A list of references for hearing by a TTP/Timetabling Panel (including those references to the former Timetabling Committee which had not been resolved as at 15.04.05).

Note 1: The “Date” column indicates, if shown in brackets, the month that the reference was notified for hearing by a Timetabling Panel (Timetabling Committee prior to 15 April 2005); OR, if not in brackets, it indicates the date of the hearing.

Note 2: References to the Timetabling Committee were registered with prefix ‘ttc’. Those which were taken forward on 15 April 2005 for hearing by a Timetabling Panel were re-registered with prefix ‘TTP’. Both registration numbers are shown where appropriate. Details of such references are also found on the ‘old’ Access Dispute Resolution Committee site.

Note 3: References to the Network and Vehicle Change Committee were registered with prefix ‘NV’. Disputes NV75 – NV77 inc and NV79 – NV84 inc were taken forward on 15 April 2005 for consideration by a Timetabling Panel. The Panel recorded its determinations for these references in a single document titled “Panel Decision Number 1”. Details of the individual references are to be found on the ‘old’ Access Dispute Resolution Committee site.

Reference Number PDF Version Date Reference From Subject Submissions From The Parties
TTP1 [TTC257] (Dec 04) Northern Rail (East) Network Rail's decision in respect of the Rules of the Route (Version 2) for 2005/06 (settled out of court)
TTP2 [TTC259] (Dec 04) First ScotRail Network Rail's decision in respect of the Rules of the Route (Version 2) for 2005/06 (settled out of court)
TTP3 [TTC262] also [TTC290] TTP3 20.07.05 English Welsh & Scottish Railway Network Rail's decision in respect of the Rules of the Route (Version 2 and batching document 3) for 2005/06
TTP4 [TTC264] TTP4 22.08.05 Freightliner Network Rail's decision in respect of the Rules of the Route (Version 2) for 2005/06
TTP5 [TTC266] (Dec 04) Great North Eastern Railway Network Rail's decision in respect of items in Section 7 of the Rules of the Route (Version 2) for 2005/06 (settled out of court)
TTP6 [TTC272] (Jan 05) Great North Eastern Railway Network Rail's decision in respect of items in Sections 4 & 5 of the Rules of the Route (Version 2) for 2005/06 (settled out of court)
TTP7 [TTC273] also [TTC287] (Dec 04) Freightliner Heavy Haul Network Rail's decision in respect of the Rules of the Route (Version 2 and Version 3) for 2005/06 (settled out of court)
TTP8 [TTC281] (Jan 05) CrossCountry Trains Network Rail's decision in respect of the Rules of the Route (Version 2) for 2005/06 (settled out of court)
TTP9 [TTC285] (Jan 05) First ScotRail Network Rail's decision in respect of changes (in a batching document) to the Rules of the Route for 2005/06 (settled out of court)
TTP10 TTP10 09.06.05 English Welsh & Scottish Railway Network Rail's decision in respect of Bids for the June 2005 Timetable
TTP11 (Apr 05) Freightliner Heavy Haul Network Rail's decision in respect of changes (in batching document 3) to the Rules of the Route for 2005/06 (settled out of court)
TTP12 (Apr 05) First ScotRail Network Rail's decision in respect of changes (in Version 3) to the Rules of the Route for 2005/06 (settled out of court)
TTP13 (Apr 05) Central Trains Network Rail's decision in respect of changes (in batching document 4) to the Rules of the Route for 2005/06 (settled out of court)
TTP14 (May 05) First ScotRail Network Rail's decision in respect of changes (in Version 4.5) to the Rules of the Route for 2005/06 (settled out of court)
TTP15 (May 05) Freightliner Network Rail's decision in respect of changes (in Version 4) to the Rules of the Route for 2005/06 (settled out of court)
TTP16 (May 05) First ScotRail Network Rail's decision in respect of changes (in batching document 4) to the Rules of the Route for 2005/06 (settled out of court)
TTP17 (June 05) Central Trains Network Rail's decision in respect of changes (in batching document 5) to the Rules of the Route for 2005/06 (settled out of court)
TTP18 (May 05) English Welsh & Scottish Railway Network Rail's decision in respect of changes (in batching document 5) to the Rules of the Route for 2005/06 (settled out of court)
TTP19 (July 05) First ScotRail Network Rail's decision in respect of changes (in batching document 5) to the Rules of the Route for 2005/06 (settled out of court)
TTP20 (July 05) First ScotRail Network Rail's decision in respect of Bids for the December 2005 Timetable (settled out of court)
TTP21 (July 05) Great Western Trains Network Rail's decision to propose amendments to the Rules of the Route 2004/05 for weeks 41-44 (settled out of court)
TTP22 (July 05) English Welsh & Scottish Railway Network Rail's decision in respect of Bids for the December 2005 Timetable (settled out of court)
TTP23 (July 05) Freightliner Heavy Haul Network Rail's decision in respect of Bids for the December 2005 Timetable (settled out of court)
TTP24 (July 05) Freightliner Network Rail's decision in respect of Bids for the December 2005 Timetable (settled out of court)
TTP25 (July 05) Great Western Trains Network Rail's decision in respect of Bids for the December 2005 Timetable (settled out of court)
TTP26 (July 05) Midland Main line Network Rail's decision in respect of Bids for the December 2005 Timetable (settled out of court)
TTP27 (Aug 05) CrossCountry Trains Network Rail's decision to propose amendments to Rules of the Route 2004/05 for weeks 29-34 (settled out of court)
TTP28 (Aug 05) Freightliner Heavy Haul Network Rail's decision to propose amendments to Rules of the Route 2004/05 for weeks 23-25 (settled out of court)
TTP29 (Aug 05) English Welsh & Scottish Railway Network Rail's decision to propose amendments to Rules of the Route 2004/05 for weeks 23-25 (settled out of court)
TTP30 (July 05) First ScotRail Network Rail's decision in respect of changes (in Version 5) to the Rules of the Route for 2005/06 (settled out of court)
TTP31 (Aug 05) English Welsh & Scottish Railway Network Rail's decision in respect of changes (in batching document 6) to the Rules of the Route for 2005/06 (settled out of court)
TTP32 (Aug 05) First ScotRail Network Rail's decision in respect of changes (in batching document 6) to the Rules of the Route for 2005/06 (settled out of court)
TTP33 (Aug 05) Central Trains Network Rail's decision in respect of changes (in batching document 6) to the Rules of the Route for 2005/06 (settled out of court)
TTP34 (Aug 05) West Coast Trains Network Rail's decision in respect of changes (in batching document 6) to the Rules of the Route for 2005/06 (settled out of court)
TTP35 (Aug 05) CrossCountry Trains Network Rail's decision in respect of changes (in batching document 6) to the Rules of the Route for 2005/06 (settled out of court)
TTP36 (Sept 05) First/Keolis TPE Network Rail's decision in respect of changes (in batching document 6) to the Rules of the Route for 2005/06 (settled out of court)
TTP37 (Sept 05) First ScotRail Network Rail's decision in respect of changes (in batching document 7) to the Rules of the Route for 2005/06 (settled out of court)
TTP38 (Nov 05) Freightliner Network Rail's decision in respect of a change to the Rules of the Route 2005/06 for week 50 (settled out of court)
TTP39 (Nov 05) First ScotRail Network Rail's decision in respect of changes to the Rules of the Plan for 2006/07 (settled out of court)
TTP40 (Nov 05) CrossCountry Trains Network Rail's decision in respect of changes to the Rules of the Route 2005/06 for week 52 (settled out of court)
TTP41 (Dec 05) GB Railfreight Network Rail's decision in respect of a Spot Bid for 1M44 (settled out of court)
TTP42 (Dec 05) English Welsh & Scottish Railway Network Rail's decision in respect of changes (in batching document 8) to the Rules of the Route for 2005/06 (settled out of court)
TTP43 (Dec 05) First ScotRail Network Rail's decision in respect of changes to the Rules of the Plan for 2006/07 (settled out of court)
TTP44 (Dec 05) First ScotRail Network Rail's decision in respect of changes (in batching document 8) to the Rules of the Route for 2005/06 (settled out of court)
TTP45 (Dec 05) Great Western Trains Network Rail's decision in respect of changes to the Rules of the Plan for 2006/07 (settled out of court)
TTP46 (Dec 05) CrossCountry Trains Network Rail's decision in respect of changes (in batching document 8) to the Rules of the Route for 2005/06 (settled out of court)
TTP47 (Dec 05) Northern Rail Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP48 (Jan 06) First/Keolis TransPennine Express Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP49 (Jan 06) Arriva Trains Wales Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP50 (Jan 06) West Coast Trains Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP51 (Jan 06) Freightliner Heavy Haul Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP52 (Jan 06) Silverlink Tran Services Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP53 (Jan 06) First ScotRail Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP54 (Jan 06) Central Trains Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP55 (Jan 06) CrossCountry Trains Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP56 (Jan 06) Direct Rail Services Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP57 (Jan 06) English Welsh & Scottish Railway Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2007/08 (settled out of court)
TTP58 (Jan 06) Freightliner Heavy Haul Network Rail's decision in respect of Bids for the June 2006 Timetable (settled out of court)
TTP59 (Jan 06) Freightliner Network Rail's decision in respect of Bids for the June 2006 Timetable (settled out of court)
TTP60 (Jan 06) First ScotRail Network Rail's decision in respect of Bids for the June 2006 Timetable (settled out of court)
TTP61 (Jan 06) English Welsh & Scottish Railway Network Rail's decision in respect of Bids for the June 2006 Timetable (settled out of court)
TTP62 (Feb 06) CrossCountry Trains Network Rail's decision on changes to the Rules of the Route for 2005/06 between Wilmslow and Slade Lane Jcn in weeks 11-16 (settled out of court)
TTP63 (Feb 06) West Coast Trains Network Rail's decision on changes to the Rules of the Route for 2005/06 between Wilmslow and Slade Lane Jcn in weeks 11-16 (settled out of court)
TTP64 (Feb 06) Northern Rail Network Rail's decision on changes to the Rules of the Route for 2005/06 between Wilmslow and Slade Lane Jcn in weeks 11-16 (settled out of court)
TTP65 (Feb 06) CrossCountry Trains Network Rail's decision on changes to Section 7 of the Rules of the Route for 2005/06 (settled out of court)
TTP66 Hearing on 06.09.06 deferred Freightliner Heavy Haul Network Rail's decision to change the Rules of the Route for 2005/06 at Dudding Hill - in weeks 9, 20 & 22 (settled out of court)
TTP67 (Mar 06) New Southern Railway Network Rail's decision to change the Rules of the Route for 2005/06 in weeks 24-28 (settled out of court)
TTP68 TTP68 Hearing on 06.09.06 deferred until 19.10.06 Direct Rail Services Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2
