Trains | Network Rail’s decisions regarding a late notice cancellation in Week 21, 2022/23 (settled out of court) | ||
TTP2258 | (July 23) | Arriva Rail London | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2257 | (July 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2256 | (July 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2255 | (July 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2254 | (July 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2253 | (July 23) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2252 | (July 23) | TfW Rail Services | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2251 | 09.08.23 | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24. This was partially determined, with the remaining items (settled out of court) | ||
TTP2250 | (July 23) | Northern Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2249 | (July 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2248 | (July 23) | GB Railfreight | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2023/24 (settled out of court) | ||
TTP2247 | (July 23) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding late notice access in Week 33, 2022/23 (settled out of court) | ||
TTP2246 | (July 23) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding late notice access in Week 29, 2022/23 (settled out of court) | ||
TTP2245 | 09.08.23 | Heathrow Express | Network Rail’s decisions regarding late notice access in Week 33, 2022/23 | ||
TTP2244 | 09.08.23 | Heathrow Express | Network Rail’s decisions regarding late notice access in Week 29, 2022/23 | ||
TTP2243 | 09.08.23 | First Greater Western | Network Rail’s decisions regarding late notice access in Week 33, 2022/23 | ||
TTP2242 | (June 23) | XC Trains | Network Rail’s amended decision in Weeks 41-45, 2024 (settled out of court) | ||
TTP2241 | (June 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 28-32, 2022/23 (settled out of court) | ||
TTP2240 | (June 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 23-27, 2022/23 (settled out of court) | ||
TTP2239 | (June 23) | Abellio East Anglia | Network Rail’s amended decision in Weeks 45-48, 2024 (settled out of court) | ||
TTP2238 | (June 23) | XC Trains | Network Rail’s amended decision in Weeks 41-45, 2024 (settled out of court) | ||
TTP2237 | (June 23) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2023/24 (settled out of court) | ||
TTP2236 | (June 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2023/24 (settled out of court) | ||
TTP2235 | (June 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2023/24 (settled out of court) | ||
TTP2234 | (June 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2023/24 (settled out of court) | ||
TTP2233 | (June 23) | First MTR South Western Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2023/24 (settled out of court) | ||
TTP2232 | (June 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2023/24 (settled out of court) | ||
TTP2231 | (June 23) | XC Trains | Network Rail’s amended decision in Week 51, 2024 (settled out of court) | ||
TTP2230 | (May 23) | DB Cargo (UK) | Network Rail’s amended decision in Week 40, 2024 (settled out of court) | ||
TTP2229 | (May 23) | DB Cargo (UK) | Network Rail’s decisions regarding late notice access in Week 22, 2022/23 (settled out of court) | ||
TTP2228 | (May 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 28-32, 2022/23 (settled out of court) | ||
TTP2227 | (May 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 23-27, 2022/23 (settled out of court) | ||
TTP2226 | (May 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 18-22, 2022/23 (settled out of court) | ||
TTP2225 | (May 23) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2022/23 (settled out of court) | ||
TTP2224 | (May 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2022/23 (settled out of court) | ||
TTP2223 | (May 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2022/23 (settled out of court) | ||
TTP2222 | (May 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2022/23 (settled out of court) | ||
TTP2221 | (May 23) | TfW Rail Services | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2022/23 (settled out of court) | ||
TTP2220 | (May 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2022/23 (settled out of court) | ||
TTP2219 | (May 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2022/23 (settled out of court) | ||
TTP2218 | (May 23) | DB Cargo (UK) | Network Rail's decision regarding the timetable offer in Week 16, 2023 (settled out of court) | ||
TTP2217 | (May 23) | XC Trains | Network Rail’s amended decisions in Weeks 26-30, 2023 (settled out of court) | ||
TTP2216 | (Apr 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2022/23 (settled out of court) | ||
TTP2215 | (Apr 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2022/23 (settled out of court) | ||
TTP2214 | (Apr 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2022/23 (settled out of court) | ||
TTP2213 | (Apr 23) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2022/23 (settled out of court) | ||
TTP2212 | (Apr 23) | TfW Rail Services | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2022/23 (settled out of court) | ||
TTP2211 | (Apr 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2022/23 (settled out of court) | ||
TTP2210 | (Apr 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2022/23 (settled out of court) | ||
TTP2209 | (Apr 23) | MTR Corporation (Crossrail) | Network Rail’s amended decision in Week 36, 2023 (settled out of court) | ||
TTP2208 | (Apr 23) | Heathrow Express | Network Rail’s amended decision in Week 36, 2023 (settled out of court) | ||
TTP2207 | 10.05.23 | Heathrow Express | Network Rail's decision regarding the timetable offer in Week 11, 2023 | ||
TTP2206 | (Mar 23) | XC Trains | Network Rail’s amended decision in Weeks 34 and 35, 2023 (settled out of court) | ||
TTP2205 | (Mar 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2022/23 (settled out of court) | ||
TTP2204 | (Mar 23) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2022/23 (settled out of court) | ||
TTP2203 | (Mar 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2022/23 (settled out of court) | ||
TTP2202 | (Mar 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2022/23 (settled out of court) | ||
TTP2201 | (Mar 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2022/23 (settled out of court) | ||
TTP2200 | (Mar 23) | GB Railfreight | Network Rail’s decisions regarding late notice access in Week 51, 2022/23 (settled out of court) | ||
TTP2199 | (Mar 23) | XC Trains | Network Rail’s decisions regarding late notice TSR in Week 03, 2022/23 | ||
TTP2198 | (Mar 23) | GB Railfreight | Network Rail’s decisions regarding late notice access in Week 12, 2022/23 (settled out of court) | ||
TTP2197 | (Mar 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 24-28, 2022/23 (settled out of court) | ||
TTP2196 | (Mar 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 18-22, 2022/23 (settled out of court) | ||
TTP2195 | (Mar 23) | XC Trains | Network Rail’s decisions regarding late notice access in Weeks 12-16, 2022/23 (settled out of court) | ||
TTP2194 | (Mar 23) | DB Cargo (UK) | Network Rail’s decisions regarding late notice access in Week 51, 2022/23 (settled out of court) | ||
TTP2193 | (Mar 23) | GB Railfreight | Network Rail's decision regarding the timetable offer in Week 02, 2023 (settled out of court) | ||
TTP2192 | (Mar 23) | GB Railfreight | Network Rail's decision regarding the timetable offer in Week 01, 2023 (settled out of court) | ||
TTP2191 | (Mar 23) | GB Railfreight | Network Rail’s decisions regarding late notice access in Week 50, 2022/23 (settled out of court) | ||
TTP2190 | (Feb 23) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 35, 2022/23 (settled out of court) | ||
TTP2189 | (Feb 23) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 34, 2022/23 (settled out of court) | ||
TTP2188 | (Feb 23) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 31, 2022/23 (settled out of court) | ||
TTP2187 | 19.04.23 | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2024, Version 2 | ||
TTP2186 | (Feb 23) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2024, Version 2 (settled out of court) | ||
TTP2185 | (Feb 23) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2024, Version 2 (settled out of court) | ||
TTP2184 | (Feb 23) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2183 | (Feb 23) | First Trenitalia West Coast Rail | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2182 | (Feb 23) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2181 | (Feb 23) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2180 | (Feb 23) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2179 | (Feb 23) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2178 | (Feb 23) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2177 | (Feb 23) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2176 | (Feb 23) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2175 | (Feb 23) | Freightliner & Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2174 | (Feb 23) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2173 | (Feb 23) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2172 | (Feb 23) | ScotRail Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2171 | (Feb 23) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2170 | (Feb 23) | Heathrow Express | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2169 | (Feb 23) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2168 | (Feb 23) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2167 | (Feb 23) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2024, Version 2 (settled out of court) | ||
TTP2166 | (Feb 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2022/23 (settled out of court) | ||
TTP2165 | (Feb 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2022/23 (settled out of court) | ||
TTP2164 | (Feb 23) | Northern Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2022/23 (settled out of court) | ||
TTP2163 | (Feb 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2022/23 (settled out of court) | ||
TTP2162 | (Feb 23) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2022/23 (settled out of court) | ||
TTP2161 | (Feb 23) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2022/23 (settled out of court) | ||
TTP2160 | (Feb 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2022/23 (settled out of court) | ||
TTP2159 | (Jan 23) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2022/23 (settled out of court) | ||
TTP2158 | (Jan 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2022/23 (settled out of court) | ||
TTP2157 | (Jan 23) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2022/23 (settled out of court) | ||
TTP2156 | (Jan 23) | Arriva Rail London | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2022/23 (settled out of court) | ||
TTP2155 | (Jan 23) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2022/23 (settled out of court) | ||
TTP2154 | (Jan 23) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2022/23 (settled out of court) | ||
TTP2153 | (Jan 23) | DB Cargo (UK) | Network Rail’s late notice decisions in Weeks 47, 49 & 52, 2023 (settled out of court) | ||
TTP2152 | (Jan 23) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2022/23 (settled out of court) | ||
TTP2151 | (Jan 23) | Arriva Rail London | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2022/23 (settled out of court) | ||
TTP2150 | (Dec 22) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2022/23 (settled out of court) | ||
TTP2149 | (Dec 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2022/23 (settled out of court) | ||
TTP2148 | (Dec 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2022/23 (settled out of court) | ||
TTP2147 | (Dec 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2022/23 (settled out of court) | ||
TTP2146 | (Dec 22) | Serco Caledonian Sleepers | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2023 (settled out of court) | ||
TTP2145 | (Dec 22) | GB Railfreight | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2023 (settled out of court) | ||
TTP2144 | (Dec 22) | TfW Rail Services | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2023 (settled out of court) | ||
TTP2143 | (Dec 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2023 (settled out of court) | ||
TTP2142 | (Dec 22) | First Greater Western | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2023 (settled out of court) | ||
TTP2141 | (Dec 22) | XC Trains | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2023 (settled out of court) | ||
TTP2140 | (Dec 22) | DB Cargo (UK) | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2023 (settled out of court) | ||
TTP2139 | (Dec 22) | Abellio East Anglia | Network Rail’s late notice decisions in Weeks 45, 47-03, 2023 (settled out of court) | ||
TTP2138 | (Dec 22) | Heathrow Express | Network Rail's decision regarding the timetable offer in Week 46, 2023 (settled out of court) | ||
TTP2137 | (Dec 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2022/23 (settled out of court) | ||
TTP2136 | (Dec 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2022/23 (settled out of court) | ||
TTP2135 | (Dec 22) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2022/23 (settled out of court) | ||
TTP2134 | (Nov 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2022/23 (settled out of court) | ||
TTP2133 | (Nov 22) | DB Cargo (UK) | Network Rail’s late notice decisions in Week 52, 2023 (settled out of court) | ||
TTP2132 | (Nov 22) | XC Trains | Network Rail’s late notice decisions in Weeks 30-34, 2023 (settled out of court) | ||
TTP2131 | (Nov 22) | XC Trains | Network Rail’s late notice decisions in Weeks 24-28, 2023 (settled out of court) | ||
TTP2130 | (Nov 22) | XC Trains | Network Rail’s late notice decisions in in Weeks 18-22, 2023 (settled out of court) | ||
TTP2129 | (Nov 22) | XC Trains | Network Rail’s late notice decisions in in Weeks 12-16, 2023 (settled out of court) | ||
TTP2128 | (Nov 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2022/23 (settled out of court) | ||
TTP2127 | (Nov 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2022/23 (settled out of court) | ||
TTP2126 | (Nov 22) | XC Trains | Network Rail’s late notice decision in Weeks 06-10, 2023 (settled out of court) | ||
TTP2125 | (Nov 22) | XC Trains | Network Rail’s late notice decision in Weeks 01-04, 2023 (settled out of court) | ||
TTP2124 | (Nov 22) | XC Trains | Network Rail’s late notice decision in Week 04, 2023 (settled out of court) | ||
TTP2123 | (Nov 22) | GB Railfreight | Network Rail’s late notice decision in Week 52, 2023 (settled out of court) | ||
TTP2122 | (Nov 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s late notice decision in Week 04, 2023 (settled out of court) | ||
TTP2121 | (Nov 22) | GB Railfreight | Network Rail’s amended decision in Week 19, 2023 (settled out of court) | ||
TTP2120 | (Nov 22) | Freightliner Heavy Haul | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP2119 | (Nov 22) | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding the timetable offer in Week 39, 2022 (settled out of court) | ||
TTP2118 | (Nov 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2022/23 (settled out of court) | ||
TTP2117 | (Nov 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2022/23 (settled out of court) | ||
TTP2116 | (Oct 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2022/23 (settled out of court) | ||
TTP2115 | (Oct 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2022/23 (settled out of court) | ||
TTP2114 | (Oct 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2022/23 (settled out of court) | ||
TTP2113 | (Oct 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2022/23 (settled out of court) | ||
TTP2112 | (Oct 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2022/23 (settled out of court) | ||
TTP2111 | (Oct 22) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2022/23 (settled out of court) | ||
TTP2110 | (Oct 22) | First MTR South Western Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2022/23 (settled out of court) | ||
TTP2109 | (Sept 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2022/23 (settled out of court) | ||
TTP2108 | (Sept 22) | Abellio East Anglia | Network Rail’s late notice decision in Weeks 39, 41, 42 and 04 2023 (settled out of court) | ||
TTP2107 | (Sept 22) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2023, Version 4.1 (settled out of court) | ||
TTP2106 | (Sept 22) | Abellio East Anglia | Network Rail’s late notice decision in Weeks 39 and 40, 2023 (settled out of court) | ||
TTP2105 | (Sept 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2022/23 (settled out of court) | ||
TTP2104 | (Sept 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2022/23 (settled out of court) | ||
TTP2103 | (Sept 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2022/23 (settled out of court) | ||
TTP2102 | (Sept 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2022/23 (settled out of court) | ||
TTP2101 | (Sept 22) | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding the timetable offer in Week 30, 2022 (settled out of court) | ||
TTP2100 | (Aug 22) | XC Trains | Network Rail’s decisions regarding amended access in Week 02, 2022/23 (settled out of court) | ||
TTP2099 | (Aug 22) | London North Eastern Railway | Network Rail’s decisions regarding amended access in Week 02, 2022/23 (settled out of court) | ||
TTP2098 | (Aug 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding amended access in Week 41, 2022/23 (settled out of court) | ||
TTP2097 | (Aug 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2022/23 (settled out of court) | ||
TTP2096 | (Aug 22) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2022/23 (settled out of court) | ||
TTP2095 | (Aug 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2022/23 (settled out of court) | ||
TTP2094 | (Aug 22) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2022/23 (settled out of court) | ||
TTP2093 | (Aug 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2022/23 (settled out of court) | ||
TTP2092 | (Aug 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2022/23 (settled out of court) | ||
TTP2091 | (Aug 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2022/23 (settled out of court) | ||
TTP2090 | (Aug 22) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2023, Version 4. First hearing (Anglia matters) cancelled. Remaining matters scheduled for 03.11.22. Hearing two postponed and then withdrawn. | ||
TTP2089 | (Aug 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2023, Version 4. First hearing (Anglia matters) cancelled. Remaining matters scheduled for 03.11.22, then withdrawn before the hearing. | ||
TTP2088 | (Aug 22) | XC Trains | Network Rail’s Timetable Planning Rules decisions for 2023, Version 4 (settled out of court) | ||
TTP2087 | (Aug 22) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2023, Version 4 (settled out of court) | ||
TTP2086 | (Aug 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2085 | (Aug 22) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2084 | (Aug 22) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2083 | (Aug 22) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2082 | (Aug 22) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2081 | (Aug 22) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2080 | (Aug 22) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2079 | (Aug 22) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2078 | (Aug 22) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2077 | (Aug 22) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2076 | (Aug 22) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2075 | (Aug 22) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2074 | (Aug 22) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2073 | (July 22) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2023, Version 4 (settled out of court) | ||
TTP2072 | (Aug 22) | MTR Corporation (Crossrail) | Network Rail’s decisions regarding amended access in Week 06, 2022/23 (settled out of court) | ||
TTP2071 | (July 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding amended access in Week 47, 2022/23 (settled out of court) | ||
TTP2070 | (July 22) | GB Railfreight | Network Rail’s decisions regarding amended access in Week 47, 2022/23 (settled out of court) | ||
TTP2069 | (July 22) | Serco Caledonian Sleepers | Network Rail’s decisions regarding amended access in Week 47, 2022/23 (settled out of court) | ||