TTP69 (Mar 06) London & South Eastern Railway Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP70 (Mar 06) First ScotRail Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP71 (Mar 06) Central Trains Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP72 (Mar 06) Arriva Trains Wales Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP73 (Mar 06) Freightliner Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP74 (Mar 06) GB Railfreight Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP75 (Mar 06) CrossCountry Trains Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP76 (Mar 06) Thameslink Rail Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP77 (Mar 06) Heathrow Connect Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP78 (Mar 06) New Southern Railway Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP79 (Apr 06) English Welsh & Scottish Railway Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP80 (Apr 06) Northern Rail Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP81 (Apr 06) Silverlink Train Services Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 2 (settled out of court)
TTP82 (May 06) New Southern Railway Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 3 (settled out of court)
TTP83 (May 06) First Great Western Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 3 (settled out of court)
TTP84 (July 06) English Welsh & Scottish Railway Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 4 (settled out of court)
TTP85 (July 06) Great North Eastern Railway Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 4 (settled out of court)
TTP86 (July 06) First Great Western Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 4 (settled out of court)
TTP87 (July 06) First ScotRail Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 4 (settled out of court)
TTP88 (July 06) Heathrow Connect Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 4 (settled out of court)
TTP89 (July 06) Central Trains Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 4 (settled out of court)
TTP90 (July 06) CrossCountry Trains Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 4 (settled out of court)
TTP91 (July 06) New Southern Railway Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Version 4 (settled out of court)
TTP92 (July 06) First ScotRail Network Rail's Offer for the Principal Timetable December 2006 (settled out of court)
TTP93 (July 06) English Welsh & Scottish Railway Network Rail's Offer for the Principal Timetable December 2006 (settled out of court)
TTP94 (July 06) Heathrow Connect Network Rail's Offer for the Principal Timetable December 2006 (settled out of court)
TTP95A TTP95A 08.09.06 First Greater Western Network Rail's Offer for the Principal Timetable December 2006 Redhill - Gatwick services
TTP95B TTP95B 08.09.06 First Greater Western Network Rail's Offer for the Principal Timetable December 2006: Paddington Slough services
TTP96 Hearing set to resume on 26.10.06 but then deferred; parties subsequently settled Great North Eastern Railway Network Rail's Offer for the Principal Timetable December 2006 (ORR's decision re locus) (settled out of court)
TTP97 (July 06) Freightliner Network Rail's Offer for the Principal Timetable December 2006 (settled out of court)
TTP98 (July 06) Freightliner Heavy Haul Network Rail's Offer for the Principal Timetable December 2006 (settled out of court)
TTP99 (July 06) Grand Central Railway Network Rail's Offer for the Principal Timetable December 2006 (settled out of court)
TTP100 TTP100 24.08.06 First Greater Western A Network Rail Offer in accordance with Condition D4.8
TTP101 (July 06) Hull Trains Network Rail's Offer for the Principal Timetable December 2006 (settled out of court)
TTP102 TTP102TTP102 06.09.06 Freightliner Heavy Haul and English Welsh & Scottish Railway Network Rail's proposal to take a disruptive possession at short notice. Freightliner and English Welsh & Scottish Railways lodged an appeal with the ORR against the Panel's decision. In February 2007 ORR delivered its judgement, upholding the appeal.
TTP103 (Sept 06) CrossCountry Trains Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Batch 9 document (settled out of court)
TTP104 (Sept 06) GNER Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Batch 9 document (settled out of court)
TTP105 (Sept 06) Northern Rail Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Batch 9 document (settled out of court)
TTP106 (Sept 06) Central Trains Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Batch 9 document (settled out of court)
TTP107 (Sept 06) First ScotRail Network Rail's decision in respect of changes to the Rules of the Route for 2006/07 Batch 9 document (settled out of court)
TTP108 (Oct 06) CrossCountry Trains Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2008 (settled out of court)
TTP109 (Nov 06) Freightliner Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2008 (withdrawn by referrer)
TTP110 (Nov 06) English Welsh & Scottish Railway Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2008 (withdrawn by referrer)
TTP111 (Nov 06) First ScotRail Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2008 (settled out of court)
TTP112 (Nov 06) West Coast Trains Network Rail's proposals in a Final Possession Strategy Notice for WCRM Enhancements and Renewals 2008 (settled out of court)
TTP113 (Nov 06) West Coast Trains Network Rail's proposal to change the Rules of the Route for Period D' 2007 Manchester Crewe (settled out of court)
TTP114 (Dec 06) Northern Rail Network Rail's proposals for the Rules of the Route 2007 Version 4.1 (settled out of court)
TTP115 (Dec 06) First ScotRail Network Rail's Offer for the Subsidiary Timetable May 2007 (settled out of court)
TTP116 (Jan 07) English Welsh & Scottish Railway Network Rail's Offer for the Subsidiary Timetable May 2007 (settled out of court)
TTP117 (Jan 07) Freightliner Network Rail's Offer for the Subsidiary Timetable May 2007 (settled out of court)
TTP118 (Jan 07) Freightliner Heavy Haul Network Rail's Offer for the Subsidiary Timetable May 2007 (settled out of court)
TTP119 (Jan 07) English Welsh & Scottish Railway Network Rail's proposals for the Rules of the Plan 2008 (settled out of court)
TTP120 (Jan 07) First ScotRail Network Rail's proposals for the Rules of the Plan 2008 (settled out of court)
TTP121 (Mar 07) English Welsh & Scottish Railway Network Rail's proposals for the Rules of the Route 2007 (weeks 29/30: Crewe North Preston Brook Tunnel) (settled out of court)
TTP122 (Mar 07) Freightliner Network Rail's proposals for the Rules of the Route 2007 (weeks 29/30: Crewe North Preston Brook Tunnel) (settled out of court)
TTP123 (Mar 07) Freightliner Network Rail's proposed Rules of the Route 2007-08: Version 3 (withdrawn by referrer)
TTP124 (Mar 07) Central Trains Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP125 (Mar 07) Freightliner Heavy Haul Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP126 (Mar 07) Silverlink Train Services Network Rail's proposed Rules of the Route 2007-08: Version 3 (panel jurisdiction changed now ADP27)
TTP127 (Mar 07) c2c Rail Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP128 (Mar 07) English Welsh & Scottish Railway Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP129 (Mar 07) London South Eastern Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP130 (Mar 07) Eurostar (U.K.) Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP131 (Mar 07) First ScotRail Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP132 (Mar 07) Arriva Trains Wales Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP133 (Mar 07) The Chiltern Railway Co. Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP134 (Mar 07) London Eastern Railway Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP135 (Mar 07) Northern Rail Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP136 (Mar 07) Direct Rail Services Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP137 (Mar 07) Great North Eastern Railway Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP138 (Mar 07) First Great Western Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP139 (Mar 07) GB Railfreight Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP140 (Mar 07) CrossCountry Trains Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP141 (Mar 07) New Southern Railway Network Rail's proposed Rules of the Route 2007-08: Version 3 (settled out of court)
TTP142 (Apr 07) CrossCountry Trains Network Rail's proposed amendment to Rules of the Route 2007: Weeks 29/30 at Gloucester (settled out of court)
TTP143 (Apr 07) First Great Western Network Rail's proposed amendment to Rules of the Route 2007 Weeks 29/30 at Gloucester (settled out of court)
TTP144 (May 07) Central Trains Network Rail's proposed supplemental' amendments to Rules of the Route 2007-08: (settled out of court)
TTP145 (May 07) CrossCountry Trains Network Rail's proposed supplemental' amendments to Rules of the Route 2007-08: (settled out of court)
TTP146 (May 07) English Welsh & Scottish Railway Network Rail's proposed supplemental' amendments to Rules of the Route 2007-08 (settled out of court)
TTP147 (May 07) First ScotRail Network Rail's proposed supplemental' amendments to Rules of the Route 2007-08 (settled out of court)
TTP148 (June 07) First Great Western Network Rail's proposed amendment to Rules of the Route 2007: Week 39 at Airport Jn (settled out of court)
TTP149 (July 07) CrossCountry Trains Network Rail's Offer for the Principal Timetable December 2007 (settled out of court)
TTP150 (July 07) London Eastern Railway Network Rail's decision regarding requirement for a Possession Strategy Notice for Colchester Clacton resignalling works (settled out of court)
TTP151 (July 07) English Welsh & Scottish Railway Network Rail's Offer for the Principal Timetable December 2007 (settled out of court)
TTP152 (July 07) Freightliner Heavy Haul Network Rail's Offer for the Principal Timetable December 2007 (settled out of court)
TTP153 (July 07) Freightliner Network Rail's Offer for the Principal Timetable December 2007 (settled out of court)
TTP154 (July 07) First Great Western Network Rail's Offer for the Principal Timetable December 2007 (settled out of court)
TTP155 (July 07) First Great Western Network Rail's proposed amendment to Rules of the Route 2007: Week 19 between Wootton Bassett and Narroways Hill Jn (settled out of court)
TTP156 (July 07) First ScotRail Network Rail's proposed Rules of the Plan 2008: Version 4 (settled out of court)
TTP157 (July 07) English Welsh & Scottish Railway Network Rail's proposals for Rules of the Plan 2007 (week 32: Kilsby North Rugby North Jn) (settled out of court)
TTP158 (July 07) English Welsh & Scottish Railway Network Rail's proposals for Rules of the Plan 2007 (week 34: Ely North Jn Peterborough) (settled out of court)
TTP159 (August 07) English Welsh & Scottish Railway Network Rail's proposals for Rules of the Plan 2007 (week 34: Severn Bridge Jn Marsh Brook LC and at Sutton Bridge Jn) (settled out of court)
TTP160 (Sept 07) First ScotRail Network Rail's proposed Rules of the Route 2008: Version 6 (settled out of court)
TTP161 (Sept 07) English Welsh & Scottish Railway Network Rail's proposed Rules of the Route 2008: Version 6 (withdrawn by referrer)
TTP162 (Sept 07) Freightliner Network Rail's proposed Rules of the Route 2008: Version 6 (settled out of court)
TTP163 (Sept 07) Freightliner Heavy Haul Network Rail's proposals for Rules of the Plan 2007 (week 34: Severn Bridge Jn Marsh Brook LC and at Sutton Bridge Jn) (settled out of court)
TTP164 (Sept 07) CrossCountry Trains Network Rail's proposed Rules of the Route 2008: Version 6 (settled out of court)
TTP165 (Sept 07) Freightliner Heavy Haul Network Rail's proposed Rules of the Route 2008: Version 6 (settled out of court)
TTP166 (Sept 07) CrossCountry Trains Network Rail's proposals for Rules of the Plan 2007 (weeks 31 and 32: Crewe Cheadle Hulme area) (settled out of court)
TTP167 (Oct 07) West Coast Trains Network Rail's supplemental proposals for Rules of the Route 2008, WCRM Rugby Nuneaton area (settled out of court)
TTP168 (Oct 07) English Welsh & Scottish Railway Network Rail's supplemental proposals for Rules of the Route 2008, WCRM Rugby Nuneaton area (withdrawn by referrer)
TTP169 (Oct 07) Freightliner Network Rail's supplemental proposals for Rules of the Route 2008, WCRM Rugby Nuneaton area (withdrawn by referrer)
TTP170 (Oct 07) GB Railfreight Network Rail's supplemental proposals for Rules of the Route 2008, WCRM Rugby Nuneaton area (settled out of court)
TTP171 (Oct 07) Central Trains Network Rail's supplemental proposals for Rules of the Route 2008, WCRM Rugby Nuneaton area (withdrawn by referrer)
TTP172 (Nov 07) English Welsh & Scottish Railway Network Rail's proposals for additional possessions, Week 35, Rugby Brandon (settled out of court)
TTP173 (Nov 07) English Welsh & Scottish Railway Network Rail's proposals for additional possessions, Week 39-51, Rugby and Trent Valley areas (settled out of court)
TTP174 (Nov 07) English Welsh & Scottish Railway Network Rail's proposals for additional possessions, Week 22 blockade in Stoke-on-Trent area (withdrawn by referrer)
TTP175 (Nov 07) English Welsh & Scottish Railway Network Rail's proposals for additional possessions, Week 18 in Northampton area (settled out of court)
TTP176 (Nov 07) English Welsh & Scottish Railway Network Rail's proposals for additional possessions during 2008 in Northampton/Daventry and Trent Valley areas (settled out of court)
TTP177 (Nov 07) English Welsh & Scottish Railway Network Rail's Possession Strategy Notice, WCRM, Dec 2008 Dec 2010 (withdrawn by referrer)
TTP178 (Nov 07) Freightliner Network Rail's Rules of the Route Decisions Week 39, Hillmorton Rugby (settled out of court)
TTP179 (Nov 07) Freightliner Network Rail's Rules of the Route Decisions Week 52, Atherstone Rugeley Trent Valley Jn (withdrawn by referrer)
TTP180 (Nov 07) Freightliner Network Rail's Rules of the Route Decisions Week 18, Northampton area (withdrawn by referrer)
TTP181 (Nov 07) CrossCountry Trains Network Rail's proposals for additional possessions, Week 51, Hinckley Nuneaton Abbey (settled out of court)
TTP182 (Nov 07) West Coast Trains Network Rail's proposals for additional possessions between Rugby Trent Valley Jn and Armitage Jn (settled out of court)
TTP183 (Nov 07) CrossCountry Trains Network Rail's Possession Strategy Notice, WCRM, Dec 2008 Dec 2010 (settled out of court)
TTP184 (Nov 07) West Coast Trains Network Rail's Possession Strategy Notice, WCRM (Bletchley area) , Dec 2008 - Dec 2010 (settled out of court)
TTP185 (Nov 07) English Welsh & Scottish Railway Network Rail's Supplemental 2008 Rules of the Route Decisions for LNE (settled out of court)
TTP186 (Nov 07) XC Trains Network Rail's Supplemental 2008 Rules of the Route Decisions for LNE (settled out of court)
TTP187 (Nov 07) London & Birmingham Railway Network Rail's Possession Strategy Notice, WCRM, Dec 2008 - Dec 2010 (settled out of court)
TTP188 (Nov 07) Great North Eastern Railway Network Rail's Supplemental 2008 Rules of the Route Decisions for LNE (settled out of court)
TTP189 (Nov 07) First Greater Western Network Rail's Supplemental 2008 Rules of the Route Decisions (settled out of court)
TTP190 (Nov 07) New Southern Railway Network Rail's Supplemental 2008 Rules of the Route Decisions (settled out of court)
TTP191 (Dec 07) West Coast Trains Network Rail's Amendment proposal, Week 44, Hanslope - Hillmorton (settled out of court)
TTP192 (Dec 07) West Coast Trains Network Rail's Amendment proposal, Week 8, Hillmorton Brandon (settled out of court)
TTP193 (Dec 07) XC Trains Network Rail's decision regarding train slots, Periods D1/D2 2008 (settled out of court)
TTP194 TTP194 21.02.08 West Coast Trains Network Rail's extension of engineering access, Week 40, Hanslope Rugby Trent Valley
TTP195 TTP195 21.02.08 EWS Network Rail's extension of engineering access, Week 40, Rugby area
TTP196 (Dec 07) Freightliner Network Rail's 2008 Subsidiary Timetable Final Offer (settled out of court)
TTP197 (Jan 08) EWS Network Rail's 2008 Subsidiary Timetable Final Offer (settled out of court)
TTP198 (Jan 08) Freightliner Heavy Haul Network Rail's 2008 Subsidiary Timetable Final Offer (settled out of court)
TTP199 (Jan 08) First ScotRail Network Rail's 2008 Subsidiary Timetable Final Offer (settled out of court)
TTP200 (Jan 08) English Welsh & Scottish Railway Network Rail's decision regarding a possession between Gretna Jn and Annan, Weeks 17 19 (settled out of court)
TTP201 (Jan 08) English Welsh & Scottish Railway Network Rail's decision regarding a possession between Gretna Jn and Annan, Week 43 (settled out of court)
TTP202 (Jan 08) First Greater Western Network Rail's 2008 Subsidiary Timetable Final Offer (settled out of court)
TTP203 (Jan 08) First ScotRail Network Rail's proposals for the Rules of the Plan 2009 (settled out of court)
TTP204 (Jan 08) Freightliner Heavy Haul Network Rail's decision regarding a possession between Gretna Jn and Annan, Week 43 (settled out of court)
TTP205 (Jan 08) Freightliner Heavy Haul Network Rail's decision regarding possessions between Ulceby North Jn and Humber Road Jn, Weeks 46 49 (settled out of court)
TTP206 (Feb 08) First Capital Connect Network Rail's decision regarding Spot Bid for services to call at new Mitcham Eastfields station (settled out of court)
TTP207 (Mar 08) First ScotRail Network Rail's proposals for the Rules of the plan 2009, Version 2 (LNW/LNE) (settled out of court)
TTP208 (Mar 08) First ScotRail Network Rail's proposals for the Rules of the plan 2009, Version 2 (Scotland) (settled out of court)
TTP209 (Mar 08) English Welsh & Scottish Railway Network Rail's decisions regarding possessions in the Grantham area, Weeks 11 14 (settled out of court)
TTP210 TTP210TTP210 08.05.08 7 Operators see below Network Rail's Final West Coast Route Modernisation Decision document (NAUM-30) Network Rail lodged an appeal with the ORR against the Panel's decisions but the appeal was subsequently withdrawn
TTP210-WCT 08.05.08 West Coast Trains
TTP210-LM 08.05.08 London & Birmingham Railway
TTP210-FKTP 08.05.08 First/Keolis TransPennine
TTP210-EWS 08.05.08 English Welsh & Scottish Railway
TTP210-FL 08.05.08 Freightliner
TTP210-GBRf 08.05.08 GB Railfreight
TTP210-XCT (Apr 08) XC Trains (settled out of court)
TTP211 (Apr 08) New Southern Railway Network Rail's Rules of the Plan decisions for 2009 (settled out of court)
TTP212 (Apr 08) Arriva Trains Wales Network Rail's Rules of the Plan decisions for 2009 (referred back for reconsideration of applicable process and Panel jurisdiction)
TTP213 (Apr 08) English Welsh & Scottish Railway Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP214 (Apr 08) Freightliner Heavy Haul Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP215 (Apr 08) Freightliner Network Rail's proposed Rules of the Route 2008-09: Version 3 (withdrawn by referrer)
TTP216 (Apr 08) West Coast Trains Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP217 (Apr 08) First Greater Western Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP218 (Apr 08) Northern Rail Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP219 (Apr 08) New Southern Railway Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP220 (Apr 08) Heathrow Express Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP221 (Apr 08) London & South Eastern Railway Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP222 TTP222 05.11.08 Direct Rail Services Network Rail's proposed Rules of the Route 2008-09: Version 3
TTP223 (Apr 08) XC Trains Network Rail's proposed Rules of the Route 2008-09: Version 3 (withdrawn by referrer)
TTP224 (Apr 08) Chiltern Railways Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP225 (Apr 08) London Eastern Railway Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP226 (Apr 08) Arriva Trains Wales Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP227 (Apr 08) First/Keolis TransPennine Network Rail's proposed Rules of the Route 2008-09: Version 3 (withdrawn by referrer)
TTP228 (Apr 08) London & Birmingham Railway Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP229 (Apr 08) Stagecoach South Western Trains Network Rail's proposed Rules of the Route 2008-09: Version 3 (withdrawn by referrer)
TTP230 (Apr 08) First ScotRail Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP231 (Apr 08) Eurostar (UK) Network Rail's proposed Rules of the Route 2008-09: Version 3 (withdrawn by referrer)
TTP232 (Apr 08) NXEC Trains Network Rail's proposed Rules of the Route 2008-09: Version 3 (settled out of court)
TTP233 (Apr 08) Freightliner Heavy Haul Network Rail's decision regarding possessions in the Sheffield area, Week 8/9 (settled out of court)
TTP234 (Apr 08) Northern Rail Network Rail's Rules of the Plan decisions for 2009 (settled out of court)
TTP235 (May 08) Freightliner Heavy Haul Network Rail's Timetable Offer in relation to Hampstead Tunnel Blockade 2008 (settled out of court)
TTP236 (May 08) English Welsh & Scottish Railway Network Rail's Timetable Offer in relation to Hampstead Tunnel Blockade 2008 (settled out of court)
TTP237 (June 08) XC Trains Network Rail's Offer for Week 22 (WThFO) between Crewe and Manchester (settled out of court)
TTP238 (July 08) Freightliner Network Rail's Offer for the Principal Timetable, December 2008 (settled out of court)
TTP239 (July 08) First Greater Western Network Rail's Offer for the Principal Timetable, December 2008 (settled out of court)
TTP240 (July 08) c2c Rail Network Rail's Offer for the Principal Timetable, December 2008 (settled out of court)
TTP241 (July 08) Northern Rail Network Rail's Offer for the Principal Timetable, December 2008 (settled out of court)
TTP242 TTP242 22.10.08 First ScotRail Network Rail's Offer for the Principal Timetable, December 2008ORR's decision not to hear an appeal
TTP243 (July 08) New Southern Railway Network Rail's Offer for the Principal Timetable, December 2008 (Panel jurisdiction changed now ADP33)
TTP244 TTP244 08.09.08 Wrexham Shropshire & Marylebone Railway Network Rail's Offer for the Principal Timetable, December 2008Wrexham Shropshire & Marylebone Railway lodged an appeal with the ORR against the Panel's decisions ORR's first determinationORR's second determination
TTP245 (July 08) Renaissance Trains for Glasgow Trains Network Rail's Offer for the Principal Timetable, December 2008 (withdrawn by referrer)
TTP246 (Aug 08) Arriva Trains Wales Network Rail's supplemental Rules of the Route 2008-09 decision for Gobowen (Excl.) Saltney Jn (withdrawn by referrer)
TTP247 (Sept 08) English Welsh & Scottish Railway Network Rail's proposed Rules of the Route 2009: Version 6 (settled out of court)
TTP248 (Sept 08) Freightliner Heavy Haul Network Rail's proposed Rules of the Route 2009: Version 6 (settled out of court)
TTP249 (Sept 08) New Southern Railway Network Rail's proposed Rules of the Route 2009: Version 6 (settled out of court)
TTP250 (Sept 08) Freightliner Network Rail's proposed Rules of the Route 2009: Version 6 (withdrawn by referrer)
TTP251 (Sept 08) Northern Rail Network Rail's proposed Rules of the Route 2009: Version 6 (settled out of court)
TTP252 (Sept 08) NXEC Trains Network Rail's proposed Rules of the Route 2009: Version 6 (settled out of court)
TTP253 (Sept 08) Arriva Trains Wales Network Rail's proposed Rules of the Route 2009: Version 6 (settled out of court)