TTP2068 | (July 22) | First Greater Western | Network Rail’s decisions regarding the New Working Timetable Publication for 2023 (settled out of court) | ||
TTP2067 | (July 22) | DB Cargo (UK) | Network Rail’s decisions regarding the New Working Timetable Publication for 2023 (settled out of court) | ||
TTP2066 | (July 22) | Serco Caledonian Sleepers | Network Rail’s decisions regarding the New Working Timetable Publication for 2023 (settled out of court) | ||
TTP2065 | (July 22) | GB Railfreight | Network Rail’s decisions regarding the New Working Timetable Publication for 2023 (settled out of court) | ||
TTP2064 | (July 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding the New Working Timetable Publication for 2023 (settled out of court) | ||
TTP2063 | (July 22) | XC Trains | Network Rail’s decisions regarding the New Working Timetable Publication for 2023 (settled out of court) | ||
TTP2062 | (July 22) | Legge Infrastructure Services | Network Rail’s decisions regarding the New Working Timetable Publication for 2023 (settled out of court) | ||
TTP2061 | (July 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2022/23 (settled out of court) | ||
TTP2060 | (July 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2022/23 (settled out of court) | ||
TTP2059 | (July 22) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2022/23 (settled out of court) | ||
TTP2058 | (July 22) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2022/23 (settled out of court) | ||
TTP2057 | (July 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2022/23 (settled out of court) | ||
TTP2056 | (July 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2022/23 (settled out of court) | ||
TTP2055 | (June 22) | DB Cargo (UK) | Network Rail’s amended decision in Week 51, 2023 (settled out of court) | ||
TTP2054 | (June 22) | Abellio East Anglia | Network Rail’s late notice decision in Weeks 39 and 40, 2023 (settled out of court) | ||
TTP2053 | (June 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2022/23 (settled out of court) | ||
TTP2052 | (June 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2022/23 (settled out of court) | ||
TTP2051 | (June 22) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2022/23 (settled out of court) | ||
TTP2050 | (June 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2022/23 (settled out of court) | ||
TTP2049 | (June 22) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2022/23 (settled out of court) | ||
TTP2048 | (June 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2022/23 (settled out of court) | ||
TTP2047 | (May 22) | Northern Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2021/22 (settled out of court) | ||
TTP2046 | (May 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2021/22 | ||
TTP2045 | (May 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2021/22 (settled out of court) | ||
TTP2044 | (May 22) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2.2 (settled out of court) | ||
TTP2043 | (May 22) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2.2 (settled out of court) | ||
TTP2042 | (May 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2.2 (settled out of court) | ||
TTP2041 | (May 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2021/22 (settled out of court) | ||
TTP2040 | (May 22) | Abellio East Anglia | Network Rail’s late notice decision in Week 31, 2022 (settled out of court) | ||
TTP2039 | (Apr 22) | First Greater Western | Network Rail’s late notice decision in Week 26, 2022 (settled out of court) | ||
TTP2038 | (Apr 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s late notice decision in Week 12, 2022 (settled out of court) | ||
TTP2037 | (Apr 22) | GB Railfreight | Network Rail’s late notice decision in Week 12, 2022 (settled out of court) | ||
TTP2036 | (Apr 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2021/22 (settled out of court) | ||
TTP2035 | (Apr 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2021/22 (settled out of court) | ||
TTP2034 | (Apr 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2021/22 (settled out of court) | ||
TTP2033 | (Apr 22) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2021/22 (settled out of court) | ||
TTP2032 | (Apr 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2021/22 (settled out of court) | ||
TTP2031 | (Apr 22) | DB Cargo (UK) | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP2030 | (Mar 22) | Abellio East Anglia | Network Rail’s late notice decision in Week 12, 2022 (settled out of court) | ||
TTP2029 | (Mar 22) | XC Trains | Network Rail's rejection of a Train Operator Variation Request (settled out of court) | ||
TTP2028 | (Mar 22) | GB Railfreight | Network Rail’s decisions for the 2023 International Freight Capacity Notice (settled out of court) | ||
TTP2027 | (Mar 22) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2021/22 (settled out of court) | ||
TTP2026 | (Mar 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2021/22 (settled out of court) | ||
TTP2025 | (Mar 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2021/22 (settled out of court) | ||
TTP2024 | (Mar 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2021/22 (settled out of court) | ||
TTP2023 | (Mar 22) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2021/22 (settled out of court) | ||
TTP2022 | (Mar 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2021/22 (settled out of court) | ||
TTP2021 | (Feb 22) | GB Railfreight | Network Rail's decision regarding the timetable offer in Week 05, 2022 (settled out of court) | ||
TTP2020 | (Feb 22) | DB Cargo (UK) | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2 (settled out of court) | ||
TTP2019 | (Feb 22) | First Transpennine Express | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2 (settled out of court) | ||
TTP2018 | (Feb 22) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2 (settled out of court) | ||
TTP2017 | (Feb 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2 (settled out of court) | ||
TTP2016 | (Feb 22) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2 (settled out of court) | ||
TTP2015 | (Feb 22) | XC Trains | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2 (settled out of court) | ||
TTP2014 | (Feb 22) | First Greater Western | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2 (settled out of court) | ||
TTP2013 | (Feb 21) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2023, Version 2 (settled out of court) | ||
TTP2012 | (Feb 22) | First Trenitalia West Coast Rail | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2011 | (Feb 22) | First Transpennine Express | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2010 | (Feb 22) | Abellio Scotrail | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2009 | (Feb 22) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2008 | (Feb 22) | Grand Central Railway | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2007 | (Feb 22) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2006 | (Feb 22) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2005 | (Feb 22) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2004 | (Feb 22) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2003 | (Feb 22) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2002 | (Feb 22) | Freightliner & Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2001 | (Feb 22) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP2000 | (Feb 22) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP1999 | (Feb 22) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP1998 | (Feb 22) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP1997 | (Feb 22) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP1996 | (Feb 22) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP1995 | (Feb 22) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP1994 | (Feb 22) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2023, Version 2 (settled out of court) | ||
TTP1993 | (Feb 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2021/22 (settled out of court) | ||
TTP1992 | (Feb 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2021/22 (settled out of court) | ||
TTP1991 | (Feb 22) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2021/22 (settled out of court) | ||
TTP1990 | (Feb 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2021/22 (settled out of court) | ||
TTP1989 | (Feb 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2021/22 (settled out of court) | ||
TTP1988 | (Feb 22) | GB Railfreight | Network Rail's decision regarding the timetable offer in Week 04, 2022 (settled out of court) | ||
TTP1987 | (Feb 22) | GB Railfreight | Network Rail's decision regarding the timetable offer in Week 02, 2022 (settled out of court) | ||
TTP1986 | (Jan 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2021/22 (settled out of court) | ||
TTP1985 | (Jan 22) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2021/22 (settled out of court) | ||
TTP1984 | (Jan 22) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2021/22 (settled out of court) | ||
TTP1983 | (Jan 22) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2021/22 (settled out of court) | ||
TTP1982 | (Jan 22) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2021/22 (settled out of court) | ||
TTP1981 | (Jan 22) | TfW Rail Services | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2022 (settled out of court) | ||
TTP1980 | (Jan 22) | XC Trains | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2022 (settled out of court) | ||
TTP1979 | (Jan 22) | Freightliner Heavy Haul | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2022 (settled out of court) | ||
TTP1978 | (Jan 22) | First Greater Western | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2022 (settled out of court) | ||
TTP1977 | (Dec 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2021/22 (settled out of court) | ||
TTP1976 | (Dec 21) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2021/22 (settled out of court) | ||
TTP1975 | (Dec 21) | DB Cargo (UK) | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2022 (settled out of court) | ||
TTP1974 | (Dec 21) | DB Cargo (UK) | Network Rail's decision regarding the timetable offer in Week 47, 2022 (settled out of court) | ||
TTP1973 | (Dec 21) | GB Railfreight | Network Rail's decision regarding the timetable offer in Week 47, 2022 (settled out of court) | ||
TTP1972 | (Dec 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2021/22 (settled out of court) | ||
TTP1971 | (Dec 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2021/22 (settled out of court) | ||
TTP1970 | (Nov 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2021/22 (settled out of court) | ||
TTP1969 | (Nov 21) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2021/22 (settled out of court) | ||
TTP1968 | (Nov 21) | Abellio East Anglia | Late amendments to Weeks 10, 16, 22 & 30, 2022 (settled out of court) | ||
TTP1967 | (Nov 21) | Abellio East Anglia | Late amendments to Weeks 01-08, 10 & 11, 2022 (settled out of court) | ||
TTP1966 | (Nov 21) | Abellio East Anglia | Late amendments to Weeks 09-12, 2022 (settled out of court) | ||
TTP1965 | (Nov 21) | DB Cargo (UK) | Late amendments to Week 39, 2022 (settled out of court) | ||
TTP1964 | (Nov 21) | Abellio East Anglia | Late amendments to Weeks 45-52, 2022 (settled out of court) | ||
TTP1963 | (Nov 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2021/22 (settled out of court) | ||
TTP1962 | (Nov 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2021/22 (settled out of court) | ||
TTP1961 | (Nov 21) | First MTR South Western Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2021/22 (settled out of court) | ||
TTP1960 | (Oct 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2021/22 (settled out of court) | ||
TTP1959 | (Oct 21) | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP1958 | (Oct 21) | TfW Rail Services | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2021/22 (settled out of court) | ||
TTP1957 | (Oct 21) | GB Railfreight | Late amendments to Weeks 40-42, 2022 (settled out of court) | ||
TTP1956 | (Oct 21) | Freightliner & Freightliner Heavy Haul | Late amendments to Weeks 39-42, 2022 (settled out of court) | ||
TTP1955 | (Oct 21) | Freightliner & Freightliner Heavy Haul | Decisions in Weeks 24, 25 & 26, 2022 (settled out of court) | ||
TTP1954 | (Oct 21) | GB Railfreight | Amendments to Section 5 of the 2022 EAS (settled out of court) | ||
TTP1953 | (Oct 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2021/22 (settled out of court) | ||
TTP1952 | (Oct 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2021/22 (settled out of court) | ||
TTP1951 | (Oct 21) | TfW Rail Services | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2021/22 (settled out of court) | ||
TTP1950 | (Oct 21) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2021/22 (settled out of court) | ||
TTP1949 | (Oct 21) | First MTR South Western Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2021/22 (settled out of court) | ||
TTP1948 | (Sept 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2021/22 (settled out of court) | ||
TTP1947 | (Sept 21) | XC Trains | Network Rail’s late notice decision in Week 03, 2022 (settled out of court) | ||
TTP1946 | (Sept 21) | Abellio East Anglia | Network Rail’s late notice decision in Weeks 33, 34 & 38, 2021 (settled out of court) | ||
TTP1945 | (Sept 21) | DB Cargo (UK) | Network Rail’s decisions regarding the New Working Timetable Publication for 2022 (settled out of court) | ||
TTP1944 | (Sept 21) | Rail Operations Group | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP1943 | (Sept 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2021/22 (settled out of court) | ||
TTP1942 | (Sept 21) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2021/22 (settled out of court) | ||
TTP1941 | (Sept 21) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2021/22 (settled out of court) | ||
TTP1940 | (Sept 21) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2021/22 (settled out of court) | ||
TTP1939 | (Sept 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2021/22 (settled out of court) | ||
TTP1938 | (Aug 21) | Freightliner & Freightliner Heavy Haul | Network Rail’s decisions regarding the New Working Timetable Publication for 2022 (settled out of court) | ||
TTP1937 | (Aug 21) | GB Railfreight | Network Rail’s decisions regarding the New Working Timetable Publication for 2022 (settled out of court) | ||
TTP1936 | (Aug 21) | Arriva Rail London | Network Rail’s decisions regarding the New Working Timetable Publication for 2022 (settled out of court) | ||
TTP1935 | (Aug 21) | TfW Rail Services | Network Rail’s decisions regarding the New Working Timetable Publication for 2022 (settled out of court) | ||
TTP1934 | (Aug 21) | Rail Operations Group | Network Rail’s decisions regarding the New Working Timetable Publication for 2022 (settled out of court) | ||
TTP1933 | (Aug 21) | Abellio East Anglia | Network Rail’s late notice decision in Weeks 38, 39 & 40, 2021 (settled out of court) | ||
TTP1932 | (Aug 21) | Freightliner Heavy Haul | Network Rail’s decision regarding Week 25 (settled out of court) | ||
TTP1931 | (Aug 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2021/22 (settled out of court) | ||
TTP1930 | (Aug 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2021/22 (settled out of court) | ||
TTP1929 | (Aug 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2021/22 (settled out of court) | ||
TTP1928 | (Aug 21) | First MTR South Western Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2021/22 (settled out of court) | ||
TTP1927 | (Aug 21) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2021/22 (settled out of court) | ||
TTP1926 | (Aug 21) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2021/22 (settled out of court) | ||
TTP1925 | (Aug 21) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2021/22 (settled out of court) | ||
TTP1924 | (Aug 21) | Arriva Rail London | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4.1 (settled out of court) | ||
TTP1923 | (Aug 21) | GB Railfreight | Network Rail’s decision regarding Week 26 (settled out of court) | ||
TTP1922 | (July 21) | XC Trains | Network Rail’s late notice decision in Weeks 41-43, 2022 (settled out of court) | ||
TTP1921 | (July 21) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4 (settled out of court) | ||
TTP1920 | (July 21) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4 (settled out of court) | ||
TTP1919 | (July 21) | West Midlands Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4 (settled out of court) | ||
TTP1918 | (July 21) | Arriva Rail London | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4 (settled out of court) | ||
TTP1917 | (July 21) | London North Eastern Railway | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4 (settled out of court) | ||
TTP1916 | (July 21) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4 (settled out of court) | ||
TTP1915 | (July 21) | XC Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4 (settled out of court) | ||
TTP1914 | (July 21) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2022, Version 4 (settled out of court) | ||
TTP1913 | (July 21) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1912 | (July 21) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1911 | (July 21) | Abellio Scotrail | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1910 | (July 21) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1909 | (July 21) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1908 | (July 21) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1907 | (July 21) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1906 | (July 21) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1905 | (July 21) | Freightliner & Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1904 | (July 21) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1903 | (July 21) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1902 | (July 21) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1901 | (July 21) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1900 | (July 21) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1899 | (July 21) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2022, Version 4 (settled out of court) | ||
TTP1898 | (July 21) | DB Cargo (UK) | Amendments to Section 4 of the 2021 EAS (settled out of court) | ||
TTP1897 | (July 21) | First MTR South Western Trains | Late amendments to Section 4 of the 2021 EAS (settled out of court) | ||
TTP1896 | (July 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2021/22 (settled out of court) | ||
TTP1895 | (July 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2021/22 (settled out of court) | ||
TTP1894 | (July 21) | First MTR South Western Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2021/22 (settled out of court) | ||
TTP1893 | (July 21) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2021/22 (settled out of court) | ||
TTP1892 | (July 21) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2021/22 (settled out of court) | ||
TTP1891 | (July 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2021/22 (settled out of court) | ||
TTP1890 | (June 21) | Freightliner | Network Rail’s decision regarding Week 19 (settled out of court) | ||
TTP1889 | (June 21) | Freightliner & Freightliner Heavy Haul | Network Rail’s decision regarding Week 38 (settled out of court) | ||
TTP1888 | (June 21) | TfW Rail Services | Network Rail’s decisions regarding the revised Subsidiary Working Timetable Publication for 2021 (settled out of court) | ||
TTP1887 | (June 21) | First MTR South Western Trains | Network Rail’s decision regarding Week 31, 2021 (settled out of court) | ||
TTP1886 | (June 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2021/22 (settled out of court) | ||
TTP1885 | (June 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2021/22 (settled out of court) | ||
TTP1884 | (June 21) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2021/22 (settled out of court) | ||
TTP1883 | (June 21) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2021/22 (settled out of court) | ||
TTP1882 | (June 21) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2021/22 (settled out of court) | ||
TTP1881 | (June 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2021/22 (settled out of court) | ||
TTP1880 | 13.07.21 | GB Railfreight | Late amendments to Section 4 of the 2021 EAS | ||
TTP1879 | (May 21) | DB Cargo (UK) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2020/21 (settled out of court) | ||
TTP1878 | (May 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2020/21 (settled out of court) | ||
TTP1877 | (May 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2020/21 (settled out of court) | ||
TTP1876 | (May 21) | XC Trains | Network Rail’s late notice decision in Week 28, 2021 (settled out of court) | ||
TTP1875 | (May 21) | GB Railfreight | Network Rail’s decisions in Weeks 12 & 13, 2021 (settled out of court) | ||
TTP1874 | (Apr 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2020/21 (settled out of court) | ||
TTP1873 | (Apr 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2020/21 (settled out of court) | ||
TTP1872 | (Apr 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2020/21 (settled out of court) | ||
TTP1871 | (Apr 21) | XC Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2.1 - Western & Wales (settled out of court) | ||
TTP1870 | (Apr 21) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2.1 (settled out of court) | ||
TTP1869 | (Apr 21) | First MTR South Western Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2.1 (settled out of court) | ||
TTP1868 | (Apr 21) | Arriva Rail London | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2.1 (settled out of court) | ||
TTP1867 | (Mar 21) | XC Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2.1 (settled out of court) | ||
TTP1866 | (Mar 21) | Abellio East Anglia | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2.1 (settled out of court) | ||
TTP1865 | (Mar 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2020/21 (settled out of court) | ||
TTP1864 | (Mar 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2020/21 (settled out of court) | ||
TTP1863 | (Mar 21) | Rail Operations Group | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2020/21 (settled out of court) | ||
TTP1862 | (Mar 21) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2020/21 (settled out of court) | ||
TTP1861 | (Mar 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25-28, 2020/21 (settled out of court) | ||
TTP1860 | (Mar 21) | DB Cargo (UK) | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP1859 | (Feb 21) | First MTR South Western Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1858 | (Feb 21) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1857 | (Feb 21) | Govia Thameslink Railway | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1856 | (Feb 21) | First Greater Western | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1855 | (Feb 21) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1854 | (Feb 21) | West Midlands Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1853 | (Feb 21) | Arriva Rail London | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1852 | (Feb 21) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1851 | (Feb 21) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1850 | (Feb 21) | XC Trains | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1849 | (Feb 21) | Abellio East Anglia | Network Rail’s Timetable Planning Rules decisions for 2022, Version 2 (settled out of court) | ||
TTP1848 | (Feb 21) | London & South Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1847 | (Feb 21) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1846 | (Feb 21) | East Coast Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1845 | (Feb 21) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1844 | (Feb 21) | First Transpennine Express | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1843 | (Feb 21) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1842 | (Feb 21) | Abellio Scotrail | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1841 | (Feb 21) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1840 | (Feb 21) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1839 | (Feb 21) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1838 | (Feb 21) | Freightliner & Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1837 | (Feb 21) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1836 | (Feb 21) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1835 | (Feb 21) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1834 | (Feb 21) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1833 | (Feb 21) | Grand Central Railway | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1832 | (Feb 21) | First Trenitalia West Coast Rail | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1831 | (Feb 21) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1830 | (Feb 21) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1829 | (Feb 21) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1828 | (Feb 21) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1827 | (Feb 21) | Chiltern Railways | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1826 | (Feb 21) | Rail Operations Group | Network Rail’s Engineering Access Statement decisions for 2022, Version 2 (settled out of court) | ||
TTP1825 | (Feb 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2020/21 (settled out of court) | ||
TTP1824 | (Feb 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2020/21 (settled out of court) | ||
TTP1823 | (Feb 21) | Rail Operations Group | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21-24, 2020/21 (settled out of court) | ||
TTP1822 | (Feb 21) | First Trenitalia West Coast Rail | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2021 | ||
TTP1821 | (Feb 21) | Direct Rail Services | Network Rail's decision regarding Week 50 2020/21 (settled out of court) | ||
TTP1820 | (Feb 21) | Arriva Rail London | Network Rail's decision regarding Week 51 2020/21 (settled out of court) | ||
TTP1819 | (Feb 21) | GB Railfreight | Network Rail's decision regarding Week 51 2020/21 (settled out of court) | ||
TTP1818 | (Feb 21) | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding Week 51 2020/21 (settled out of court) | ||
TTP1817 | (Feb 21) | DB Cargo (UK) | Network Rail's decision regarding Week 50 2020/21 (settled out of court) | ||
TTP1816 | (Feb 21) | GB Railfreight | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP1815 | (Jan 21) | GB Railfreight | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2021 (settled out of court) | ||
TTP1814 | (Jan 21) | Freightliner Heavy Haul | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2021 (settled out of court) | ||
TTP1813 | (Jan 21) | DB Cargo (UK) | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2021 (settled out of court) | ||
TTP1812 | (Jan 21) | Rail Express Systems | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2021 (settled out of court) | ||
TTP1811 | (Jan 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2020/21 (settled out of court) | ||
TTP1810 | (Jan 21) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2020/21 (settled out of court) | ||
TTP1809 | (Jan 21) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2020/21 (settled out of court) | ||
TTP1808 | (Jan 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17-20, 2020/21 (settled out of court) | ||
TTP1807 | (Jan 21) | First Greater Western | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2021 (settled out of court) | ||
TTP1806 | (Jan 21) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2020/21 (settled out of court) | ||
TTP1805 | (Jan 21) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2020/21 (settled out of court) | ||
TTP1804 | (Dec 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2020/21 (settled out of court) | ||
TTP1803 | (Dec 20) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13-16, 2020/21 (settled out of court) | ||
TTP1802 | (Dec 20) | GB Railfreight | Network Rail’s decisions regarding Weeks 09 & 10 (settled out of court) | ||
TTP1801 | (Dec 20) | GB Railfreight | Network Rail’s decisions regarding Week 10 (settled out of court) | ||
TTP1800 | (Dec 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2020/21 (settled out of court) | ||
TTP1799 | (Dec 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2020/21 (settled out of court) | ||
TTP1798 | (Nov 20) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2020/21 (settled out of court) | ||
TTP1797 | (Nov 20) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2020/21 (settled out of court) | ||
TTP1796 | (Nov 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09-12, 2020/21 (settled out of court) | ||
TTP1795 | (Nov 20) | Abellio East Anglia | Network Rail’s decisions regarding Weeks 09, 10, 11 & 13 2021 (settled out of court) | ||
TTP1794 | (Nov 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2020/21 (settled out of court) | ||
TTP1793 | (Nov 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2020/21 (settled out of court) | ||
TTP1792 | (Nov 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05-08, 2020/21 (settled out of court) | ||
TTP1791 | (Oct 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-14 on an ongoing basis (settled out of court) | ||
TTP1790 | (Oct 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-12 on an ongoing basis (settled out of court) | ||
TTP1789 | (Oct 20) | Freightliner | Network Rail's decision not to offer Variations at TW-14 on an ongoing basis (settled out of court) | ||
TTP1788 | (Oct 20) | Freightliner | Network Rail's decision not to offer Variations at TW-12 on an ongoing basis (settled out of court) | ||
TTP1787 | (Oct 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2020/21 (settled out of court) | ||
TTP1786 | (Oct 20) | TfW Rail Services | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2020/21 (settled out of court) | ||
TTP1785 | (Oct 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2020/21 (settled out of court) | ||
TTP1784 | (Oct 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2020/21 (settled out of court) | ||
TTP1783 | (Oct 20) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01-04, 2020/21 (settled out of court) | ||
TTP1782 | (Oct 20) | GB Railfreight | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP1781 | (Oct 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-14 for Week 40 of 2020/21 (settled out of court) | ||
TTP1780 | (Oct 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-12 for Week 38 of 2019/20 (settled out of court) | ||
TTP1779 | (Oct 20) | Freightliner | Network Rail's decision not to offer Variations at TW-14 for Week 40 of 2020/21 (settled out of court) | ||
TTP1778 | (Oct 20) | Freightliner | Network Rail's decision not to offer Variations at TW-12 for Week 38 of 2019/20 (settled out of court) | ||
TTP1777 | (Sept 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-14 for Week 38 of 2019/20 (settled out of court) | ||
TTP1776 | (Sept 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-12 for Week 36 of 2019/20 (settled out of court) | ||
TTP1775 | (Sept 20) | Freightliner | Network Rail's decision not to offer Variations at TW-14 for Week 38 of 2019/20 (settled out of court) | ||
TTP1774 | (Sept 20) | Freightliner | Network Rail's decision not to offer Variations at TW-12 for Week 36 of 2019/20 (settled out of court) | ||
TTP1773 | (Sept 20) | DB Cargo (UK) | Network Rail's decision regarding Week 05 2020/21 (settled out of court) | ||
TTP1772 | (Sept 20) | First Greater Western | Network Rail's decision regarding Week 01 2020/21 (settled out of court) | ||
TTP1771 | (Sept 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-14 for Week 37 of 2019/20 (settled out of court) | ||
TTP1770 | (Sept 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-12 for Week 35 of 2019/20 (settled out of court) | ||
TTP1769 | (Sept 20) | Freightliner | Network Rail's decision not to offer Variations at TW-14 for Week 37 of 2019/20 (settled out of court) | ||
TTP1768 | (Sept 20) | Freightliner | Network Rail's decision not to offer Variations at TW-12 for Week 35 of 2019/20 (settled out of court) | ||
TTP1767 | (Sept 20) | Abellio East Anglia | Network Rail's decision regarding Weeks 42-45 2020/21 (settled out of court) | ||
TTP1766 | (Sept 20) | Abellio East Anglia | Network Rail's decision regarding Weeks 38, 39 & 40 2020/21 (settled out of court) | ||
TTP1765 | (Sept 20) | Freightliner | Network Rail's decision regarding Week 42 2020/21 (settled out of court) | ||
TTP1764 | (Sept 20) | GB Railfreight | Network Rail's decision regarding Week 42 2020/21 (settled out of court) | ||
TTP1763 | (Sept 20) | DB Cargo (UK) | Network Rail's decision regarding Week 42 2020/21 (settled out of court) | ||
TTP1762 | (Sept 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2020/21 (settled out of court) | ||
TTP1761 | (Sept 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2020/21 (settled out of court) | ||
TTP1760 | (Sept 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2020/21 (settled out of court) | ||
TTP1759 | (Sept 20) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49-52, 2020/21 (settled out of court) | ||
TTP1758 | (Sept 20) | GB Railfreight | Network Rail's decision not to offer Variations at TW-14 for Week 37 of 2019/20 (settled out of court) | ||
TTP1757 | (Sept 20) | GB Railfreight | Network Rail's decision not to offer Variations at TW-14 for Week 36 of 2019/20 (settled out of court) | ||
TTP1756 | (Sept 20) | GB Railfreight | Network Rail's decision not to offer Variations at TW-14 for Week 35 of 2019/20 (settled out of court) | ||
TTP1755 | (Sept 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-14 for Week 36 of 2019/20 (settled out of court) | ||
TTP1754 | (Sept 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-12 for Week 34 of 2019/20 (settled out of court) | ||
TTP1753 | (Sept 20) | Freightliner | Network Rail's decision not to offer Variations at TW-14 for Week 36 of 2019/20 (settled out of court) | ||
TTP1752 | (Sept 20) | Freightliner | Network Rail's decision not to offer Variations at TW-12 for Week 34 of 2019/20 (settled out of court) | ||
TTP1751 | (Aug 20) | XC Trains | Network Rail’s further Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1750 | (Aug 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-14 for Week 34 of 2019/20 (settled out of court) | ||
TTP1749 | (Aug 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-12 for Week 32 of 2019/20 (settled out of court) | ||
TTP1748 | (Aug 20) | Freightliner | Network Rail's decision not to offer Variations at TW-14 for Week 34 of 2019/20 (settled out of court) | ||
TTP1747 | (Aug 20) | Freightliner | Network Rail's decision not to offer Variations at TW-12 for Week 32 of 2019/20 (settled out of court) | ||
TTP1746 | (Aug 20) | Grand Central Railway | Network Rail's decision regarding Week 29 2019/20 (settled out of court) | ||
TTP1745 | (Aug 20) | Abellio East Anglia | Network Rail's decision regarding Week 51 2020/21 (settled out of court) | ||
TTP1744 | (Aug 20) | Abellio East Anglia | Network Rail's decision regarding Week 49 2020/21 (settled out of court) | ||
TTP1743 | (Aug 20) | GB Railfreight | Network Rail's decision not to offer Variations at TW-14 for Week 34 of 2019/20 (settled out of court) | ||
TTP1742 | (Aug 20) | GB Railfreight | Network Rail's decision not to offer Variations at TW-14 for Week 33 of 2019/20 (settled out of court) | ||
TTP1741 | (Aug 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-12 for Week 31 of 2019/20 (settled out of court) | ||
TTP1740 | (Aug 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations at TW-14 for Week 33 of 2019/20 (settled out of court) | ||
TTP1739 | (Aug 20) | Freightliner | Network Rail's decision not to offer Variations at TW-12 for Week 31 of 2019/20 (settled out of court) | ||
TTP1738 | (Aug 20) | Freightliner | Network Rail's decision not to offer Variations at TW-14 for Week 33 of 2019/20 (settled out of court) | ||
TTP1737 | (Aug 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2020/21 (settled out of court) | ||
TTP1736 | (Aug 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2020/21 (settled out of court) | ||
TTP1735 | (Aug 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45-48, 2020/21 (settled out of court) | ||
TTP1734 | (Aug 20) | GB Railfreight | Network Rail's decision not to offer Variations for Week 32 of 2019/20 (settled out of court) | ||
TTP1733 | (Aug 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 32 of 2019/20 (settled out of court) | ||
TTP1732 | (Aug 20) | Freightliner | Network Rail's decision not to offer Variations for Week 32 of 2019/20 (settled out of court) | ||
TTP1731 | (July 20) | DB Cargo (UK) | Network Rail's decision not to offer Variations for Week 31 of 2019/20 (settled out of court) | ||
TTP1730 | (July 20) | GB Railfreight | Network Rail's decision not to offer Variations for Week 31 of 2019/20 (settled out of court) | ||
TTP1729 | (July 20) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 31 of 2019/20 (settled out of court) | ||
TTP1728 | (July 20) | Freightliner | Network Rail's decision not to offer Variations for Week 31 of 2019/20 (settled out of court) | ||
TTP1727 | (July 20) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2021, Version 4 (settled out of court) | ||
TTP1726 | (July 20) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2021, Version 4 (settled out of court) | ||
TTP1725 | (July 20) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2021, Version 4 (settled out of court) | ||
TTP1724 | (July 20) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1723 | (July 20) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1722 | (July 20) | First Transpennine Express | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1721 | (July 20) | Freightliner & Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1720 | (July 20) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1719 | (July 20) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1718 | (July 20) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1717 | (July 20) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1716 | (July 20) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1715 | (July 20) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1714 | (July 20) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1713 | (July 20) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1712 | (July 20) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1711 | (July 20) | Grand Central Railway | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1710 | (July 20) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1709 | (July 20) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2021, Version 4 (settled out of court) | ||
TTP1708 | 13.08.20 | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding Weeks 22-27 2019/20. Network Rail appealed to ORR in respect of the Panel's determination. ORR issued a letter to NR & the CRC with the appeal determination. | ||
TTP1707 | (July 20) | DB Cargo (UK) | Network Rail's decision regarding Weeks 22-27 2019/20 (settled out of court) | ||
TTP1706 | 13.08.20 | GB Railfreight | Network Rail's decision regarding Weeks 21, 23-26 2019/20. Network Rail appealed to ORR in respect of the Panel's determination. ORR issued a letter to NR & the CRC with the appeal determination. | ||
TTP1705 | (July 20) | Serco Caledonian Sleepers | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1704 | (July 20) | GB Railfreight | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1703 | (July 20) | First Trenitalia West Coast Rail | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1702 | (July 20) | Grand Central Railway | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1701 | (July 20) | Govia Thameslink Railway | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1700 | (July 20) | London North Eastern Railway | Network Rail’s Timetable Planning Rules decisions for 2021, Version 4 (settled out of court) | ||
TTP1699 | (July 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2020/21 (settled out of court) | ||
TTP1698 | (July 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2020/21 (settled out of court) | ||
TTP1697 | (July 20) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2020/21 (settled out of court) | ||
TTP1696 | (July 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41-44, 2020/21 (settled out of court) | ||
TTP1695 | (July 20) | Freightliner | Network Rail's decision regarding Week 29 2019/20 (settled out of court) | ||
TTP1694 | (July 20) | DB Cargo (UK) | Network Rail's decision regarding Weeks 18-20 2020/21 (settled out of court) | ||
TTP1693 | (July 20) | Abellio East Anglia | Network Rail's decision regarding Weeks 47-50 2020/21 (settled out of court) | ||
TTP1692 | (July 20) | Freightliner | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1691 | (July 20) | Freightliner Heavy Haul | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1690 | (July 20) | DB Cargo (UK) | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1689 | (July 20) | Rail Express Systems | Network Rail’s decisions regarding the Working Timetable Publication for 2021 (settled out of court) | ||