TTP254 (Oct 08) English Welsh & Scottish Railway Network Rail's decisions regarding additional possessions in the Aylesbury area, Week 34 (settled out of court)
TTP255 (Dec 08) English Welsh & Scottish Railway Network Rail's Offer for the Subsidiary Timetable, May 2009 (settled out of court)
TTP256 (Jan 09) First Greater Western Network Rail's Offer for the Subsidiary Timetable, May 2009 (settled out of court)
TTP257 TTP257 20.01.09 GB Railfreight Network Rail's rejection of part of a Spot Bid
TTP258 (Jan 09) Freightliner Heavy Haul Network Rail's Offer for the Subsidiary Timetable, May 2009 (settled out of court)
TTP259 (Mar 09) New Southern Railway Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP260 (Mar 09) First ScotRail Network Rail's Rules of the Plan decisions for 2009-10: Version 2 (settled out of court)
TTP261 (Mar 09) Wrexham Shropshire & Marylebone Railway Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP262 (Mar 09) Chiltern Railways Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP263 (Mar 09) Freightliner Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP264 (Mar 09) Freightliner Heavy Haul Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP265 (Mar 09) First ScotRail Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP266 (Mar 09) DB Schenker Rail (UK) Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP267 (Mar 09) First Greater Western Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP268 (Mar 09) London Eastern Railway Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP269 (Mar 09) East Midlands Trains Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP270 (Mar 09) c2c Rail Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP271 TTP271 28.04.09 West Coast Trains Network Rail's Rules of the Route decisions for 2009-10: Version 2
TTP272 (Mar 09) Arriva Trains Wales Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP273 (Mar 09) XC Trains Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP274 (Mar 09) London & Birmingham Railway Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP275 (Mar 09) First/Keolis TransPennine Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP276 (Mar 09) NXEC Trains Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP277 (Mar 09) Northern Rail Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP278 (Mar 09) First Capital Connect Network Rail's Rules of the Route decisions for 2009-10: Version 2 (settled out of court)
TTP279 (Apr 09) West Coast Trains Network Rail's Timetable Offer for 30 May 2009 (settled out of court)
TTP280 (June 09) First Greater Western Network Rail's Final Possession Strategy Notice for CrossRail 2011-12 (settled out of court)
TTP281 (July 09) DB Schenker Rail (UK) Network Rail's Offer for the Principal Timetable, December 2009 (settled out of court)
TTP282 (July 09) London & Birmingham Railway Network Rail's Offer for the Principal Timetable, December 2009 (settled out of court)
TTP283 (July 09) Freightliner Network Rail's Offer for the Principal Timetable, December 2009 (settled out of court)
TTP284 (July 09) Freightliner Heavy Haul Network Rail's Offer for the Principal Timetable, December 2009 (settled out of court)
TTP285 (July 09) First Greater Western Network Rail's Offer for the Principal Timetable, December 2009 (settled out of court)
TTP286 (July 09) First ScotRail Network Rail's Offer for the Principal Timetable, December 2009 (settled out of court)
TTP287 (Aug 09) DB Schenker Rail (UK) Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP288 (Aug 09) New Southern Railway Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP289 (Aug 09) First Capital Connect Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP290 13.11.09 NX EC Trains Network Rail's Rules of the Route decisions for 2009-10: Version 4 (Hearing cancelled - settled out of court )
TTP291 (Aug 09) West Coast Trains Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP292 (Aug 09) Freightliner Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP293 (Aug 09) Heathrow Express Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP294 (Aug 09) XC Trains Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP295 (Aug 09) London & Birmingham Railway Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP296 (Aug 09) First Greater Western Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP297 (Aug 09) First/Keolis TransPennine Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP298 (Aug 09) Arriva Trains Wales Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP299 (Aug 09) GB Railfreight Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP300 (Aug 09) East Midlands Trains Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP301 (Aug 09) Northern Rail Network Rail's Rules of the Route decisions for 2009-10: Version 4 (settled out of court)
TTP302 30.11.09 First ScotRail Network Rail's Rules of the Route decisions for 2009-10: Version 4 (as relating to arrangements during S&C renewals at Mossend East) (settled out of court)
TTP303 (Aug 09) GB Railfreight Network Rail's Rules of the Plan decisions for 2009-10: Version 4 (settled out of court)
TTP304 (Aug 09) First ScotRail Network Rail's Rules of the Plan decisions for 2009-10: Version 4 (settled out of court)
TTP305 (Aug 09) First ScotRail Network Rail's Rules of the Route decisions for 2009-10: Version 4 (as relating to diversion of sleeper train services) (Panel jurisdiction changed now ADP40)
TTP306 27.01.10 Freightliner Network Rail's Final Possession Strategy Notice for Water Orton 2011-12 (settled out of court)
TTP307 27.01.10 DB Schenker Rail (UK) Network Rail's Final Possession Strategy Notice for Water Orton 2011-12 (settled out of court)
TTP308 27.01.10 West Coast Trains Network Rail's Final Possession Strategy Notice for Water Orton 2011-12 (settled out of court)
TTP309 27.01.10 Freightliner Heavy Haul Network Rail's Final Possession Strategy Notice for Water Orton 2011-12 (settled out of court)
TTP310 TTP310 27.01.10 XC Trains Network Rail's Final Possession Strategy Notice for Water Orton 2011-12
TTP311 27.01.10 London & Birmingham Railway Network Rail's Final Possession Strategy Notice for Water Orton 2011-12 (settled out of court)
TTP312 TTP312 27.01.10 GB Railfreight Network Rail's Final Possession Strategy Notice for Water Orton 2011-12
TTP313 (Nov 09) First Capital Connect Network's Rail's supplemental timetable revision items for 2010 (settled out of court)
TTP314 (Nov 09) DB Schenker Rail (UK) Network Rail's additional possession items for 2010 (Gargrave Carlisle South Jn route) (settled out of court)
TTP315 (Nov 09) Freightliner Heavy Haul Network Rail's additional possession items for 2010 (Gargrave Carlisle South Jn route) (settled out of court)
TTP316 (Nov 09) DB Schenker Rail (UK) Network Rail's additional possession items for 2010 (Gretna Jn Glasgow Central via Kilmarnock route) (settled out of court)
TTP317 TTP317TTP317TTP317TTP317 17.12.09 First ScotRail Diversion of sleeper train services via East Coast Main Line during Weeks 10 - 12, 2010First ScotRail appealed to ORR against the determination of the Panel hearing
TTP318 (Dec 09) Freightliner Heavy Haul Rejection by Network Rail of bids associated with trains planned to start or terminate at Mossend Down Yard Reception Sidings (settled out of court)
TTP319 (Dec 09) DB Schenker Rail (UK) Network Rail's offer for the Subsidiary Timetable 2010 (settled out of court)
TTP320 (Jan 10) Northern Rail Network Rail's offer for the Subsidiary Timetable 2010 (settled out of court)
TTP321 (Jan 10) Southern Railway Network Rail's offer for the Subsidiary Timetable 2010 (withdrawn by referrer)
TTP322 (Jan 10) First Greater Western Network Rail's offer for the Subsidiary Timetable 2010 (settled out of court)
TTP323 (Jan 10) Freightliner Heavy Haul Network Rail's offer for the Subsidiary Timetable 2010 (settled out of court)
TTP324 TTP324 29.03.10 West Coast Trains Network Rail's offer for the Subsidiary Timetable 2010
TTP325 (Feb 10) First ScotRail Network Rail's Rules of the Plan decisions for 2010-11: version 2 (settled out of court)
TTP326 (Feb 10) Southern Railway etwork Rail's Rules of the Route decisions for 2010-11: version 2 (settled out of court)
TTP327 (Feb 10) Freightliner Network Rail's Rules of the Route decisions for 2010-11: version 2 (settled out of court)
TTP328 (Feb 10) London Underground Network Rail's Rules of the Route decisions for 2010-11: version 2 (settled out of court)
TTP329 (Feb 10) DB Schenker Rail (UK) Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP330 (Feb 10) Heathrow Express Network Rail's Rules of the Route decisions for 2010-11: version 2 (settled out of court)
TTP331 (Feb 10) Arriva Trains Wales Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP332 (Feb 10) First Capital Connect Network Rail's Rules of the Route decisions for 2010-11: version 2 (settled out of court)
TTP333 (Feb 10) c2c Rail Network Rail's Rules of the Route decisions for 2010-11: version 2 (settled out of court)
TTP334 (Feb 10) XC Trains Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP335 (Feb 10) First ScotRail Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP336 (Feb 10) London Eastern Railway Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP337 TTP337TTP337 20.01.11 West Coast Trains Network Rail's Rules of the Route decisions for 2011-12: version 2 (Following the hearing and further discussion with Network Rail, West Coast Trains withdrew the Coventry Corridor element of the dispute) West Coast Trains appealed to ORR against the determination of the Panel hearingORR's appeal determination
TTP338 (Feb 10) GB Railfreight Network Rail's Rules of the Route decisions for 2010-11: version 2 (settled out of court)
TTP339 (Feb 10) First/Keolis Transpennine Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP340 (Feb 10) First Greater Western Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP341 (Feb 10) Northern Rail Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP342 (Feb 10) East Coast Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP343 (Feb 10) East Midlands Trains Network Rail's Rules of the Route decisions for 2011-12: version 2 (settled out of court)
TTP344 (Apr 10) XC Trains Network Rail's Final Possession Strategy Notice for Water Orton 2011-12 (30 March 2010 issue) (settled out of court)
TTP345 (Jul 10) First Greater Western Network Rail's proposed relevant dates for the 2012 Timetable (settled out of court)
TTP346 (Jul 10) First Capital Connect Network Rail's proposed relevant dates for the 2012 Timetable (settled out of court)
TTP347 (Jul 10) DB Schenker Rail (UK) Network Rail's Final Possession Strategy Notice for Bletchley Remodelling 2012 & 2013 (settled out of court)
TTP348 (Jul 10) West Coast Trains Network Rail's Final Possession Strategy Notice for Bletchley Remodelling 2012 & 2013 (settled out of court)
TTP349 (Jul 10) DB Schenker Rail (UK) Network Rail's Offer for the Principal Timetable, December 2010 (settled out of court)
TTP350 TTP350 23.08.10 Southern Railway Network Rail's Offer for the Principal Timetable, December 2010
TTP351 (Jul 10) Freightliner Heavy Haul Network Rail's Offer for the Principal Timetable, December 2010 (settled out of court)
TTP352 (Jul 10) West Coast Trains Network Rail's Offer for the Principal Timetable, December 2010 (settled out of court)
TTP353 (Jul 10) GB Railfreight Network Rail's Offer for the Principal Timetable, December 2010 (settled out of court)
TTP354 (Jul 10) Freightliner Network Rail's Offer for the Principal Timetable, December 2010 (settled out of court)
TTP355 (Jul 10) First Greater Western Network Rail's Offer for the Principal Timetable, December 2010 (settled out of court)
TTP356 TTP356 23.08.10 First Capital Connect Network Rail's Offer for the Principal Timetable, December 2010First Capital Connect appealed to ORR regarding the TTP determination but subsequently withdrew following issue of ORR's decision on the associated s22 application
TTP357 (Jul 10) DB Schenker Rail (UK) Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP358 (Jul 10) Southern Railway Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP359 TTP359TTP359 20.01.11 West Coast Trains Network Rail's Rules of the Route decisions for 2010-11: Version 4 (Following the hearing and further discussion with Network Rail, West Coast Trains withdrew the Coventry Corridor element of the dispute) West Coast Trains appealed to ORR against the determination of the Panel hearingORR's appeal determination
TTP360 (Jul 10) Arriva Trains Wales Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP361 (Jul 10) Southern Railway Network Rail's rejection of Spot Bids for the 2011 SX Timetable (settled out of court)
TTP362 (Jul 10) First Capital Connect Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP363 (Jul 10) London & Birmingham Railway Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP364 (Jul 10) XC Trains Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP365 (Jul 10) Stagecoach South Western Trains Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP366 (Jul 10) London & South Eastern Railway Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP367 (Jul 10) East Midlands Trains Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP368 (Jul 10) GB Railfreight Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP369 (Jul 10) East Coast Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP370 (Jul 10) First/Keolis Transpennine Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP371 TTP371TTP371 (Jul 10) Freightliner & Freightliner Heavy Haul Network Rail's Rules of the Plan decisions for 2010-11: Version 4Determined without oral hearingNetwork Rail appealed to ORR in respect of para. 5.1 of the determinationORR appeal determination
TTP372 (Jul 10) First ScotRail Network Rail's Offer for the Principal Timetable, December 2010 (settled out of court)
TTP373 (Jul 10) London Eastern Railway Network Rail's Rules of the Route decisions for 2010-11: Version 4 (settled out of court)
TTP374 (Aug 10) London Eastern Railway Network Rail's Final Possession Strategy Notice for CrossRail 2012-13 (settled out of court)
TTP375 TTP375 23.08.10 First Capital Connect Network Rail's acceptance of Spot Bids for the 2011 SX TimetableFirst Capital Connect appealed to ORR regarding the TTP determination but subsequently withdrew following issue of ORR's decision on the associated s22 application
TTP376 TTP376 29.09.10 Arriva Trains Wales Network Rail's Restrictions of Use in the Preston Brook Tunnel area, Weeks 45 50
TTP377 TTP377 29.09.10 Northern Rail Network Rail's Restrictions of Use, Armitage Jn to Preston Fylde Jn, Weeks 49 & 50
TTP378 (Sept 10) DB Schenker Rail (UK) Network Rail's Restrictions of Use, Chinley South Jn to Peak Forest South, Weeks 10 13, 2011 (settled out of court)
TTP379 (Nov 10) Freightliner Heavy Haul Network Rail's Restrictions of Use, Brindle Heath Sidings, Weeks 36 45 (settled out of court)
TTP380 (Dec 10) Freightliner Network Rail's Offer for the Subsidiary Timetable, May 2011 (settled out of court)
TTP381 (Dec 10) West Coast Trains Network Rail's Confirmed Period Possession Plan for Week 9, 2011 (settled out of court)
TTP382 TTP382TTP382 20.01.11 West Coast Trains Network Rail's Confirmed Period Possession Plan for Weeks 13 - 16, 2011 (Following the hearing and further discussion with Network Rail, West Coast Trains withdrew the Coventry Corridor element of the dispute) West Coast Trains appealed to ORR against the determination of the Panel hearingORR's appeal determination
TTP383 (Dec 10) West Coast Trains Network Rail's Offer for the Subsidiary Timetable, May 2011 (settled out of court)
TTP384 TTP384 29.03.11 First Capital Connect Network Rail's Offer for the Subsidiary Timetable, May 2011
TTP385 (Dec 10) First Greater Western Network Rail's Offer for the Subsidiary Timetable, May 2011 (settled out of court)
TTP386 (Dec 10) DB Schenker Rail (UK) Network Rail's Offer for the Subsidiary Timetable, May 2011 (settled out of court)
TTP387 (Dec 10) GB Railfreight Network Rail's Offer for the Subsidiary Timetable, May 2011 (settled out of court)
TTP388 (Dec 10) East Coast Network Rail's Offer for the Subsidiary Timetable, May 2011 (settled out of court)
TTP389 (Dec 10) Freightliner Heavy Haul Network Rail's Offer for the Subsidiary Timetable, May 2011 (settled out of court)
TTP390 (Feb 11) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP391 (Feb 11) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP392 (Feb 11) XC Trains Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP393 (Feb 11) London Eastern Railway Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP394 (Feb 11) Heathrow Express Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP395 (Feb 11) Freightliner Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP396 (Feb 11) First Greater Western Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP397 (Feb 11) GB Railfreight Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP398 (Feb 11) London & Birmingham Railway Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP399 (Feb 11) Arriva Trains Wales Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP400 (Feb 11) First ScotRail Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP401 (Feb 11) West Coast Trains Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP402 (Feb 11) East Coast Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP403 (Feb 11) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP404 (Feb 11) Stagecoach South Western Trains Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP405 (Feb 11) Southern Railway Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP406 (Feb 11) First Capital Connect Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP407 (Feb 11) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP408 (Feb 11) Northern Rail Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP409 (Feb 11) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2012, Version 2 (settled out of court)
TTP410 (Feb 11) Southern Railway Network Rail's Timetable Planning Rules decisions for 2012, Version 2 (settled out of court)
TTP411 (Feb 11) West Coast Trains Network Rail's Timetable Planning Rules decisions for 2012, Version 2 (settled out of court)
TTP412 (Feb 11) First ScotRail Network Rail's Timetable Planning Rules decisions for 2012, Version 2 (settled out of court)
TTP413 (Feb 11) Freightliner Network Rail's Timetable Planning Rules decisions for 2012, Version 2 (settled out of court)
TTP414 (Feb 11) Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2012, Version 2 (settled out of court)
TTP415 (Mar 11) Freightliner Network Rail's additional Timetable Planning Rules decisions for 2012, Version 2 (settled out of court)
TTP416 (Mar 11) Freightliner Heavy Haul Network Rail's additional Timetable Planning Rules decisions for 2012, Version 2 (settled out of court)
TTP417 (Mar 11) DB Schenker Rail (UK) Network Rail's additional Timetable Planning Rules decisions for 2012, Version 2 (settled out of court)
TTP418 (Apr 11) London Eastern Railway Network Rail's decision to amend timing allowances in the Timetable Planning Rules 2012, Version 2 (settled out of court)
TTP419 (May 11) Arriva Trains Wales Network Rail's Restriction of Use, Wrexham Central Dee Marsh Junction, Week 36 (settled out of court)
TTP420 (May 11) Arriva Trains Wales Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP421 (May 11) DB Schenker Rail (UK) Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP422 (May 11) Freightliner Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP423 (May 11) Freightliner Heavy Haul Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP424 (May 11) GB Railfreight Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP 425 (June 11) DB Regio Tyne & Wear Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP 426 (June 11) First/Keolis Transpennine Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP427 (June 11) Freightliner Heavy Haul Network Rail's decision to change Rules of the Route 2011 in relation to possession arrangements between Neasden Junction and Neasden South Junction, 12 - 28 August 2011 (settled out of court)
TTP428 (June 11) First Capital Connect Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP429 (June 11) Southern Railway Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP430 (June 11) Grand Central Railway Network Rail's decisions regarding the New Working Timetable Publication for 2012 (settled out of court)
TTP431 (July 11) DB Schenker Rail (UK) Network Rail's decisions amending the Engineering Access Statement for 2012, Version 2 (settled out of court)
TTP432 (July 11) Northern Rail Network Rail's decisions amending the Engineering Access Statement for 2012, Version 2 (settled out of court)
TTP433 (July 11) First Greater Western Network Rail's decision regarding Summer Saturday Seasonal Services dates 2012 (settled out of court)
TTP434 TTP434 27.02.12 West Coast Trains Network Rail's decisions amending the Engineering Access Statement for 2012, Version 2
TTP435 (Aug 11) London Eastern Railway Network Rail's Final Crossrail East Possession Strategy Notice 2013 (settled out of court)
TTP436 (Aug 11) London& South Eastern Railway Network Rail's Final Crossrail East Possession Strategy Notice 2013 (settled out of court)
TTP437 (Aug 11) GB Railfreight Network Rail's decisions regarding Restrictions of Use in Marylebone - Neasden area, Week 22 (settled out of court)
TTP438 (Aug 11) Freightliner Heavy Haul Network Rail's decisions regarding amendments to Engineering Access Statement 2012 in Weeks 18 20 (settled out of court)
TTP439 TTP439 10.10.11 West Coast Trains Network Rail's decisions amending Engineering Access Statement 2012, Weeks 41 & 42
TTP440 TTP440 10.10.11 First/Keolis Transpennine Network Rail's decisions amending Engineering Access Statement 2012, Weeks 41 & 42
TTP441 (Sept 11) West Coast Trains Network Rail's decision amending Engineering Access Statement 2012, Week 46 (settled out of court)
TTP442 (Nov 11) XC Trains Network Rail's decision amending Engineering Access Statement 2012, Week 40 (settled out of court)
TTP443 (Nov 11) West Coast Trains Network Rail's decision amending Engineering Access Statement 2012, Week 10 (settled out of court)
TTP444 (Nov 11) First Capital Connect Network Rail's decisions amending Engineering Access Statement 2012, Weeks 9 12 (settled out of court)
TTP445 (Nov 11) East Coast Network Rail's decisions amending Engineering Access Statement 2012, Weeks 9 12 (settled out of court)
TTP446 (Dec 11) Freightliner Heavy Haul Network Rail's decisions in 2012 New Working Timetable Publication, Weekends in Periods G & H (settled out of court)
TTP447 (Dec 11) DB Schenker Rail (UK) Network Rail's decisions in 2012 New Working Timetable Publication, Weekends in Periods G & H (settled out of court)
TTP448 (Dec 11) DB Schenker Rail (UK) Network Rail's decision amending Engineering Access Statement 2012, Week 48 (settled out of court)
TTP449 (Dec 11) Freightliner Heavy Haul Network Rail's decision amending Engineering Access Statement 2012, Week 48 (settled out of court)