TTP1688 | (July 20) | Freightliner | Network Rail's decision regarding Week 28 2019/20 (settled out of court) | ||
TTP1687 | (July 20) | Freightliner | Network Rail's decision regarding Week 27 2019/20 (settled out of court) | ||
TTP1686 | (July 20) | GB Railfreight | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP1685 | (June 20) | Freightliner | Network Rail's decision regarding Week 26 2019/20 (settled out of court) | ||
TTP1684 | (June 20) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2020/21 (settled out of court) | ||
TTP1683 | (June 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2020/21 (settled out of court) | ||
TTP1682 | (June 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2020/21 (settled out of court) | ||
TTP1681 | (June 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37-40, 2020/21 (settled out of court) | ||
TTP1680 | (June 20) | Freightliner | Network Rail's decision regarding Week 25 2019/20 (settled out of court) | ||
TTP1679 | (June 20) | DB Cargo (UK) | Network Rail's decision regarding Week 46 2020/21 (settled out of court) | ||
TTP1678 | (June 20) | ROG | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP1677 | (June 20) | Freightliner | Network Rail's decision regarding Week 46 2020/21 (settled out of court) | ||
TTP1676 | (June 20) | Freightliner | Network Rail's decision regarding Week 24 2019/20 (settled out of court) | ||
TTP1675 | (June 20) | Freightliner | Network Rail's decision regarding Week 23 2019/20 (settled out of court) | ||
TTP1674 | (May 20) | Abellio East Anglia | Network Rail's decision regarding Weeks 39/40 2021/22 (settled out of court) | ||
TTP1673 | (May 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2020/21 (settled out of court) | ||
TTP1672 | (May 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2020/21 (settled out of court) | ||
TTP1671 | (May 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33-36, 2020/21 (settled out of court) | ||
TTP1670 | (Apr 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2020/21 (settled out of court) | ||
TTP1669 | (Apr 20) | DB Cargo (UK) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2020/21 (settled out of court) | ||
TTP1668 | (Apr 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2020/21 (settled out of court) | ||
TTP1667 | (Apr 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29-32, 2020/21 (settled out of court) | ||
TTP1666 | (Mar 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2020/21 (settled out of court) | ||
TTP1665 | (Mar 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2020/21 (settled out of court) | ||
TTP1664 | (Mar 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2020/21 (settled out of court) | ||
TTP1663 | (Mar 20) | First Greater Western | Network Rail's decision regarding Week 27 2020/21 (settled out of court) | ||
TTP1662 | (Mar 20) | Govia Thameslink Railway | Network Rail's decision regarding Week 29 2020/21 (settled out of court) | ||
TTP1661 | (Feb 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2020/21 (settled out of court) | ||
TTP1660 | (Feb 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2020/21 (settled out of court) | ||
TTP1659 | (Feb 20) | Northern Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2020/21 (settled out of court) | ||
TTP1658 | (Feb 20) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1657 | (Feb 20) | First Transpennine Express | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1656 | (Feb 20) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1655 | (Feb 20) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1654 | (Feb 20) | First Trenitalia West Coast Rail | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1653 | (Feb 20) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1652 | (Feb 20) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1651 | (Feb 20) | Freightliner | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1650 | (Feb 20) | Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1649 | (Feb 20) | Abellio Scotrail | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1648 | (Feb 20) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1647 | (Feb 20) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1646 | (Feb 20) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1645 | (Feb 20) | London & South Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1644 | (Feb 20) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1643 | (Feb 20) | Northern Trains | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1642 | (Feb 20) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1641 | (Feb 20) | Grand Central Railway | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1640 | (Feb 20) | West Midlands Trains | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1639 | (Feb 20) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2021, Version 2 (settled out of court) | ||
TTP1638 | (Feb 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2020/21 (settled out of court) | ||
TTP1637 | (Feb 20) | First MTR South Western Trains | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 (settled out of court) | ||
TTP1636 | (Feb 20) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 (settled out of court) | ||
TTP1635 | (Feb 20) | Northern Trains | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 (settled out of court) | ||
TTP1634 | (Feb 20) | First Greater Western | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 (settled out of court) | ||
TTP1633 | (Feb 20) | Arriva Rail London | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 (settled out of court) | ||
TTP1632 | (Feb 20) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 (settled out of court) | ||
TTP1631 | (Feb 20) | DB Cargo (UK) | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 (settled out of court) | ||
TTP1630 | 16.04.20 | West Midlands Trains | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 | ||
TTP1629 | (Feb 20) | First Trenitalia West Coast Rail | Network Rail’s Timetable Planning Rules decisions for 2021, Version 2 (settled out of court) | ||
TTP1628 | (Jan 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2020/21 (settled out of court) | ||
TTP1627 | (Jan 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2020/21 (settled out of court) | ||
TTP1626 | (Jan 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2020/21 (settled out of court) | ||
TTP1625 | 24.02.20 | First MTR South Western Trains | Network Rail’s decisions regarding the revised Subsidiary Working Timetable Publication for 2020 | ||
TTP1624 | (Jan 20) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2020/21 (settled out of court) | ||
TTP1623 | (Jan 20) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2020/21 (settled out of court) | ||
TTP1622 | (Jan 20) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2020/21 (settled out of court) | ||
TTP1621 | (Jan 20) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2020/21 (settled out of court) | ||
TTP1620 | (Jan 20) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2020/21 (settled out of court) | ||
TTP1619 | (Dec 19) | Chiltern Railways | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2020/21 (settled out of court) | ||
TTP1618 | (Dec 19) | London North Eastern Railway | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1617 | (Dec 19) | Govia Thameslink Railway | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1616 | (Dec 19) | XC Trains | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1615 | (Dec 19) | Grand Central Railway | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1614 | (Dec 19) | First Greater Western | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1613 | (Dec 19) | GB Railfreight | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1612 | (Dec 19) | Rail Express Systems | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1611 | (Dec 19) | DB Cargo (UK) | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1610 | 19.02.20 | First Trenitalia West Coast Rail | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 | ||
TTP1609 | (Dec 19) | London North Eastern Railway | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1608 | (Dec 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09 - 12, 2020/21 (settled out of court) | ||
TTP1607 | (Dec 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09 - 12, 2020/21 (settled out of court) | ||
TTP1606 | (Dec 19) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09 - 12, 2020/21 (settled out of court) | ||
TTP1605 | (Dec 19) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09 - 12, 2020/21 (settled out of court) | ||
TTP1604 | (Dec 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 09 - 12, 2020/21 (settled out of court) | ||
TTP1603 | (Nov 19) | Freightliner Heavy Haul | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1602 | (Nov 19) | Abellio East Anglia | Network Rail’s decisions regarding the Subsidiary Working Timetable Publication for 2020 (settled out of court) | ||
TTP1601 | (Nov 19) | DB Cargo (UK) | Network Rail's decision regarding Week 19 2020/21 (settled out of court) | ||
TTP1600 | (Nov 19) | London North Eastern Railway | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1599 | (Nov 19) | Freightliner | Network Rail's decision regarding Week 48 2019/20 (settled out of court) | ||
TTP1598 | (Nov 19) | GB Railfreight | Network Rail's decision regarding Removal of Train Slots (settled out of court) | ||
TTP1597 | (Nov 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05 - 08, 2020/21 (settled out of court) | ||
TTP1596 | (Nov 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05 - 08, 2020/21 (settled out of court) | ||
TTP1595 | (Nov 19) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05 - 08, 2020/21 (settled out of court) | ||
TTP1594 | (Nov 19) | West Coast Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05 - 08, 2020/21 (settled out of court) | ||
TTP1593 | (Nov 19) | West Midlands Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05 - 08, 2020/21 (settled out of court) | ||
TTP1592 | (Nov 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 05 - 08, 2020/21 (settled out of court) | ||
TTP1591 | (Oct 19) | DB Cargo (UK) | Network Rail's decision regarding Week 02, 2020/21 (settled out of court) | ||
TTP1590 | (Oct 19) | DB Cargo (UK) | Network Rail's decision regarding Week 40, 2019/20 (settled out of court) | ||
TTP1589 | (Oct 19) | DB Cargo (UK) | Network Rail's decision regarding Removal of Train Slots (settled out of court) | ||
TTP1588 | (Oct 19) | XC Trains | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1587 | (Oct 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01 - 04, 2020/21 (settled out of court) | ||
TTP1586 | (Oct 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01 - 04, 2020/21 (settled out of court) | ||
TTP1585 | (Oct 19) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01 - 04, 2020/21 (settled out of court) | ||
TTP1584 | (Oct 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01 - 04, 2020/21 (settled out of court) | ||
TTP1583 | (Oct 19) | Grand Central Railway | Network Rail's decision regarding the Week 41 2019/20 timetable offer (settled out of court) | ||
TTP1582 | (Oct 19) | London North Eastern Railway | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1581 | (Oct 19) | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1580 | (Oct 19) | GB Railfreight | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1579 | (Oct 19) | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding length-specific TPRs on LNE & EM Routes (settled out of court) | ||
TTP1578 | (Sept 19) | London North Eastern Railway | Network Rail's decision regarding length-specific TPRs on LNE & EM Routes (settled out of court) | ||
TTP1577 | (Sept 19) | DB Cargo (UK) | Network Rail's decision regarding Weeks 43-44 2019/20 (settled out of court) | ||
TTP1576 | (Sept 19) | XC Trains | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1575 | (Sept 19) | Freightliner & Freightliner Heavy Haul | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1574 | (Sept 19) | XC Trains | Network Rail's decision regarding length-specific TPRs (settled out of court) | ||
TTP1573 | (Sept 19) | Direct Rail Services | Network Rail's decisions regarding Week 30 (settled out of court) | ||
TTP1572 | (Sept 19) | DB Cargo (UK) | Network Rail's decisions regarding Week 30 (settled out of court) | ||
TTP1571 | (Sept 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2019/20 (settled out of court) | ||
TTP1570 | (Sept 19) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2019/20 (settled out of court) | ||
TTP1569 | (Sept 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2019/20 (settled out of court) | ||
TTP1568 | (Sept 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2019/20 (settled out of court) | ||
TTP1567 | (Aug 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2019/20 (settled out of court) | ||
TTP1566 | (Aug 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2019/20 (settled out of court) | ||
TTP1565 | (Aug 19) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2019/20 (settled out of court) | ||
TTP1564 | (Aug 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2019/20 (settled out of court) | ||
TTP1563 | (July 19) | First Transpennine Express | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1562 | (Aug 19) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1561 | (Aug 19) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1560 | (Aug 19) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1559 | (Aug 19) | Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1558 | (Aug 19) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1557 | (Aug 19) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1556 | (Aug 19) | Arriva Rail North | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1555 | (Aug 19) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1554 | (Aug 19) | First Transpennine Express | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1553 | (Aug 19) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1552 | (Aug 19) | Abellio Scotrail | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1551 | (Aug 19) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1550 | (Aug 19) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2020, Version 4 (settled out of court) | ||
TTP1549 | (Aug 19) | First MTR South Western Trains | Network Rail’s Timetable Planning Rules decisions for 2020, Version 4 (settled out of court) | ||
TTP1548 | (Aug 19) | Arriva Rail North | Network Rail’s Timetable Planning Rules decisions for 2020, Version 4 (settled out of court) | ||
TTP1547 | (Aug 19) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2020, Version 4 (settled out of court) | ||
TTP1546 | (July 19) | Freightliner | Network Rail's decision regarding Week 39 2019/20 (settled out of court) | ||
TTP1545 | (July 19) | First Greater Western | Network Rail’s Timetable Planning Rules decisions for 2020, Version 4 (settled out of court) | ||
TTP1544 | (July 19) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1543 | (July 19) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1542 | (July 19) | GB Railfreight | Network Rail’s rejection of a Train Operator Variation Request (settled out of court) | ||
TTP1541 | (July 19) | Arriva Rail London | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1540 | (July 19) | Freightliner | Network Rail’s Engineering Access Statement decisions for 2020, Version 4 (settled out of court) | ||
TTP1539 | (July 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2019/20 (settled out of court) | ||
TTP1538 | (July 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2019/20 (settled out of court) | ||
TTP1537 | (July 19) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2019/20 (settled out of court) | ||
TTP1536 | (July 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2019/20 (settled out of court) | ||
TTP1535 | (July 19) | Arriva Rail North | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1534 | (July 19) | Chiltern Railways | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1533 | (July 19) | TfW Rail Services | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1532 | (July 19) | London North Eastern Railway | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1531 | (July 19) | XC Trains | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1530 | (June 19) | First Greater Western | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1529 | (June 19) | GB Railfreight | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1528 | (June 19) | Arriva Rail London | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1527 | (June 19) | DB Cargo (UK) | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1526 | (June 19) | Rail Express Systems | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1525 | (June 19) | Abellio Scotrail | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1524 | (June 19) | Freightliner Heavy Haul | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1523 | (June 19) | East Midlands Trains | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1522 | (June 19) | Legge Infrastructure Services | Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court) | ||
TTP1521 | 08.08.19 | GB Railfreight | Network Rail’s decision for Week 32 of 2019/20 | ||
TTP1520 | 10.09.19 | Freightliner | Network Rail’s decisions regarding the New Working Timetable Publication for 2020. Network Rail appealed to ORR in respect of the Panel's determination. In January 2020 the ORR partially upheld the appeal. | ||
TTP1519 | (June 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20 (settled out of court) | ||
TTP1518 | (June 19) | XC Trains | Network Rail’s decision for Week 25 of 2019/20 (settled out of court) | ||
TTP1517 | (June 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20 (settled out of court) | ||
TTP1516 | (June 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20 (settled out of court) | ||
TTP1515 | (June 19) | MTR Corporation (Crossrail) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20 (settled out of court) | ||
TTP1514 | (June 19) | DB Cargo (UK) | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20 (settled out of court) | ||
TTP1513 | (May 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2019/20 (settled out of court) | ||
TTP1512 | (May 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2019/20 (settled out of court) | ||
TTP1511 | (May 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2019/20 (settled out of court) | ||
TTP1510 | (May 19) | First Greater Western | Network Rail’s decision for Week 33, 2019/20 (Settled out of court) | ||
TTP1509 | (Apr 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court) | ||
TTP1508 | (Apr 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court) | ||
TTP1507 | (Apr 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court) | ||
TTP1506 | (Apr 19) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court) | ||
TTP1505 | (Apr 19) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court) | ||
TTP1504 | (Apr 19) | Arriva Rail North | Network Rail’s decision to amend the Timetable Planning Rules for 2020 at Manchester Airport (settled out of court) | ||
TTP1503 | (Mar 19) | DB Cargo (UK) | Network Rail’s intention to remove certain freight Train Slots from the Working Timetable (settled out of court) | ||
TTP1502 | (Mar 19) | Govia Thameslink Railway | Network Rail’s Possessions Strategy Notice for Gatwick Airport station project (settled out of court) | ||
TTP1501 | (Mar 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court) | ||
TTP1500 | (Mar 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court) | ||
TTP1499 | (Mar 19) | London North Eastern Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court) | ||
TTP1498 | (Mar 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court) | ||
TTP1497 | (Mar 19) | First Greater Western | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court) | ||
TTP1496 | (Mar 19) | DB Cargo (UK) | Network Rail’s intention to remove certain freight Train Slots from the Working Timetable (settled out of court) | ||
TTP1495 | (Mar 19) | First Greater Western | Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court) | ||
TTP1494 | (Mar 19) | GB Railfreight | Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court) | ||
TTP1493 | (Mar 19) | TfW Rail Services | Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court) | ||