TTP450 (Jan 12) First Capital Connect Network Rail's decisions amending Engineering Access Statement 2012, Weeks 13 16 (settled out of court)
TTP451 (Jan 12) East Coast Network Rail's decisions amending Engineering Access Statement 2012, Weeks 13 16 (settled out of court)
TTP452 (Feb 12) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP453 (Feb 12) Freightliner Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP454 (Feb 12) East Coast Network Rail's decisions amending Engineering Access Statement 2012, Weeks 21 24 (settled out of court)
TTP455 (Feb 12) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP456 (Feb 12) XC Trains Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP457 (Feb 12) First Greater Western Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP458 (Feb 12) First ScotRail Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP459 (Feb 12) Heathrow Express Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP460 (Feb 12) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP461 (Feb 12) First Capital Connect Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP462 (Feb 12) c2c Rail Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP463 (Feb 12) West Coast Trains Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP464 (Feb 12) GB Railfreight Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP465 (Feb 12) London & Birmingham Railway Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP466 (Feb 12) East Coast Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP467 (Feb 12) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP468 (Feb 12) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP469 (Feb 12) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP470 (Feb 12) Stagecoach South Western Trains Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP471 (Feb 12) Northern Rail Network Rail's Engineering Access Statement decisions for 2013, Version 2 (settled out of court)
TTP472 (Feb 12) First ScotRail Network Rail's Timetable Planning Rules decisions for 2013, Version 2 (settled out of court)
TTP473 (Feb 12) Abellio Greater Anglia Network Rail's Timetable Planning Rules decisions for 2013, Version 2 (settled out of court)
TTP474 (Feb 12) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2013, Version 2 (settled out of court)
TTP475 (Feb 12) Northern Rail Network Rail's decisions amending Engineering Access Statement 2012, Weeks 3, 5 & 8 (settled out of court)
TTP476 (Apr 12) West Coast Trains Network Rail's decisions amending the Engineering Access Statement for 2013, Version 2 (settled out of court)
TTP477 (Apr 12) Northern Rail Network Rail's decisions amending the Engineering Access Statement for 2013, Version 2 (settled out of court)
TTP478 (Apr 12) First Capital Connect Network Rail's decisions amending Engineering Access Statement 2012, Weeks 25 28 (settled out of court)
TTP479 (Apr 12) East Coast Network Rail's decisions amending Engineering Access Statement 2012, Weeks 25 28 (settled out of court)
TTP480 (Apr 12) Northern Rail Network Rail's decision amending Engineering Access Statement 2012 in Week 31 (settled out of court)
TTP481 (Apr 12) First Capital Connect Network Rail's decisions amending Engineering Access Statement 2012, Weeks 29 32 (settled out of court)
TTP482 (May 12) First Capital Connect Network Rail's decisions amending Engineering Access Statement 2012, Weeks 33 36 (settled out of court)
TTP483 (June 12) East Coast Network Rail's decisions amending Engineering Access Statement 2013, Weeks 37 40 (settled out of court)
TTP484 (June 12) GB Railfreight Network Rail's decisions regarding the New Working Timetable Publication for 2013 (settled out of court)
TTP485 (June 12) Freightliner Network Rail's decisions regarding the New Working Timetable Publication for 2013 (settled out of court)
TTP486 (June 12) DB Schenker Rail (UK) Network Rail's decisions regarding the New Working Timetable Publication for 2013 (settled out of court)
TTP487 (June 12) DB Schenker Rail (UK) Network Rail's decision amending Engineering Access Statement 2013 for renewal of Wolverhampton Crane Street Jn between 28 March and 2 April 2013 (settled out of court)
TTP488 (June 12) West Coast Trains Network Rail's decision document LNW13-0003-LC amending Engineering Access Statement 2013, Version 2 (settled out of court)
TTP489 (June 12) West Coast Trains Network Rail's decision document LNW13-0004-CE amending Engineering Access Statement 2013, Version 2 (settled out of court)
TTP490 (June 12) Northern Rail Network Rail's decision document LNW13-0004-CE amending Engineering Access Statement 2013, Version 2 (settled out of court)
TTP491 (June 12) XC Trains Network Rail's decision document LNW13-0004-CE amending Engineering Access Statement 2013, Version 2 (settled out of court)
TTP492 (June 12) Freightliner Heavy Haul Network Rail's decisions regarding the New Working Timetable Publication for 2013 (settled out of court)
TTP493 TTP493 18.09.12 Grand Central Railway Network Rail's failure to adhere to timescales for producing New Working Timetable Publication for 2013Preliminary Record of Determination
TTP494 TTP494 18.09.12 Grand Central Railway Network Rail's rejection of Access Proposal for 16 08 (SX) London King's Cross - Wakefield Kirkgate service in New Working Timetable Publication for 2013Preliminary Record of DeterminationNetwork Rail appealed to ORR against the decision advised in the Preliminary Record of Determination. ORR did not consider that a determination had yet been issued for the purposes of Network Code Condition D5.2.1 and declined to accept the appeal ORR letter
TTP495 TTP495 18.09.12 Grand Central Railway Network Rail's rejection of Access Proposal for 13 23 (SX) London King's Cross - Sunderland service in New Working Timetable Publication for 2013Preliminary Record of Determination
TTP496 (July 12) First Capital Connect Network Rail's decisions regarding the New Working Timetable Publication for 2013 (settled out of court)
TTP497 (July 12) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP498 (July 12) First Capital Connect Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP499 (July 12) Heathrow Express Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP500 (July 12) Southern Railway Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP501 (July 12) East Coast Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP502 (July 12) First Greater Western Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP503 (July 12) London & Birmingham Railway Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP504 (July 12) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP505 (July 12) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP506 (July 12) First ScotRail Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP507 (July 12) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP508 (July 12) West Coast Trains Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP509 (July 12) GB Railfreight Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP510 (July 12) XC Trains Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP511 (July 12) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP512 (July 12) Stagecoach South Western Trains Network Rail's Engineering Access Statement decisions for 2013, Version 4 (settled out of court)
TTP513 TTP513TTP513 (Jul 12) Freightliner Network Rail's Timetable Planning Rules decisions for 2013, Version 4Determined without oral hearingNetwork Rail appealed to ORR in respect of para. 5.1 of the determinationORR appeal determination
TTP514 TTP514TTP514 (Jul 12) Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2013, Version 4Determined without oral hearingNetwork Rail appealed to ORR in respect of para. 5.1 of the determinationORR appeal determination
TTP515 (July 12) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2013, Version 4 (settled out of court)
TTP516 (Aug 12) First Capital Connect Network Rail's Timetable Planning Rules decisions for 2013, Version 4 (settled out of court)
TTP517 (July 12) First Capital Connect Network Rail's decision to undertake midweek daytime possessions of Nos. 3 & 4 platform lines at Blackfriars, Weeks 24 52. (settled out of court)
TTP518 TTP518 18.09.12 Grand Central Railway Network Rail's decision to retime 1N90 from December 2012
TTP519 (Aug 12) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2013 (settled out of court)
TTP520 (Sept 12) Arriva Trains Wales Network Rail's decision regarding possessions between Crewe Junction and Gresty Lane in Weeks 36 & 37 (settled out of court)
TTP521 (Sept 12) West Coast Trains Network Rail's decisions for Camden Jn Wembley Central in Confirmed Period Possession Plan for Weeks 1 - 4, 2013 (settled out of court)
TTP522 (Sept 12) Heathrow Express Network Rail's decisions for London (Paddington) Reading in Week 1 of Confirmed Period Possession Plan 2013 (settled out of court)
TTP523 (Sept 12) First Greater Western Network Rail's decisions for London (Paddington) Reading in Week 1 of Confirmed Period Possession Plan 2013 (settled out of court)
TTP524 (Oct 12) First Capital Connect Network Rail's decisions for East Midlands Route in Confirmed Period Possession Plan 2013, Weeks 1 4 (settled out of court)
TTP525 (Oct 12) West Coast Trains Network Rail's decision document LNW13-0013-CE amending Engineering Access Statement 2013 in Week 32 (settled out of court)
TTP526 (Oct 12) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan 2013, Weeks 5 8 (settled out of court)
TTP527 (Nov 12) East Coast Network Rail's decisions in Confirmed Period Possession Plan 2013, Weeks 5 8 (settled out of court)
TTP528 (Nov 12) West Coast Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 11 & 12, 2013 (settled out of court)
TTP529 (Nov 12) Grand Central Railway Network Rail's decision relating to 16 08 departure path from London Kings Cross in Subsidiary Timetable 2013 (settled out of court)
TTP530 (Nov 12) Freightliner Heavy Haul Network Rail's decisions regarding GN-GE Project disruptive access proposal 2013TTY (settled out of court)
TTP531 (Nov 12) DB Schenker Rail (UK) Network Rail's decisions regarding GN-GE Project disruptive access proposal 2013TTY (settled out of court)
TTP532 (Nov 12) GB Railfreight Network Rail's decisions regarding GN-GE Project disruptive access proposal 2013TTY (settled out of court)
TTP533 (Nov 12) Northern Rail Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2013 (settled out of court)
TTP534 (Nov 12) Freightliner Heavy Haul Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2013 (settled out of court)
TTP535 (Dec 12) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 9, 2013 (settled out of court)
TTP536 (Dec 12) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Week 9, 2013 (settled out of court)
TTP537 (Dec 12) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2013 (settled out of court)
TTP538 (Dec 12) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2013 (settled out of court)
TTP539 (Dec 12) First Capital Connect Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2013 (settled out of court)
TTP540 (Dec 12) First Greater Western Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2013 (settled out of court)
TTP541 (Dec 12) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 13, 2013 (settled out of court)
TTP542 (Dec 12) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2013 (settled out of court)
TTP543 (Dec 12) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Week 13, 2013 (settled out of court)
TTP544 (Dec 12) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 & 2, 2013 (settled out of court)
TTP545 08.02.13 Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 6, 2013 (settled out of court following Panel hearing)
TTP546 (Jan 13) Arriva Trains Wales Network Rail's decision regarding Single Line Working Allowances in Week 19 of 2013 (settled out of court)
TTP547 (Jan 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 & 18, 2013 (settled out of court)
TTP548 (Jan 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2013 (settled out of court)
TTP549 (Jan 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2013 (settled out of court)
TTP550 (Feb 13) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP551 (Feb 13) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP552 (Feb 13) Freightliner Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP553 (Feb 13) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP554 (Feb 13) Heathrow Express Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP555 (Feb 13) First ScotRail Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP556 (Feb 13) GB Railfreight Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP557 (Feb 13) West Coast Trains Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP558 (Feb 13) First Greater Western Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP559 (Feb 13) London & Birmingham Railway Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP560 (Feb 13) First Capital Connect Network Rail's Engineering Access Statement decisions for 2014, Version 2 (Withdrawn by referrer)
TTP561 (Feb 13) East Coast Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP562 (Feb 13) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP563 (Feb 13) Southern Railway Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP564 (Feb 13) XC Trains Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP565 (Feb 13) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP566 (Feb 13) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP567 (Feb 13) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP568 (Feb 13) Northern Rail Network Rail's Engineering Access Statement decisions for 2014, Version 2 (settled out of court)
TTP569 (Feb 13) XC Trains Network Rail's Timetable Planning Rules decisions for 2014, Version 2 (settled out of court)
TTP570 TTP570TTP570 (Feb 13) Freightliner Network Rail's Timetable Planning Rules decisions for 2014, Version 2Determined without oral hearingNetwork Rail appealed to ORR in respect of para. 5.1 of the determinationORR appeal determination
TTP571 TTP571TTP571 (Feb 13) Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2014, Version 2Determined without oral hearingNetwork Rail appealed to ORR in respect of para. 5.1 of the determinationORR appeal determination
TTP572 (Feb 13) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2014, Version 2 (settled out of court)
TTP573 (Feb 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2013 (settled out of court)
TTP574 (Feb 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2013 (settled out of court)
TTP575 (Feb 13) First/Keolis Transpennine Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2013 (settled out of court)
TTP576 (Feb 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2013 (settled out of court)
TTP577 (Feb 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2013 (settled out of court)
TTP578 (Mar 13) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan 2013, Weeks 25 28 (settled out of court)
TTP579 (Mar 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2013 (settled out of court)
TTP580 (Mar 13) Arriva Trains Wales Network Rail's decision regarding a revised Access Proposal for Week 14, 2013 (settled out of court)
TTP581 (Apr 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 25, 2013 (settled out of court)
TTP582 (Apr 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2013 (settled out of court)
TTP583 (Apr 13) Arriva Trains Wales Network Rail's decision regarding a revised Access Proposal for Week 15, 2013 (settled out of court)
TTP584 (Apr 13) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2013 (settled out of court)
TTP585 (Apr 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Week 32, 2013 (settled out of court)
TTP586 (Apr 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2013 (settled out of court)
TTP587 (Apr 13) Arriva Trains Wales Network Rail's decision regarding a revised Access Proposal for Week 16, 2013 (settled out of court)
TTP588 (Apr 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2013 (settled out of court)
TTP589 (Apr 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 31, 2013 (settled out of court)
TTP590 (May 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2013 (settled out of court)
TTP591 (May 13) London & Birmingham Railway Network Rail's decision to remove trains from the New Working Timetable for Subsidiary Change Date 2013 (settled out of court)
TTP592 (May 13) Arriva Trains Wales Network Rail's decision regarding a revised Access Proposal for Week 22, 2013 (settled out of court)
TTP593 (June 13) DB Schenker Rail (UK) Network Rail's decision regarding allocation of capacity through Restriction of Use at Skelton Junction in Week 22, 2013 (settled out of court)
TTP594 (June 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2013/14 (settled out of court)
TTP595 (June 13) Arriva Trains Wales Network Rail's decision regarding a revised Access Proposal for Week 24, 2013 (settled out of court)
TTP596 (June 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2013/14 (settled out of court)
TTP597 (June 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 & 38, 2013/14 (settled out of court)
TTP598 (June 13) DB Schenker Rail (UK) Network Rail's decisions regarding the New Working Timetable Publication for 2014 (settled out of court)
TTP599 (June 13) Freightliner Network Rail's decisions regarding the New Working Timetable Publication for 2014 (settled out of court)
TTP600 (June 13) Freightliner Heavy Haul Network Rail's decisions regarding the New Working Timetable Publication for 2014 (settled out of court)
TTP601 (June 13) GB Railfreight Network Rail's decisions regarding the New Working Timetable Publication for 2014 (settled out of court)
TTP602 (July 13) West Coast Trains Network Rail's decisions regarding the New Working Timetable Publication for 2014 (Withdrawn by referrer)
TTP603 (July 13) London & Birmingham Railway Network Rail's decisions regarding the New Working Timetable Publication for 2014 (settled out of court)
TTP604 (July 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan 2014, Weeks 41 44 (settled out of court)
TTP605 (July 13) East Coast Network Rail's LNE 2014 Batch Document decision (settled out of court)
TTP606 (July 13) Freightliner Heavy Haul Network Rail's LNE 2014 Batch Document decision (settled out of court)
TTP607 (July 13) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP608 (July 13) First Capital Connect Network Rail's LNE 2014 Batch Document decision (settled out of court)
TTP609 (July 13) Freightliner Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP610 (Aug 13) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP611 (Aug 13) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP612 (Aug 13) Arriva Trains Wales Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP613 (Aug 13) West Coast Trains Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP614 (Aug 13) First Greater Western Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP615 (Aug 13) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP616 (Aug 13) First ScotRail Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP617 (Aug 13) East Coast Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP618 (Aug 13) GB Railfreight Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP619 (Aug 13) First Capital Connect Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP620 (Aug 13) XC Trains Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP621 (Aug 13) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP622 (Aug 13) Southern Railway Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP623 (Aug 13) Heathrow Express Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP624 (Aug 13) Northern Rail Network Rail's Engineering Access Statement decisions for 2014, Version 4 (settled out of court)
TTP625 TTP625 23.03.16 Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2014, Version 4
TTP626 (Aug 13) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2014, Version 4 (settled out of court)
TTP627 (Aug 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2014 (settled out of court)
TTP628 (Aug 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2014 (settled out of court)
TTP629 (Aug 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2014 (settled out of court)
TTP630 (Aug 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2014 (settled out of court)
TTP631 (Sept 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2014 (settled out of court)
TTP632 (Sept 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2014 (settled out of court)
TTP633 (Sept 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 & 50, 2014 (settled out of court)
TTP634 (Sept 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 & 50, 2014 (settled out of court)
TTP635 (Oct 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2014 (settled out of court)
TTP636 (Oct 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2014 (settled out of court)
TTP637 (Oct 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2014 (settled out of court)
TTP638 (Oct 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2014 (settled out of court)
TTP639 (Oct 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2014 (settled out of court)
TTP640 (Oct 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2014 (Withdrawn by referrer)
TTP641 (Oct 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Week 6, 2014 (settled out of court)
TTP642 (Oct 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 & 6, 2014 (settled out of court)
TTP643 (Nov 13) Freightliner Heavy Haul Network Rail's decisions regarding Ratcliffe Power Station Slot Review and Recast for December 2013 (settled out of court)
TTP644 (Nov 13) First/Keolis Transpennine Network Rail's decisions regarding additional access at Manchester Airport in Weeks 51 - 02, 2014 (settled out of court)
TTP645 (Nov 13) Northern Rail Network Rail's decisions regarding additional access at Manchester Airport in Weeks 51 - 02, 2014 (settled out of court)
TTP646 (Nov 13) Arriva Trains Wales Network Rail's decisions regarding additional access at Manchester Airport in Weeks 51 - 02, 2014 (settled out of court)
TTP647 (Nov 13) Freightliner Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2014 (settled out of court)
TTP648 (Nov 13) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 09 - 12, 2014 (settled out of court)
TTP649 (Nov 13) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2014 (settled out of court)
TTP650 (Nov 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2014 (settled out of court)
TTP651 (Nov 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2014 (settled out of court)
TTP652 (Nov 13) Freightliner Heavy Haul Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2014 (settled out of court)
TTP653 (Dec 13) Grand Central Railway Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2014 (settled out of court)
TTP654 (Dec 13) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2014 (settled out of court)
TTP655 (Dec 13) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2014 (settled out of court)