TTP1492 | (Mar 19) | London & South Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1491 | (Mar 19) | Abellio Scotrail | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1490 | (Mar 19) | TfW Rail Services | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1489 | (Mar 19) | Govia Thameslink Railway | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1488 | (Mar 19) | First Transpennine Express | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1487 | (Mar 19) | Grand Central Railway | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1486 | (Mar 19) | West Coast Trains | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1485 | (Mar 19) | MTR Corporation (Crossrail) | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1484 | (Mar 19) | First MTR South Western Trains | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1483 | (Mar 19) | First Greater Western | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1482 | (Mar 19) | XC Trains | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1481 | (Mar 19) | GB Railfreight | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1480 | (Mar 19) | Serco Caledonian Sleepers | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1479 | (Mar 19) | Abellio East Anglia | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1478 | (Mar 19) | Arriva Rail North | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1477 | (Mar 19) | London North Eastern Railway | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1476 | (Mar 19) | Arriva Rail North | Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court) | ||
TTP1475 | (Feb 19) | Freightliner & Freightliner Heavy Haul | Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court) | ||
TTP1474 | (Feb 19) | Freightliner Heavy Haul | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1473 | (Feb 19) | DB Cargo (UK) | Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court) | ||
TTP1472 | (Feb 19) | DB Cargo (UK) | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1471 | (Feb 19) | Freightliner | Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court) | ||
TTP1470 | (Feb 19) | Govia Thameslink Railway | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2019/20 (settled out of court) | ||
TTP1469 | (Feb 19) | XC Trains | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2019/20 (settled out of court) | ||
TTP1468 | (Feb 19) | Abellio East Anglia | Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2019/20 (settled out of court) | ||
TTP1467 | (Feb 19) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2019/20 (settled out of court) | ||
TTP1466 | (Feb 19) | Abellio East Anglia | Network Rail's decisions for Week 42 of 2019/20 to Week 6 of 2020/21 (settled out of court) | ||
TTP1465 | (Feb 19) | TfW Rail Services | Network Rail's decision for Week 52 of 2018/19 and Week 1 of 2019/20 (settled out of court) | ||
TTP1464 | (Jan 19) | First Greater Western | Network Rail's decisions for Weeks 15 - 17 and 38 - 40 of 2019/20 (settled out of court) | ||
TTP1463 | (Jan 19) | TfW Rail Services | Network Rail's decision for Week 40, 2019/20 (settled out of court) | ||
TTP1462 | (Jan 19) | TfW Rail Services | Network Rail's decision for Week 39, 2019/20 (settled out of court) | ||
TTP1461 | (Jan 19) | TfW Rail Services | Network Rail's decision for Week 38, 2019/20 (settled out of court) | ||
TTP1460 | (Jan 19) | TfW Rail Services | Network Rail's decision for Week 17, 2019/20 (settled out of court) | ||
TTP1459 | (Jan 19) | TfW Rail Services | Network Rail's decision for Week 16, 2019/20 (settled out of court) | ||
TTP1458 | (Jan 19) | TfW Rail Services | Network Rail's decision for Week 15, 2019/20 (settled out of court) | ||
TTP1457 | (Jan 19) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20 (settled out of court) | ||
TTP1456 | (Jan 19) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20 (settled out of court) | ||
TTP1455 | (Jan 19) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20 (settled out of court) | ||
TTP1454 | (Jan 19) | DB Cargo (UK) | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20 (settled out of court) | ||
TTP1453 | (Jan 19) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20 (settled out of court) | ||
TTP1452 | (Jan 19) | DB Cargo (UK) | Network Rail's intention to remove certain freight Train Slots from the Working Timetable (settled out of court) | ||
TTP1451 | (Jan 19) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2019/20 (settled out of court) | ||
TTP1450 | (Dec 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2019/20 (settled out of court) | ||
TTP1449 | (Dec 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2019/20 (settled out of court) | ||
TTP1448 | (Dec 18) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2019/20 (settled out of court) | ||
TTP1447 | (Dec 18) | Freightliner | Network Rail's rejection of Train Operator Variation Requests (settled out of court) | ||
TTP1446 | (Dec 18) | West Coast Trains | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1445 | (Dec 18) | Arriva Rail North | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1444 | (Dec 18) | XC Trains | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1443 | (Dec 18) | First Greater Western | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1442 | (Dec 18) | DB Cargo (UK) | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1441 | (Dec 18) | Rail Express Systems | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1440 | (Nov 17) | GB Railfreight | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1439 | (Nov 17) | Abellio Scotrail | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1438 | (Dec 18) | Freightliner Heavy Haul | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1437 | (Nov 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2019/20 (settled out of court) | ||
TTP1436 | (Nov 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2019/20 (settled out of court) | ||
TTP1435 | (Nov 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2019/20 (settled out of court) | ||
TTP1434 | (Nov 18) | London North Eastern Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2019/20 (settled out of court) | ||
TTP1433 | (Nov 18) | DB Cargo (UK) | Network Rail's decision for Week 25, 2019/20 (settled out of court) | ||
TTP1432 | (Nov 18) | TfW Rail Services | Network Rail's decision for Week 24, 2019/20 (settled out of court) | ||
TTP1431 | (Nov 18) | TfW Rail Services | Network Rail's decision for Week 23, 2019/20 (settled out of court) | ||
TTP1430 | (Nov 18) | TfW Rail Services | Network Rail's decision for Week 22, 2019/20 (settled out of court) | ||
TTP1429 | (Nov 18) | TfW Rail Services | Network Rail's decision for Week 21, 2019/20 (settled out of court) | ||
TTP1428 | (Nov 18) | TfW Rail Services | Network Rail's decision for Week 20, 2019/20 (settled out of court) | ||
TTP1427 | (Nov 18) | TfW Rail Services | Network Rail's decision for Week 19, 2019/20 (settled out of court) | ||
TTP1426 | (Nov 18) | TfW Rail Services | Network Rail's decision for Weeks 17 & 18, 2019/20 (settled out of court) | ||
TTP1425 | (Nov 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2019/20 (settled out of court) | ||
TTP1424 | (Nov 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2019/20 (settled out of court) | ||
TTP1423 | (Nov 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2019/20 (settled out of court) | ||
TTP1422 | (Oct 18) | First Greater Western | Network Rail's decision for Week 20, 2019/20 (settled out of court) | ||
TTP1421 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 16, 2019/20 (settled out of court) | ||
TTP1420 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 15, 2019/20 (settled out of court) | ||
TTP1419 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 14, 2019/20 (settled out of court) | ||
TTP1418 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 13, 2019/20 (settled out of court) | ||
TTP1417 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 12, 2019/20 (settled out of court) | ||
TTP1416 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 11, 2019/20 (settled out of court) | ||
TTP1415 | (Oct 18) | DB Cargo (UK) | Network Rail's decisions for Weeks 11, 12 & 17, 2019/20 (settled out of court) | ||
TTP1414 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 3, 2019/20 (settled out of court) | ||
TTP1413 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 2, 2019/20 (settled out of court) | ||
TTP1412 | (Oct 18) | TfW Rail Services | Network Rail's decision for Week 10, 2019/20 (settled out of court) | ||
TTP1411 | (Oct 18) | Freightliner | Network Rail's offer for Week 32, 2018/19 (settled out of court) | ||
TTP1410 | (Oct 18) | Arriva Trains Wales | Network Rail's decision for Week 9, 2019/20 (settled out of court) | ||
TTP1409 | (Oct 18) | Arriva Trains Wales | Network Rail's decision for Week 6, 2019/20 (settled out of court) | ||
TTP1408 | (Oct 18) | Arriva Trains Wales | Network Rail's further decision for Week 4, 2019/20 (settled out of court) | ||
TTP1407 | (Oct 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2019/20 (settled out of court) | ||
TTP1406 | (Oct 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2019/20 (settled out of court) | ||
TTP1405 | (Oct 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2019/20 (settled out of court) | ||
TTP1404 | (Oct 18) | Arriva Trains Wales | Network Rail's decision for Week 50, 2018/19 (settled out of court) | ||
TTP1403 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 5, 2019/20 (settled out of court) | ||
TTP1402 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 44, 2018/19 (settled out of court) | ||
TTP1401 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 52, 2018/19 (settled out of court) | ||
TTP1400 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 4, 2019/20 (settled out of court) | ||
TTP1399 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 1, 2019/20 (settled out of court) | ||
TTP1398 | (Sept 18) | West Coast Trains | Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1397 | (Sept 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2018/19 (settled out of court) | ||
TTP1396 | (Sept 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2018/19 (settled out of court) | ||
TTP1395 | (Sept 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2018/19 | ||
TTP1394 | (Sept 18) | DB Cargo (UK) | Network Rail's decisions for Weeks 1 & 4, 2019/20 (settled out of court) | ||
TTP1393 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 51, 2018/19 (settled out of court) | ||
TTP1392 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 49, 2018/19 (settled out of court) | ||
TTP1391 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 48, 2018/19 (settled out of court) | ||
TTP1390 | (Sept 18) | DB Cargo (UK) | Network Rail's decisions for Weeks 43, 46 & 47, 2018/19 (settled out of court) | ||
TTP1389 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 47, 2018/19 (settled out of court) | ||
TTP1388 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 46, 2018/19 (settled out of court) | ||
TTP1387 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 45, 2018/19 (settled out of court) | ||
TTP1386 | (Sept 18) | Arriva Trains Wales | Network Rail's decision for Week 43, 2018/19 (settled out of court) | ||
TTP1385 | 30.10.18 | First Greater Western | Network Rail's decision for Week 24, 2018/19 | ||
TTP1384 | 30.10.18 | DB Cargo (UK) | Network Rail's decision for Week 23, 2018/19 | ||
TTP1383 | 30.10.18 | First Greater Western | Network Rail's decision for Week 23, 2018/19 | ||
TTP1382 | (Aug 18) | Freightliner Heavy Haul | Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1381 | (Aug 18) | Abellio East Anglia | Network Rail's decision for Week 45 of 2018/19 to Week 8 of 2019/20 (settled out of court) | ||
TTP1380 | (Aug 18) | Rail Express Systems | Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1379 | (Aug 18) | DB Cargo (UK) | Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1378 | (Aug 18) | Freightliner | Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1377 | (Aug 18) | Serco Caledonian Sleepers | Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1376 | 08.11.18 | GB Railfreight | Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019. GB Railfreight and DB Cargo (UK) appealed to ORR in respect of the Panel's determination | ||
TTP1375 | (Aug 18) | Colas Rail | Network Rail's intention to remove a freight Train Slot from the Working Timetable (settled out of court) | ||
TTP1374 | (Aug 18) | DB Cargo (UK) | Network Rail's rejection of an Access Proposal (settled out of court) | ||
TTP1373 | (Aug 18) | DB Cargo (UK) | Network Rail's intention to remove certain freight Train Slots from the Working Timetable (settled out of court) | ||
TTP1372 | (Aug 18) | MTR Corporation (Crossrail) | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2018/19 (settled out of court) | ||
TTP1371 | (Aug 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2018/19 (settled out of court) | ||
TTP1370 | (Aug 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2018/19 (settled out of court) | ||
TTP1369 | (Aug 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2018/19 (settled out of court) | ||
TTP1368 | (Aug 18) | Freightliner Heavy Haul | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1367 | (Aug 18) | First Greater Western | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1366 | (Aug 18) | Govia Thameslink Railway | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1365 | (Aug 18) | First Transpennine Express | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1364 | (Aug 18) | First MTR South Western Railway | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1363 | (Aug 18) | MTR Corporation (Crossrail) | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1362 | (Aug 18) | Arriva Trains Wales | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1361 | (Aug 18) | London North Eastern Railway | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1360 | (Aug 18) | Arriva Rail North | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1359 | (Aug 18) | XC Trains | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1358 | (Aug 18) | GB Railfreight | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1357 | (Aug 18) | Serco Caledonian Sleepers | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1356 | (Aug 18) | Arriva Rail North | Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court) | ||
TTP1355 | (Aug 18) | GB Railfreight | Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court) | ||
TTP1354 | (Aug 18) | Arriva Trains Wales | Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court) | ||
TTP1353 | (Aug 18) | Abellio East Anglia | Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court) | ||
TTP1352 | (Aug 18) | XC Trains | Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court) | ||
TTP1351 | (Aug 18) | Freightliner & Freightliner Heavy Haul | Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court) | ||
TTP1350 | (Aug 18) | First Greater Western | Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court) | ||
TTP1349 | (July 18) | DB Cargo (UK) | Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court) | ||
TTP1348 | (July 18) | DB Cargo (UK) | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1347 | (July 18) | Abellio East Anglia | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1346 | (July 18) | Freightliner | Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court) | ||
TTP1345 | (July 18) | DB Cargo (UK) | Network Rail's failure to publish the Prior Working Timetable for May 2019 (settled out of court) | ||
TTP1344 | (July 18) | Freightliner Heavy Haul | Network Rail's failure to publish the Prior Working Timetable for May 2019 (settled out of court) | ||
TTP1343 | (July 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court) | ||
TTP1342 | (July 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court) | ||
TTP1341 | (July 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court) | ||
TTP1340 | (July 18) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court) | ||
TTP1339 | (July 18) | MTR Corporation (Crossrail) | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court) | ||
TTP1338 | (June 18) | Freightliner Heavy Haul | Network Rail's decisions for Weeks 41 44 of 2018/19 (settled out of court) | ||
TTP1337 | (June 18) | XC Trains | Network Rail's decision to amend the Timetable Planning Rules (settled out of court) | ||
TTP1336 | (July 18) | DB Cargo (UK) | Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1335 | (June 18) | Freightliner Heavy Haul | Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1334 | (June 18) | Abellio Scotrail | Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1333 | (June 18) | Arriva Trains Wales | Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1332 | (June 18) | First Greater Western | Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1331 | 08.11.18 | GB Railfreight | Network Rail's decisions regarding the New Working Timetable Publication for 2019. GB Railfreight and DB Cargo (UK) appealed to ORR in respect of the Panel's determination | ||
TTP1330 | (June 18) | Serco Caledonian Sleepers | Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1329 | (June 18) | West Coast Trains | Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1328 | (June 18) | Freightliner | Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court) | ||
TTP1327 | (June 18) | Arriva Trains Wales | Network Rail's decisions for Weeks 33 - 35, 2018/19 (settled out of court) | ||
TTP1326 | (June 18) | DB Cargo (UK) | Network Rail's intention to remove part of a freight Train Slot from the Working Timetable (settled out of court) | ||
TTP1325 | (June 18) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court) | ||
TTP1324 | (June 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court) | ||
TTP1323 | (June 18) | DB Cargo (UK) | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court) | ||
TTP1322 | (June 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court) | ||
TTP1321 | (June 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court) | ||
TTP1320 | (June 18) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court) | ||
TTP1319 | (June 18) | MTR Corporation (Crossrail) | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court) | ||
TTP1318 | (June 18) | Freightliner | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court) | ||
TTP1317 | 12.06.18 | Freightliner | Network Rail's offer for Week 16, 2018/19 (settled out of court) | ||
TTP1316 | (May 18) | Freightliner Heavy Haul | Network Rail's offer for Week 15, 2018/19 (settled out of court) | ||
TTP1315 | (May 18) | DB Cargo (UK) | Network Rail's decisions for Weeks 25 - 29, 2018/19 (settled out of court) | ||
TTP1314 | (May 18) | Freightliner Heavy Haul | Network Rail's offer for Week 14, 2018/19 (settled out of court) | ||
TTP1313 | 12.06.18 | Freightliner | Network Rail's offer for Week 15, 2018/19 (settled out of court) | ||
TTP1312 | (May 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court) | ||
TTP1311 | (May 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court) | ||
TTP1310 | (May 18) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court) | ||
TTP1309 | (May 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court) | ||
TTP1308 | (May 18) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court) | ||
TTP1307 | (May 18) | DB Cargo (UK) | Network Rail's decisions for Weeks 39 and 40 of 2018/19 (settled out of court) | ||
TTP1306 | (May 18) | Abellio East Anglia | Network Rail's decision for Week 14 of 2018/19 (settled out of court) | ||
TTP1305 | (Apr 18) | First Greater Western | Prioritisation of Access Proposals for the New Working Timetable for 2019 (settled out of court) | ||
TTP1304 | (Apr 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 18 of 2018/19 (settled out of court) | ||
TTP1303 | (Apr 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 18 of 2018/19 (settled out of court) | ||
TTP1302 | (Apr 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court) | ||
TTP1301 | (Apr 18) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court) | ||
TTP1300 | (Apr 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court) | ||
TTP1299 | (Apr 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court) | ||
TTP1298 | (Apr 18) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court) | ||
TTP1297 | (Apr 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 17 of 2018/19 (settled out of court) | ||
TTP1296 | (Apr 18) | Freightliner | Network Rail's decision not to offer Variations for Week 17 of 2018/19 (settled out of court) | ||
TTP1295 | (Apr 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 17 of 2018/19 (settled out of court) | ||
TTP1294 | (Apr 18) | Freightliner | Network Rail's decision not to offer Variations for Week 16 of 2018/19 (settled out of court) | ||
TTP1293 | (Apr 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 16 of 2018/19 (settled out of court) | ||
TTP1292 | (Apr 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 16 of 2018/19 (settled out of court) | ||
TTP1291 | (Apr 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 15 of 2018/19 (settled out of court) | ||
TTP1290 | (Apr 18) | Freightliner | Network Rail's decision not to offer Variations for Week 15 of 2018/19 (settled out of court) | ||
TTP1289 | (Apr 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 15 of 2018/19 (settled out of court) | ||
TTP1288 | (Mar 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 14 of 2018/19 (settled out of court) | ||
TTP1287 | (Mar 18) | Govia Thameslink Railway | Network Rail's Possessions Strategy Notice for Gatwick Airport station project (settled out of court) | ||
TTP1286 | (Mar 18) | Freightliner | Network Rail's decision not to offer Variations for Week 14 of 2018/19 (settled out of court) | ||
TTP1285 | (Mar 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 14 of 2018/19 (settled out of court) | ||
TTP1284 | (Mar 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2018/19 (settled out of court) | ||
TTP1283 | (Mar 18) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2018/19 (settled out of court) | ||
TTP1282 | (Mar 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2018/19 (settled out of court) | ||
TTP1281 | (Mar 18) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2018/19 (settled out of court) | ||
TTP1280 | (Mar 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2018/19 (settled out of court) | ||
TTP1279 | (Mar 18) | DB Cargo (UK) | Network Rail's decisions in Confirmed Period Possession Plan for Week 28, 2018/19 (settled out of court) | ||
TTP1278 | (Mar 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 13 of 2018/19 (settled out of court) | ||
TTP1277 | (Mar 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 13 of 2018/19 (settled out of court) | ||
TTP1276 | (Mar 18) | Freightliner | Network Rail's decision not to offer Variations for Week 13 of 2018/19 (settled out of court) | ||
TTP1275 | (Mar 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 12 of 2018/19 (settled out of court) | ||
TTP1274 | (Mar 18) | Freightliner | Network Rail's decision not to offer Variations for Week 12 of 2018/19 (settled out of court) | ||
TTP1273 | (Mar 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 11 of 2018/19 (settled out of court) | ||
TTP1272 | (Mar 18) | DB Cargo (UK) | Network Rail's decisions for Weeks 7, 16 - 19 and 28 of 2018/19 (settled out of court) | ||
TTP1271 | (Mar 18) | Freightliner | Network Rail's decision not to offer Variations for Week 11 of 2018/19 (settled out of court) | ||
TTP1270 | (Mar 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 11 of 2018/19 (settled out of court) | ||
TTP1269 | (Feb 18) | GB Railfreight | Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court) | ||
TTP1268 | (Feb 18) | Arriva Trains Wales | Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court) | ||
TTP1267 | (Feb 18) | First Greater Western | Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court) | ||
TTP1266 | (Feb 18) | Arriva Rail North | Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court) | ||
TTP1265 | (Feb 18) | First MTR South Western Trains | Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court) | ||
TTP1264 | (Feb 18) | Freightliner & Freightliner Heavy Haul | Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court) | ||
TTP1263 | (Feb 18) | DB Cargo (UK) | Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court) | ||
TTP1262 | (Feb 18) | DB Cargo (UK) | Network Rail's decision for Week 15 of 2018/19 (settled out of court) | ||
TTP1261 | (Feb 18) | London & South Eastern Railway | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1260 | (Feb 18) | Govia Thameslink Railway | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1259 | (Feb 18) | Abellio Scotrail | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1258 | (Feb 18) | First Transpennine Express | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1257 | (Feb 18) | First MTR South Western Trains | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1256 | (Feb 18) | Arriva Rail North | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1255 | (Feb 18) | GB Railfreight | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1254 | (Feb 18) | Serco Caledonian Sleepers | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1253 | (Feb 18) | Abellio East Anglia | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1252 | (Feb 18) | Freightliner Heavy Haul | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1251 | (Feb 18) | Trenitialia c2c | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1250 | (Feb 18) | MTR Corporation (Crossrail) | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1249 | (Feb 18) | Grand Central Railway | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1248 | 24.05.18 | First Greater Western | Network Rail's Engineering Access Statement decisions for 2019, Version 2. At the hearing on 24 May 2018 FGW reserved its position on matters not then put before the Panel. A second hearing was arranged for 7 August 2018 to deal with those other matters and also issues relating to Network Rail's compliance with the determination of the 24 May 2018 hearing, but this second hearing was then deferred due to progress being made between the parties. On 18 February 2019 First Greater Western advised that the dispute reference could be closed. | ||
TTP1247 | (Feb 18) | East Coast Main Line Company | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1246 | (Feb 18) | Arriva Trains Wales | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1245 | (Feb 18) | XC Tains | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1244 | (Feb 18) | Freightliner | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1243 | (Feb 18) | DB Cargo (UK) | Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court) | ||
TTP1242 | (Feb 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 10 of 2018/19 (settled out of court) | ||
TTP1241 | (Feb 18) | Freightliner | Network Rail's decision not to offer Variations for Week 10 of 2018/19 (settled out of court) | ||
TTP1240 | (Feb 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 10 of 2018/19 (settled out of court) | ||
TTP1239 | (Feb 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 9 of 2018/19 (settled out of court) | ||
TTP1238 | (Feb 18) | Freightliner | Network Rail's decision not to offer Variations for Week 9 of 2018/19 (settled out of court) | ||
TTP1237 | (Feb 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 9 of 2018/19 (settled out of court) | ||
TTP1236 | (Feb 18) | DB Cargo (UK) | Network Rail's decision not to offer Variations for Week 8 of 2018/19 (settled out of court) | ||
TTP1235 | (Feb 18) | Freightliner Heavy Haul | Network Rail's decision not to offer Variations for Week 8 of 2018/19 (settled out of court) | ||
TTP1234 | (Feb 18) | Freightliner | Network Rail's decision not to offer Variations for Week 8 of 2018/19 (settled out of court) | ||
TTP1233 | (Feb 18) | GB Railfreight | Network Rail's decision not to offer Variations for Week 8 of 2018/19 (settled out of court) | ||
TTP1232 | (Feb 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2018/19 (settled out of court) | ||
TTP1231 | (Feb 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2018/19 (settled out of court) | ||
TTP1230 | (Feb 18) | DB Cargo (UK) | Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2018/19 (settled out of court) | ||
TTP1229 | (Feb 18) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2018/19 (settled out of court) | ||
TTP1228 | (Feb 18) | XC Trains | Network Rail's decision for Week 16 of 2018/19 (settled out of court) | ||
TTP1227 | (Feb 18) | DB Cargo (UK) | Network Rail's decisions for Weeks 6 - 8, 13 & 14 of 2018/19 (settled out of court) | ||
TTP1226 | (Feb 18) | XC Trains | Network Rail's decision for Week 15 of 2018/19 (settled out of court) | ||
TTP1225 | (Feb 18) | DB Cargo (UK) | Network Rail's intention to remove certain freight Train Slots from the Working Timetable (settled out of court) | ||
TTP1224 | (Feb 18) | Arriva Trains Wales | Network Rail's decisions for Weeks 4 & 5 of 2018/19 (settled out of court) | ||
TTP1223 | (Feb 18) | XC Trains | Network Rail's decisions for Weeks 4 & 5 of 2018/19 (settled out of court) | ||
TTP1222 | (Feb 18) | XC Trains | Network Rail's decision for Week 27 of 2018/19 (settled out of court) | ||
TTP1221 | (Feb 18) | DB Cargo (UK) | Network Rail's decision for Week 22 of 2018/19 (settled out of court) | ||
TTP1220 | (Feb 18) | DB Cargo (UK) | Network Rail's decisions for Weeks 4 & 5 of 2018/19 (settled out of court) | ||
TTP1219 | (Feb 18) | Abellio East Anglia | Network Rail's decisions for Weeks 41 - 52 of 2018/19 (settled out of court) | ||
TTP1218 | (Jan 18) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2018/19 (settled out of court) | ||
TTP1217 | (Jan 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2018/19 (settled out of court) | ||
TTP1216 | (Jan 18) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2018/19 (settled out of court) | ||
TTP1215 | (Jan 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2018/19 (settled out of court) | ||
TTP1214 | (Jan 18) | Abellio East Anglia | Network Rail's decisions for Weeks 29 - 32 of 2018/19 (settled out of court) | ||
TTP1213 | (Jan 18) | DB Cargo (UK) | Network Rail's decision for Week 18 of 2018/19 (settled out of court) | ||
TTP1212 | (Jan 18) | XC Trains | Network Rail's decision for Week 31 of 2018/19 (settled out of court) | ||
TTP1211 | (Jan 18) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2018/19 (settled out of court) | ||
TTP1210 | (Jan 18) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2018/19 (settled out of court) | ||
TTP1209 | (Jan 18) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2018/19 (settled out of court) | ||
TTP1208 | (Dec 17) | Abellio East Anglia | Network Rail's offer for Week 1, 2018/19 (settled out of court) | ||
TTP1207 | (Dec 17) | First Transpennine Express | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1206 | (Dec 17) | Govia Thameslink Railway | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1205 | (Dec 17) | Serco Caledonian Sleepers | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1204 | (Dec 17) | GB Railfreight | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1203 | (Dec 17) | Arriva Rail North | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1202 | (Dec 17) | XC Trains | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1201 | (Dec 17) | Grand Central Railway | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1200 | (Dec 17) | West Coast Trains | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1199 | (Dec 17) | First Greater Western | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1198 | (Dec 17) | DB Cargo (UK) | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1197 | (Dec 17) | Freightliner Heavy Haul | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 | ||
TTP1196 | (Nov 17) | Freightliner | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1195 | (Nov 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court) | ||
TTP1194 | (Nov 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court) | ||
TTP1193 | (Nov 17) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court) | ||
TTP1192 | (Nov 17) | DB Cargo (UK) | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court) | ||
TTP1191 | (Nov 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court) | ||
TTP1190 | (Oct 17) | First Greater Western | Network Rail's decisions regarding engineering access between Newport and Cardiff in Weeks 6 - 8, 2018/19 (settled out of court) | ||
TTP1189 | (Oct 17) | XC Trains | Network Rail's decisions regarding engineering access between Newport and Cardiff in Weeks 6 - 8, 2018/19 (settled out of court) | ||
TTP1188 | (Nov 17) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court) | ||
TTP1187 | (Nov 17) | DB Cargo (UK) | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court) | ||
TTP1186 | (Nov 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court) | ||
TTP1185 | (Nov 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court) | ||
TTP1184 | (Nov 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court) | ||
TTP1183 | (Nov 17) | Arriva Trains Wales | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court) | ||
TTP1182 | (Oct 17) | Arriva Trains Wales | Network Rail's decisions regarding engineering access between Pilning and Fishguard Harbour in Weeks 5 - 8, 2018/19 (settled out of court) | ||
TTP1181 | (Oct 17) | XC Trains | Network Rail's decision regarding engineering access in the Coventry area in Week 22, 2018/19 (settled out of court) | ||
TTP1180 | (Oct 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court) | ||
TTP1179 | (Oct 17) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court) | ||
TTP1178 | (Oct 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court) | ||
TTP1177 | (Oct 17) | DB Cargo (UK) | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court) | ||
TTP1176 | (Oct 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court) | ||
TTP1175 | (Oct 17) | Freightliner | Network Rail's offer for Week 39, 2017/18 (settled out of court) | ||
TTP1174 | 11.10.17 | XC Trains | Network Rail's reconsidered decision regarding the New Working Timetable Publication for 2018. Network Rail appealed to ORR in respect of the Panel's determination. | ||
TTP1173 | (Sept 17) | First Greater Western | Network Rail's decision regarding engineering access in the Cardiff area in Weeks 29 & 30, 2017/18 (settled out of court) | ||
TTP1172 | (Sept 17) | GB Railfreight | Network Rail's rejection of a Train Operator Variation Request (settled out of court) | ||
TTP1171 | (Sept 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court) | ||
TTP1170 | (Sept 17) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court) | ||
TTP1169 | (Sept 17) | First MTR South Western Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court) | ||
TTP1168 | (Sept 17) | D B Cargo (UK) | Network Rail's decisions in Confirmed Period Possession Plan for Week 50, 2017/18 (settled out of court) | ||
TTP1167 | (Sept 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court) | ||
TTP1166 | (Sept 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court) | ||
TTP1165 | (Aug 17) | XC Trains | Network Rail's decision regarding possession P2017/2285097 for Week 25, 2017/18 (settled out of court) | ||
TTP1164 | (Aug 17) | Freightliner | Network Rail's decisions regarding engineering access between Gospel Oak and Barking in Weeks 25 - 29, 2017/18 (settled out of court) | ||
TTP1163 | (Aug 17) | First Greater Western | Network Rail's decision regarding possession P2017/2412232 for Week 25, 2017/18 (settled out of court) | ||
TTP1162 | (Aug 17) | Freightliner | Network Rail's offer for Weeks 25 - 29, 2017/18 (settled out of court) | ||
TTP1161 | (Aug 17) | First Greater Western | Network Rail's decision regarding South Wales Immunisation and Modernisation Works in Week 39, 2017/18 (settled out of court) | ||
TTP1160 | (Aug 17) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court) | ||
TTP1159 | (Aug 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court) | ||
TTP1158 | (Aug 17) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court) | ||
TTP1157 | (Aug 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court) | ||
TTP1156 | (Aug 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court) | ||
TTP1155 | (Aug 17) | East Midlands Trains | Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court) | ||
TTP1154 | (Aug 17) | Abellio Scotrail | Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court) | ||
TTP1153 | (Feb 18) | GB Railfreight | Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court) | ||
TTP1152 | (Aug 17) | Arriva Rail North | Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court) | ||
TTP1151 | (Aug 17) | Stagecoach South Western Trains | Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court) | ||
TTP1150 | (Aug 17) | Arriva Rail London | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1149 | (Aug 17) | Govia Thameslink Railway | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1148 | (Aug 17) | First Transpennine Express | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1147 | (Aug 17) | GB Railfreight | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1146 | (Aug 17) | Serco Caledonian Sleepers | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1145 | (Aug 17) | Stagecoach South Western Trains | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1144 | (Aug 17) | Freightliner Heavy Haul | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1143 | (Aug 17) | First Greater Western | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1142 | (Aug 17) | Arriva Rail North | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1141 | (Aug 17) | East Coast Main Line Company | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1140 | (Aug 17) | XC Trains | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court | ||
TTP1139 | (Aug 17) | Abellio Scotrail | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1138 | (Aug 17) | Abellio East Anglia | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1137 | (July 17) | Freightliner | Network Rail's rejection of a Train Operator Variation Request (settled out of court) | ||
TTP1136 | (July 17) | DB Cargo (UK) | Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court) | ||
TTP1135 | (July 17) | DB Cargo (UK) | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1134 | (July 17) | Freightliner | Network Rail's offer for Week 29, 2017/18 (settled out of court) | ||
TTP1133 | (July 17) | Freightliner | Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court) | ||
TTP1132 | (July 17) | First Greater Western | Network Rail's decisions regarding engineering access in the Cardiff area in Weeks 46 - 50, 2017/18 (settled out of court) | ||
TTP1131 | (July 17) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2017/18 (settled out of court) | ||
TTP1130 | (July 17) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2017/18 (settled out of court) | ||
TTP1129 | (July 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2017/18 (settled out of court) | ||
TTP1128 | (July 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2017/18 (settled out of court) | ||
TTP1127 | 05.09.17 | GB Railfreight | Network Rail's rejection of a Train Operator Variation Request | ||
TTP1126 | (July 17) | First Greater Western | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1125 | (July 17) | Abellio Scotrail | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1124 | (July 17) | Arriva Rail North | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1123 | (July 17) | Grand Central Railway | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1122 | 08.09.17 | XC Trains | Network Rail's decisions regarding the New Working Timetable Publication for 2018 | ||
TTP1121 | (July 17) | Stagecoach South Western Trains | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1120 | (June 17) | XC Trains | Network Rail's decision regarding engineering access in the Filton Bank area in Week 35 of 2018/19 (settled out of court) | ||
TTP1119 | (June 17) | GB Railfreight | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1118 | (June 17) | Serco Caledonian Sleepers | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1117 | (June 17) | Freightliner Heavy Haul | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1116 | (June 17) | DB Cargo (UK) | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1115 | (June 17) | Abellio East Anglia | Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court) | ||
TTP1114 | (June 17) | First Greater Western | Network Rail's decision regarding possession P2017/2163274 (commissioning of signalling in the Port Talbot area) (settled out of court) | ||
TTP1113 | (June 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court) | ||
TTP1112 | (June 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court) | ||
TTP1111 | (June 17) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court) | ||
TTP1110 | (June 17) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court) | ||
TTP1109 | (June 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court) | ||
TTP1108 | (May 17) | First Greater Western | Network Rail's decisions regarding engineering access in the Port Talbot area between Week 51 of 2017/18 and Week 5 of 2018/19. (settled out of court) | ||
TTP1107 | (May 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2017/18 (settled out of court) | ||
TTP1106 | (May 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2017/18 (settled out of court) | ||
TTP1105 | (May 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2017/18 (settled out of court) | ||
TTP1104 | (Apr 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court) | ||
TTP1103 | (Apr 17) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court) | ||
TTP1102 | (Apr 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court) | ||
TTP1101 | (Apr 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court) | ||
TTP1100 | (Apr 17) | Freightliner | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court) | ||
TTP1099 | (Mar 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2017/18 (settled out of court) | ||
TTP1098 | (Mar 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2017/18 (settled out of court) | ||
TTP1097 | (Mar 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2017/18 (settled out of court) | ||
TTP1096 | (Mar 17) | Arriva Trains Wales | Network Rail's decision to redate possession P2017/2163691 (settled out of court) | ||
TTP1095 | (Feb 17) | First Transpennine Express | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court) | ||
TTP1094 | (Feb 17) | Abellio ScotRail | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1093 | (Feb 17) | Govia Thameslink Railway | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1092 | (Feb 17) | First Greater Western | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1091 | (Feb 17) | Arriva Rail London | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1090 | (Feb 17) | First Transpennine Express | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1089 | (Feb 17) | Arriva Rail North | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1088 | (Feb 17) | Abellio East Anglia | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1087 | (Feb 17) | Serco Caledonian Sleepers | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1086 | 05.06.17 | GB Railfreight | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1085 | (Feb 17) | Stagecoach South Western Trains | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1084 | (Feb 17) | Freightliner Heavy Haul | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1083 | (Feb 17) | XC Trains | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1082 | (Feb 17) | Arriva Trains Wales | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1081 | (Feb 17) | Grand Central Railway | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1080 | (Feb 17) | East Coast | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1079 | (Feb 17) | London & South Eastern Railway | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1078 | (Feb 17) | Heathrow Express | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1077 | (Feb 17) | Freightliner | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1076 | (Feb 17) | DB Cargo (UK) | Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court) | ||
TTP1075 | (Feb 17) | Arriva Rail North | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064) (settled out of court) | ||
TTP1074 | (Feb 17) | Govia Thameslink Railway | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court) | ||
TTP1073 | 20.04.17 | XC Trains | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064) | ||
TTP1072 | (Feb 17) | Stagecoach South Western Trains | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court) | ||
TTP1071 | (Feb 17) | East Coast | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court) | ||
TTP1070 | (Feb 17) | Serco Caledonian Sleepers | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court) | ||
TTP1069 | 20.04.17 | GB Railfreight | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064) | ||
TTP1068 | 20.04.17 | Transport for London | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064) | ||
TTP1067 | (Feb 17) | London & South Eastern Railway | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court) | ||
TTP1066 | 20.04.17 | First Greater Western | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064) | ||
TTP1065 | 20.04.17 | DB Cargo (UK) | Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064) | ||
TTP1064 | 20.04.17 | Abellio Scotrail | Network Rail's Timetable Planning Rules decisions for 2018, Version 2. Abellio Scotrail appealed to ORR concerning the Panel's determination. | ||
TTP1063 | (Feb 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Week 23, 2017/18 (settled out of court) | ||
TTP1062 | (Feb 17) | Arriva Trains Wales | Network Rail's decisions in Confirmed Period Possession Plan for Week 24, 2017/18 (settled out of court) | ||
TTP1061 | (Feb 17) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24 2017/18 (settled out of court) | ||
TTP1060 | (Feb 17) | London & South Eastern Railway | Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2017/18 (settled out of court) | ||
TTP1059 | (Feb 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2017/18 (settled out of court) | ||
TTP1058 | (Jan 17) | Freightliner | Network Rail's offer for Week 2, 2017/18 (settled out of court) | ||
TTP1057 | (Jan 17) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Week 17, 2017/18 (settled out of court) | ||
TTP1056 | (Jan 17) | Arriva Trains Wales | Network Rail's decisions in Confirmed Period Possession Plan for Week 17, 2017/18 (settled out of court) | ||
TTP1055 | (Jan 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2017/18 (settled out of court) | ||
TTP1054 | (Jan 17) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2017/18 (settled out of court) | ||
TTP1053 | (Jan 17) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2017/18 (settled out of court) | ||
TTP1052 | (Jan 17) | First Greater Western | Network Rail's decision to redate Severn Tunnel possession P2017/2165162 (settled out of court) | ||
TTP1051 | (Jan 17) | Arriva Trains Wales | Network Rail's decision regarding Abergele station Down Platform line in Weeks 41 - 49, 2016/17 (settled out of court) | ||
TTP1050 | (Jan 17) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2017/18 (settled out of court) | ||
TTP1049 | (Dec 16) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2017/18 (settled out of court) | ||
TTP1048 | (Dec 16) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2017/18 (settled out of court) | ||
TTP1047 | (Dec 16) | Govia Thameslink Railway | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court) | ||
TTP1046 | (Dec 16) | XC Trains | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court) | ||
TTP1045 | (Dec 16) | Serco Caledonian Sleepers | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court) | ||
TTP1044 | (Dec 16) | GB Railfreight | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court) | ||
TTP1043 | (Dec 16) | First Greater Western | Network Rail's decision regarding engineering access between Wootton Bassett and Westerleigh Junction in August 2017 (settled out of court) | ||
TTP1042 | (Dec 16) | Freightliner Heavy Haul | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court) | ||
TTP1041 | (Dec 16) | GB Railfreight | Network Rail's rejection of a Train Operator Variation Request (settled out of court) | ||
TTP1040 | (Dec 16) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Week 9, 2017/18 (settled out of court) | ||
TTP1039 | (Nov 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2017/18 (settled out of court) | ||
TTP1038 | (Nov 16) | Arriva Rail London | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2017/18 (settled out of court) | ||
TTP1037 | (Nov 16) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2017/18 (settled out of court) | ||
TTP1036 | (Nov 16) | DB Cargo (UK) | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court) | ||
TTP1035 | (Nov 16) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Week 7, 2017/18 (settled out of court) | ||
TTP1034 | (Nov 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2017/18 (settled out of court) | ||
TTP1033 | (Nov 16) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2017/18 (settled out of court) | ||
TTP1032 | (Oct 16) | Abellio East Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2017/18 (settled out of court) | ||
TTP1031 | (Oct 16) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Week 1, 2017/18 (settled out of court) | ||
TTP1030 | (Oct 16) | West Coast Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2017/18 (settled out of court) | ||
TTP1029 | (Oct 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2017/18 (settled out of court) | ||
TTP1028 | (Oct 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2017/18 (settled out of court) | ||
TTP1027 | (Oct 16) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2017/18 (settled out of court) | ||
TTP1026 | (Sept 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2016/17 (settled out of court) | ||
TTP1025 | (Sept 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2016/17 (settled out of court) | ||
TTP1024 | (Sept 16) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2016/17 (settled out of court) | ||
TTP1023 | (Sept 16) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2016/17 (settled out of court) | ||
TTP1022 | (Aug 16) | Abellio Greater Anglia | Network Rail's decision regarding engineering access on Manor Park Up Passenger Avoiding line in Week 2, 2017/18 (settled out of court) | ||
TTP1021 | (Aug 16) | First Greater Western | Network Rail's decision amending engineering access at Bath Spa, Easter 2017 (settled out of court) | ||
TTP1020 | (Aug 16) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2016/17 (settled out of court) | ||
TTP1019 | (Aug 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2016/17 (settled out of court) | ||
TTP1018 | (Aug 16) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2016/17 (settled out of court) | ||
TTP1017 | (Aug 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2016/17 (settled out of court) | ||
TTP1016 | (Aug 16) | London Overground Rail Operations | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1015 | (Aug 16) | Stagecoach South Western Trains | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1014 | (Aug 16) | London & South Eastern Railway | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1013 | (Aug 16) | Serco Caledonian Sleepers | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1012 | (Aug 16) | First Transpennine Express | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1011 | (Aug 16) | First Greater Western | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1010 | (Aug 16) | Heathrow Express | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1009 | (Aug 16) | GB Railfreight | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1008 | (Aug 16) | Freightliner Heavy Haul | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1007 | (Aug 16) | Grand Central Railway | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1006 | (Aug 16) | Govia Thameslink Railway | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1005 | (Aug 16) | West Coast Trains | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1004 | (Aug 16) | Freightliner | Network Rail's offer for Week 32, 2016/17 (settled out of court) | ||
TTP1003 | (Aug 16) | Abellio Greater Anglia | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1002 | (Aug 16) | Arriva Rail North | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1001 | (Aug 16) | East Coast | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP1000 | (July 16) | XC Trains | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP999 | (July 16) | DB Cargo (UK) | Network Rail's decision regarding engineering access at Ashford East Junction in Week 24, 2016/17 (settled out of court) | ||
TTP998 | (July 16) | GB Railfreight | Network Rail's Timetable Planning Rules decisions for 2017, Version 4 (settled out of court) | ||
TTP997 | (July 16) | Serco Caledonian Sleepers | Network Rail's Timetable Planning Rules decisions for 2017, Version 4 (settled out of court) | ||
TTP996 | (July 16) | DB Cargo (UK) | Network Rail's Timetable Planning Rules decisions for 2017, Version 4 (settled out of court) | ||
TTP995 | (July 16) | DB Cargo (UK) | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP994 | (July 16) | West Coast Trains | Network Rail's decision amending access between Preston Fylde Junction and Blackpool North between 3 October 2016 and 8 December 2017 (settled out of court) | ||
TTP993 | (July 16) | Freightliner | Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court) | ||
TTP992 | (July 16) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2016/17 (settled out of court) | ||
TTP991 | (July 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Week 42, 2016/17 (settled out of court) | ||
TTP990 | (July 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2016/17 (settled out of court) | ||
TTP989 | (July 16) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2016/17 (settled out of court) | ||
TTP988 | (July 16) | Govia Thameslink Railway | Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court) | ||
TTP987 | (July 16) | XC Trains | Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court) | ||
TTP986 | (July 16) | First Greater Western | Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court) | ||
TTP985 | 05.08.16 | Abellio Greater Anglia | Network Rail's decisions regarding the New Working Timetable Publication for 2017. MTR Crossrail and Network Rail appealed to ORR in respect of the Panel's determination. | ||
TTP984 | (June 16) | Grand Central Railway | Network Rail's decisions amending the Confirmed Period Possession Plan for Weeks 30 & 31, 2016/17 (settled out of court) | ||
TTP983 | (June 16) | Freightliner Heavy Haul | Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court) | ||
TTP982 | (June 16) | GB Railfreight | Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court) | ||
TTP981 | (June 16) | Serco Caledonian Sleepers | Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court) | ||
TTP980 | (June 16) | Freightliner | Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court) | ||
TTP979 | (June 16) | DB Cargo (UK) | Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court) | ||
TTP978 | 16.08.16 | Abellio Greater Anglia | Network Rail's decisions regarding engineering access in Weeks 25 - 32, 2016/17 | ||
TTP977 | (June 16) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court) | ||
TTP976 | (June 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court) | ||
TTP975 | (June 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court) | ||
TTP974 | (June 16) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court) | ||
TTP973 | (June 16) | Freightliner | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court) | ||
TTP972 | (June 16) | Abellio Greater Anglia | Network Rail's decision regarding engineering access in Week 24, 2016/17 (settled out of court) | ||
TTP971 | (June 16) | First Greater Western | Network Rail's decision amending engineering access at Paddington over Christmas/New Year 2016/17 (settled out of court) | ||
TTP970 | (May 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2016/17 (settled out of court) | ||
TTP969 | (May 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2016/17 (settled out of court) | ||
TTP968 | (May 16) | Abellio Greater Anglia | Network Rail's decision regarding engineering access in Week 40, 2016/17 (settled out of court) | ||
TTP967 | (May 16) | Freightliner | Network Rail's offer for Weeks 18 - 20, 2016/17 (settled out of court) | ||
TTP966 | (May 16) | First Greater Western | Network Rail's offer for Week 14, 2016/17 (settled out of court) | ||
TTP965 | (May 16) | First Greater Western | Network Rail's decision amending the Timetable Planning Rules for 2017 (Cardiff West area) (settled out of court) | ||
TTP964 | (Apr 16) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2016/17 (settled out of court) | ||
TTP963 | (Apr 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2016/17 (settled out of court) | ||
TTP962 | (Apr 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2016/17 (settled out of court) | ||
TTP961 | (Apr 16) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2016/17 (settled out of court) | ||
TTP960 | (Apr 16) | DB Cargo (UK) | Network Rail's decisions regarding engineering access for Bromsgrove Electrification Scheme between Week 29, 2016/17 and Week 7, 2017/18 (settled out of court) | ||
TTP959 | (Apr 16) | Grand Central Railway | Network Rail's decisions regarding engineering access in Weeks 7 - 10, 2017/18 (settled out of court) | ||
TTP958 | (Apr 16) | Arriva Rail North | Network Rail's decisions regarding engineering access in Weeks 6 & 7, 2017/18 (settled out of court) | ||
TTP957 | (Mar 16) | Freightliner Heavy Haul | Network Rail's offer for Week 9, 2016/17 (settled out of court) | ||
TTP956 | (Mar 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2016/17 (settled out of court) | ||
TTP955 | (Mar 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2016/17 (settled out of court) | ||
TTP954 | (Mar 16) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2016/17 (settled out of court) | ||
TTP953 | (Mar 16) | Abellio Greater Anglia | Network Rail's decisions regarding engineering access for High Output Track Relaying System activity in Weeks 27 & 28, 2016/17 (settled out of court) | ||
TTP952 | (Feb 16) | GB Railfreight | Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court) | ||
TTP951 | (Feb 16) | Serco Caledonian Sleepers | Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court) | ||
TTP950 | (Feb 16) | Abellio ScotRail | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP949 | (Feb 16) | Northern Rail | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP948 | (Feb 16) | London Overground Rail Operations | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP947 | (Feb 16) | London & South Eastern Railway | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP946 | (Feb 16) | London & Birmingham Railway | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP945 | (Feb 16) | Govia Thameslink Railway | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP944 | (Feb 16) | GB Railfreight | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP943 | (Feb 16) | Grand Central Railway | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP942 | (Feb 16) | XC Trains | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP941 | (Feb 16) | Abellio Greater Anglia | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP940 | (Feb 16) | Serco Caledonian Sleepers | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP939 | (Feb 16) | First Greater Western | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP938 | (Feb 16) | West Coast Trains | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP937 | (Feb 16) | First/Keolis Transpennine | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP936 | (Feb 16) | MTR Crossrail | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP935 | (Feb 16) | Freightliner Heavy Haul | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP934 | (Feb 16) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2016/17 (settled out of court) | ||
TTP933 | (Feb 16) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 22 & 23, 2016/17 (settled out of court) | ||
TTP932 | (Feb 16) | East Coast | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP931 | (Feb 16) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2016/17 (settled out of court) | ||
TTP930 | (Feb 16) | Direct Rail Services | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP929 | (Feb 16) | Freightliner & Freightliner Heavy Haul | Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court) | ||
TTP928 | (Feb 16) | Freightliner | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP927 | (Feb 16) | Arriva Trains Wales | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2016/17 (settled out of court) | ||
TTP926 | (Feb 16) | DB Schenker Rail (UK) | Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court) | ||
TTP925 | (Feb 16) | DB Schenker Rail (UK) | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP924 | (Feb 16) | Heathrow Express | Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court) | ||
TTP923 | (Feb 16) | First Greater Western | Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court) | ||
TTP922 | (Feb 16) | GB Railfreight | Network Rail's rejection of a Train Operator Variation Request (settled out of court) | ||
TTP921 | (Jan 16) | Freightliner | Network Rail's rejection of a Train Operator Variation Request (settled out of court) | ||
TTP920 | (Jan 16) | XC Trains | Network Rail's offer for Week 5, 2016/17 (settled out of court) | ||
TTP919 | (Jan 16) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Week 17, 2016/17 (settled out of court) | ||
TTP918 | (Jan 16) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 & 19, 2016/17 (settled out of court) | ||
TTP917 | (Jan 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2016/17 (settled out of court) | ||
TTP916 | (Jan 16) | Abellio Greater Anglia | Network Rail's decisions regarding engineering access for High Output Ballast Cleaner activity in Weeks 4 - 8, 2016/17 (settled out of court) | ||
TTP915 | (Jan 16) | DB Schenker Rail (UK) | Network Rail's decision regarding engineering access between Gaer Junction and Marshfield in Week 29, 2016/17 (settled out of court) | ||
TTP914 | (Jan 16) | First Greater Western | Network Rail's decision regarding engineering access in the Maliphant area in Week 30, 2016/17 (settled out of court) | ||
TTP913 | (Jan 16) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2016/17 (settled out of court) | ||
TTP912 | (Jan 16) | Grand Central Railway | Network Rail's offer for Week 3, 2016/17 (settled out of court) | ||
TTP911 | (Dec 15) | Arriva Trains Wales | Network Rail's decisions regarding engineering access in Weeks 19 & 20, 2016/17 (settled out of court) | ||
TTP910 | (Dec 15) | First Greater Western | Network Rail's decision amending engineering access between Heywood Road Junction and Fairwood Junction via Westbury (settled out of court) | ||
TTP909 | (Dec 15) | First Greater Western | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court) | ||
TTP908 | (Dec 15) | West Coast Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2016/17 (settled out of court) | ||
TTP907 | (Dec 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2016/17 (settled out of court) | ||
TTP906 | (Dec 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Week 9, 2016/17 (settled out of court) | ||
TTP905 | (Nov 15) | Freightliner Heavy Haul | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court) | ||
TTP904 | (Nov 15) | Serco Caledonian Sleeper | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court) | ||
TTP903 | (Nov 15) | GB Railfreight | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court) | ||
TTP902 | (Nov 15) | Freightliner | Network Rail's decisions regarding engineering access in the Shenfield area in Weeks 25 - 32, 2016/17 (settled out of court) | ||
TTP901 | (Nov 15) | Freightliner Heavy Haul | Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court) | ||
TTP900 | (Nov 15) | London Overground Rail Operations | Network Rail's decisions regarding engineering access in the Shenfield area in Weeks 25 - 32, 2016/17 (settled out of court) | ||
TTP899 | (Nov 15) | Abellio Greater Anglia | Network Rail's decisions regarding engineering access in the Shenfield area in Weeks 25 - 32, 2016/17 (settled out of court) | ||
TTP898 | (Nov 15) | Freightliner | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court) | ||
TTP897 | (Nov 15) | DB Schenker Rail (UK) | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court) | ||
TTP896 | (Nov 15) | Grand Central Railway | Network Rail's decision regarding capacity allocation during engineering work in the Hornsey area in Week 9, 2016/17 (settled out of court) | ||
TTP895 | (Nov 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2016/17 (settled out of court) | ||
TTP894 | (Nov 15) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Week 8, 2016/17 (settled out of court) | ||
TTP893 | (Oct 15) | East Coast | Network Rail's decision regarding engineering access in the Hornsey area in Week 9, 2016/17 (settled out of court) | ||
TTP892 | (Oct 15) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2016/17 (settled out of court) | ||
TTP891 | (Oct 15) | DB Schenker Rail (UK) | Network Rail's decision regarding engineering access in the Oxford area in Weeks 17 - 19, 2016/17 (settled out of court) | ||
TTP890 | (Oct 15) | XC Trains | Network Rail's decision regarding engineering access in the Leamington Spa area in Week 15, 2016/17 (settled out of court) | ||
TTP889 | (Oct 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2016/17 (settled out of court) | ||
TTP888 | (Oct 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2016/17 (settled out of court) | ||
TTP887 | (Oct 15) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2016/17 (settled out of court) | ||
TTP886 | (Oct 15) | London Overground Rail Operations | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2016/17 (settled out of court) | ||
TTP885 | (Oct 15) | DB Schenker Rail (UK) | Network Rail's decision amending the Engineering Access Statement 2016 between Barnt Green and Abbotswood Junction (25 October - 7 November 2016) (settled out of court) | ||
TTP884 | (Sept 15) | XC Trains | Network Rail's decision regarding engineering access in the Bromsgrove area in Week 30, 2016/17 (settled out of court) | ||
TTP883 | (Sept 15) | Freightliner | Network Rail's offer for Week 40, 2015/16 (settled out of court) | ||
TTP882 | (Sept 15) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Week 53, 2015/16 (settled out of court) | ||
TTP881 | (Sept 15) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Week 53, 2015/16 (settled out of court) | ||
TTP880 | (Sept 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 52 & 53, 2015/16 (settled out of court) | ||
TTP879 | (Sept 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2015/16 (settled out of court) | ||
TTP878 | (Aug 15) | Arriva Trains Wales | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2015/16 (settled out of court) | ||
TTP877 | (Aug 15) | First Greater Western | Network Rail's offer for Week 33, 2015/16 (settled out of court) | ||
TTP876 | (Aug 15) | West Coast Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2015/16 (settled out of court) | ||
TTP875 | (Aug 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Week 47 (settled out of court) | ||
TTP874 | (Aug 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2015/16 (settled out of court) | ||
TTP873 | (Aug 15) | Freightliner | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2015/16 (settled out of court) | ||
TTP872 | 23.03.16 | Freightliner & Freightliner Heavy Haul | Network Rail's Timetable Planning Rules decisions for 2016, Version 4 | ||
TTP871 | (July 15) | Serco Caledonian Sleepers | Network Rail's Timetable Planning Rules decisions for 2016, Version 4 (settled out of court) | ||
TTP870 | (July 15) | Freightliner Heavy Haul | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP869 | (July 15) | Northern Rail | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP868 | (July 15) | Arriva Trains Wales | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP867 | (July 15) | London Overground Rail Operations | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP866 | (July 15) | First/Keolis Transpennine | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP865 | (July 15) | GB Railfreight | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP864 | (July 15) | Serco Caledonian Sleepers | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP863 | (July 15) | XC Trains | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP862 | (July 15) | West Coast Trains | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP861 | (July 15) | Govia Thameslink Railway | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP860 | (July 15) | First Greater Western | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP859 | (July 15) | Abellio Greater Anglia | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP858 | (July 15) | Grand Central Railway | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP857 | (July 15) | Heathrow Express | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP856 | (July 15) | East Coast | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP855 | (July 15) | GB Railfreight | Network Rail's Timetable Planning Rules decisions for 2016, Version 4 (settled out of court) | ||
TTP854 | (July 15) | DB Schenker Rail (UK) | Network Rail's Timetable Planning Rules decisions for 2016, Version 4 (settled out of court) | ||
TTP853 | (July 15) | DB Schenker Rail (UK) | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP852 | (July 15) | Southern Railway | Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court) | ||
TTP851 | (July 15) | Freightliner | Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court) | ||
TTP850 | (July 15) | Hull Trains | Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court) | ||
TTP849 | (July 15) | London Overground Rail Operations | Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court) | ||
TTP848 | (July 15) | Southern Railway | Network Rail's decisions regarding engineering access in Weeks 50 & 51, 2015/16 (settled out of court) | ||
TTP847 | (July 15) | Govia Thameslink Railway | Network Rail's decisions regarding engineering access in Weeks 50 & 51, 2015/16 (settled out of court) | ||
TTP846 | (July 15) | Arriva Trains Wales | Network Rail's decision regarding engineering access in the Cardiff area in Week 51, 2015/16 (settled out of court) | ||
TTP845 | (July 15) | Southern Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2015/16 (settled out of court) | ||
TTP844 | (July 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2015/16 (settled out of court) | ||
TTP843 | (July 15) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Week 44, 2015/16 (settled out of court) | ||
TTP842 | (July 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Week 44, 2015/16 (settled out of court) | ||
TTP841 | (July 15) | Arriva Trains Wales | Network Rail's decisions regarding engineering access in the Cardiff area in Weeks 52 & 53, 2015/16 (settled out of court) | ||
TTP840 | (July 15) | Abellio Greater Anglia | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2015/16 (settled out of court) | ||
TTP839 | (July 15) | Freightliner | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2015/16 (settled out of court) | ||
TTP838 | (June 15) | Serco Caledonian Sleepers | Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court) | ||
TTP837 | (June 15) | Freightliner Heavy Haul | Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court) | ||
TTP836 | (June 15) | GB Railfreight | Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court) | ||
TTP835 | (June 15) | Freightliner | Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court) | ||
TTP834 | 06.10.15 | Arriva Trains Wales | Network Rail's decisions regarding the New Working Timetable Publication for 2016 | ||
TTP833 | (June 15) | DB Schenker Rail (UK) | Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court) | ||
TTP832 | (June 15) | Freightliner Heavy Haul | Network Rail's offer for Week 25, 2015/16 (settled out of court) | ||
TTP831 | (June 15) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2015/16 (settled out of court) | ||
TTP830 | (June 15) | East Coast | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2015/16 (settled out of court) | ||
TTP829 | (June 15) | DB Schenker Rail (UK) | Network Rail's decision regarding Restriction of Use in Angerstein Junction area in Week 15, 2015/16 (settled out of court) | ||
TTP828 | (June 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2015/16 (settled out of court) | ||
TTP827 | (June 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2015/16 (settled out of court) | ||
TTP826 | (May 15) | First Greater Western | Network Rail's decisions amending the Engineering Access Statement for 2016 (settled out of court) | ||
TTP825 | (May 15) | Freightliner Heavy Haul | Network Rail's offer for Week 22, 2015/16 (settled out of court) | ||
TTP824 | (May 15) | East Coast | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2015/16 (settled out of court) | ||
TTP823 | (May 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2015/16 (settled out of court) | ||
TTP822 | (May 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2015/16 (settled out of court) | ||
TTP821 | (May 15) | DB Schenker Rail (UK) | Network Rail's decisions amending the Engineering Access Statement for 2016 (settled out of court) | ||
TTP820 | (May 15) | Freightliner & Freightliner Heavy Haul | Network Rail's decision (Version 2.1) amending Sussex Timetable Planning Rules for 2016 (settled out of court) | ||
TTP819 | (Apr 15) | GB Railfreight | Network Rail's decision (Version 2.1) amending Sussex Timetable Planning Rules for 2016 (settled out of court) | ||
TTP818 | (Apr 15) | DB Schenker Rail (UK) | Network Rail's decisions regarding engineering access in South Wales in Weeks 33 & 34, 2015/16 (settled out of court) | ||
TTP817 | (Apr 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2015/16 (settled out of court) | ||
TTP816 | (Apr 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2015/16 (settled out of court) | ||
TTP815 | (Mar 15) | Govia Thameslink Railway | Network Rail's decision in a Batch Document amending the Engineering Access Statement 2016 on the LNE Route (settled out of court) | ||
TTP814 | (Mar 15) | Freightliner Heavy Haul | Network Rail's decision in a Batch Document amending the Engineering Access Statement 2016 on the LNE Route (settled out of court) | ||
TTP813 | (Mar 15) | DB Schenker Rail (UK) | Network Rail's decision in a Batch Document amending the Engineering Access Statement 2016 on the LNE Route (settled out of court) | ||
TTP812 | (Mar 15) | East Coast | Network Rail's decision in a Batch Document amending the Engineering Access Statement 2016 on the LNE Route (settled out of court) | ||
TTP811 | (Mar 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2015/16 (settled out of court) | ||
TTP810 | (Mar 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court) | ||
TTP809 | (Mar 15) | XC Trains | Network Rail's decision regarding engineering access in the Aldwarke Junction area in Weeks 19 - 21, 2015/16 (settled out of court) | ||
TTP808 | 01.06.15 | Freightliner & Freightliner Heavy Haul | Network Rail's decision amending Timetable Planning Rules decisions for 2016, Version 2 in respect of West Ealing area. Network Rail appealed to ORR in respect of paras. 6.1.1, 6.1.2, 6.1.3 and 6.1.5 of the determination. | ||
TTP807 | 01.06.15 | GB Railfreight | Network Rail's decision amending Timetable Planning Rules decisions for 2016, Version 2 in respect of West Ealing area. Network Rail appealed to ORR in respect of paras. 6.1.1, 6.1.2, 6.1.3 and 6.1.5 of the determination. | ||
TTP806 | (Feb 15) | Govia Thameslink Railway | Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court) | ||
TTP805 | (Feb 15) | Southern Railway | Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court) | ||
TTP804 | (Feb 15) | GB Railfreight | Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court) | ||
TTP803 | (Feb 15) | XC Trains | Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court) | ||
TTP802 | (Feb 15) | Freightliner & Freightliner Heavy Haul | Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court) | ||
TTP801 | (Feb 15) | Southern Railway | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP800 | (Feb 15) | First ScotRail | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP799 | (Feb 15) | First/Keolis Transpennine | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP798 | (Feb 15) | London Overground Rail Operations | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP797 | (Feb 15) | Freightliner Heavy Haul | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP796 | (Feb 15) | Arriva Trains Wales | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP795 | (Feb 15) | London & South Eastern Railway | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP794 | (Feb 15) | Abellio Greater Anglia | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP793 | (Feb 15) | Northern Rail | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP792 | (Feb 15) | GB Railfreight | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP791 | (Feb 15) | Govia Thameslink Railway | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP790 | (Feb 15) | First Greater Western | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP789 | (Feb 15) | East Coast | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP788 | (Feb 15) | London & Birmingham Railway | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP787 | (Feb 15) | West Coast Trains | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP786 | (Feb 15) | Grand Central Railway | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP785 | (Feb 15) | XC Trains | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP784 | (Feb 15) | Heathrow Express | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP783 | (Feb 15) | Freightliner | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP782 | (Feb 15) | DB Schenker Rail (UK) | Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court) | ||
TTP781 | (Feb 15) | DB Schenker Rail (UK) | Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court) | ||
TTP780 | (Feb 15) | Grand Central Railway | Network Rail's planning of Variation for Week 9 (settled out of court) | ||
TTP779 | (Feb 15) | Northern Rail | Network Rail's decision regarding engineering access between Ashton Moss Junction and Stalybridge in Weeks 25 - 28, 2015/16 (settled out of court) | ||
TTP778 | (Feb 15) | East Coast | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court) | ||
TTP777 | (Feb 15) | Arriva Trains Wales | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court) | ||
TTP776 | (Feb 15) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court) | ||
TTP775 | (Feb 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court) | ||
TTP774 | (Feb 15) | Grand Central Railway | Network Rail's decision regarding engineering access at Doncaster in Week 23, 2015/16 (settled out of court) | ||
TTP773 | 01.04.15 | XC Trains | Network Rail's planning of Variation for Week 6 | ||
TTP772 | (Jan 15) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2015/16 (settled out of court) | ||
TTP771 | (Jan 15) | Freightliner | Network Rail Variation for Week 2 of 2015/16 (settled out of court) | ||
TTP770 | (Dec 14) | XC Trains | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court) | ||
TTP769 | (Dec 14) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2015/16 (settled out of court) | ||
TTP768 | (Dec 14) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2015/16 (settled out of court) | ||
TTP767 | (Dec 14) | Abellio Greater Anglia | Network Rail's decisions amending engineering access between Liverpool Street and Seven Kings in Weeks 17, 23, 26 and 29, 2015/16 (settled out of court) | ||
TTP766 | (Dec 14) | Arriva Trains Wales | Network Rail's decision amending engineering access in the Wolverhampton area in Week 6 (settled out of court) | ||
TTP765 | (Dec 14) | Northern Rail | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court) | ||
TTP764 | (Dec 14) | First/Keolis Transpennine | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court) | ||
TTP763 | (Dec 14) | N Yorkshire Moors Rly | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court) | ||
TTP762 | (Dec 14) | Govia Thameslink Railway | Network Rail's decision amending engineering access in the Balcombe area in Weeks 51/52, 2014/15 (settled out of court) | ||
TTP761 | (Dec 14) | Freightliner Heavy Haul | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court) | ||
TTP760 | (Nov 14) | GB Railfreight | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court) | ||
TTP759 | (Nov 14) | East Coast | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2015/16 (settled out of court) | ||
TTP758 | (Nov 14) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2015/16 (settled out of court) | ||
TTP757 | (Nov 14) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2015/16 (settled out of court) | ||
TTP756 | (Nov 14) | Govia Thameslink Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2015/16 (settled out of court) | ||
TTP755 | (Nov 14) | Freightliner | Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court) | ||
TTP754 | (Oct 14) | First Greater Western | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court) | ||
TTP753 | (Oct 14) | XC Trains | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court) | ||
TTP752 | (Oct 14) | Grand Central Railway | Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court) | ||
TTP751 |