TTP656 (Jan 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2014 (settled out of court)
TTP657 (Jan 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2014 (settled out of court)
TTP658 (Jan 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2014 (settled out of court)
TTP659 (Jan 14) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2014 (settled out of court)
TTP660 (Jan 14) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2014 (settled out of court)
TTP661 (Feb 14) Freightliner Network Rail's revised arrangements for Watford area S&C renewals in Weeks 20 - 22, 2014 (settled out of court)
TTP662 (Feb 14) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP663 (Feb 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2014 (settled out of court)
TTP664 (Feb 14) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2014 (settled out of court)
TTP665 (Feb 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2014 (settled out of court)
TTP666 (Feb 14) Heathrow Express Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP667 (Feb 14) London & Birmingham Railway Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP668 (Feb 14) Freightliner Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP669 (Feb 14) GB Railfreight Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP670 (Feb 14) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP671 (Feb 14) West Coast Trains Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP672 (Feb 14) First Capital Connect Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP673 (Feb 14) First ScotRail Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP674 (Feb 14) East Coast Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP675 (Feb 14) Arriva Trains Wales Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP676 (Feb 14) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP677 (Feb 14) XC Trains Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP678 (Feb 14) Southern Railway Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP679 (Feb 14) First Greater Western Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP680 (Feb 14) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP681 (Feb 14) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP682 (Feb 14) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP683 (Feb 14) Northern Rail Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP684 (Feb 14) Chiltern Railways Network Rail's Engineering Access Statement decisions for 2015, Version 2 (settled out of court)
TTP685 TTP685 23.03.16 Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2015, Version 2
TTP686 (Feb 14) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2015, Version 2 (settled out of court)
TTP687 (Feb 14) DB Schenker Rail (UK) Network Rail's Timetable Planning Rules decisions for 2015, Version 2 (Withdrawn by referrer)
TTP688 (Feb 14) First Capital Connect Network Rail's Timetable Planning Rules decisions for 2015, Version 2 (settled out of court)
TTP689 (Feb 14) Northern Rail Network Rail's Timetable Planning Rules decisions for 2015, Version 2 (settled out of court)
TTP690 (Feb 14) XC Trains Network Rail's Timetable Planning Rules decisions for 2015, Version 2 (Withdrawn by referrer)
TTP691 (Feb 14) First/Keolis Transpennine Network Rail's Timetable Planning Rules decisions for 2015, Version 2 (settled out of court)
TTP692 (Feb 14) East Coast Network Rail's Timetable Planning Rules decisions for 2015, Version 2 (withdrawn by referrer)
TTP693 (Mar 14) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2014 (settled out of court)
TTP694 (Mar 14) West Coast Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2014 (settled out of court)
TTP695 (Mar 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2014 (settled out of court)
TTP696 (Mar 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2014 (settled out of court)
TTP697 (Apr 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2014 (settled out of court)
TTP698 (Apr 14) Freightliner Heavy Haul Network Rail's Offer for Week 17 of 2014 (settled out of court)
TTP699 (May 14) Freightliner Network Rail's Offer for Week 21 of 2014 (settled out of court)
TTP700 (May 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2014 (settled out of court)
TTP701 (June 14) Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for Immingham area (settled out of court)
TTP702 (June 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2014/15 (settled out of court)
TTP703 (June 14) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2014/15 (settled out of court)
TTP704 (June 14) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2014/15 (settled out of court)
TTP705 (June 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2014/15 (settled out of court)
TTP706 (June 14) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2014/15 (settled out of court)
TTP707 (June 14) GB Railfreight Network Rail's decisions regarding the New Working Timetable Publication for 2015 (settled out of court)
TTP708 (June 14) Freightliner Heavy Haul Network Rail's decisions regarding the New Working Timetable Publication for 2015 (settled out of court)
TTP709 (June 14) Freightliner Network Rail's decisions regarding the New Working Timetable Publication for 2015 (settled out of court)
TTP710 (July 14) First ScotRail Network Rail's decisions regarding the New Working Timetable Publication for 2015 (settled out of court)
TTP711 (July 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2014/15 (settled out of court)
TTP712 (July 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2014/15 (settled out of court)
TTP713 (July 14) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2014/15 (settled out of court)
TTP714 (July 14) Northern Rail Network Rail's decisions regarding the New Working Timetable Publication for 2015 (settled out of court)
TTP715 (July 14) DB Schenker Rail (UK) Network Rail's Timetable Planning Rules decisions for 2015, Version 4 (settled out of court)
TTP716 (July 14) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP717 (July 14) Freightliner Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP718 (July 14) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP719 (July 14) Chiltern Railways Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP720 (Aug 14) East Coast Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP721 (Aug 14) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP722 (Aug 14) XC Trains Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP723 (Aug 14) First Capital Connect Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP724 (Aug 14) London & Birmingham Railway Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP725 (Aug 14) Heathrow Express Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP726 (Aug 14) West Coast Trains Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP727 (Aug 14) Southern Railway Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP728 (Aug 14) First Greater Western Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP729 (Aug 14) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP730 (Aug 14) Northern Rail Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP731 (Aug 14) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP732 (Aug 14) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2015, Version 4 (settled out of court)
TTP733 TTP733 23.03.16 Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2015, Version 4
TTP734 (July 14) First Capital Connect Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2014/15 (settled out of court)
TTP735 (Aug 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2014/15 (settled out of court)
TTP736 (Aug 14) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2014/15 (settled out of court)
TTP737 (Aug 14) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2014/15 (settled out of court)
TTP738 (Aug 14) Freightliner Network Rail's decisions on engineering access at Ipswich Yard in Weeks 22 - 24, 2014/15 (settled out of court)
TTP739 (Aug 14) Freightliner & Freightliner Heavy Haul Network Rail's decision to make variation to Timetable Planning Rules decisions for 2015 in South Wales (settled out of court)
TTP740 (Aug 14) DB Schenker Rail (UK) Network Rail's revised decisions regarding Weeks 41 - 8 in the Engineering Access Statement for 2015 (settled out of court)
TTP741 (Aug 14) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2014/15 (settled out of court)
TTP742 (Sept 14) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2014/15 (settled out of court)
TTP743 (Sept 14) East Coast Network Rail's revised decisions regarding Weeks 13 - 16 in the Engineering Access Statement for 2015 (settled out of court)
TTP744 (Sept 14) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2014/15 (settled out of court)
TTP745 (Sept 14) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2015/16 (settled out of court)
TTP746 (Sept 14) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2015/16 (settled out of court)
TTP747 (Oct 14) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2015/16 (settled out of court)
TTP748 (Oct 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2015/16 (settled out of court)
TTP749 (Oct 14) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court)
TTP750 (Oct 14) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court)
TTP751 (Oct 14) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court)
TTP752 (Oct 14) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court)
TTP753 (Oct 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court)
TTP754 (Oct 14) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2015/16 (settled out of court)
TTP755 (Nov 14) Freightliner Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court)
TTP756 (Nov 14) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2015/16 (settled out of court)
TTP757 (Nov 14) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2015/16 (settled out of court)
TTP758 (Nov 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2015/16 (settled out of court)
TTP759 (Nov 14) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2015/16 (settled out of court)
TTP760 (Nov 14) GB Railfreight Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court)
TTP761 (Dec 14) Freightliner Heavy Haul Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court)
TTP762 (Dec 14) Govia Thameslink Railway Network Rail's decision amending engineering access in the Balcombe area in Weeks 51/52, 2014/15 (settled out of court)
TTP763 (Dec 14) N Yorkshire Moors Rly Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court)
TTP764 (Dec 14) First/Keolis Transpennine Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court)
TTP765 (Dec 14) Northern Rail Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court)
TTP766 (Dec 14) Arriva Trains Wales Network Rail's decision amending engineering access in the Wolverhampton area in Week 6 (settled out of court)
TTP767 (Dec 14) Abellio Greater Anglia Network Rail's decisions amending engineering access between Liverpool Street and Seven Kings in Weeks 17, 23, 26 and 29, 2015/16 (settled out of court)
TTP768 (Dec 14) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2015/16 (settled out of court)
TTP769 (Dec 14) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2015/16 (settled out of court)
TTP770 (Dec 14) XC Trains Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2015 (settled out of court)
TTP771 (Jan 15) Freightliner Network Rail Variation for Week 2 of 2015/16 (settled out of court)
TTP772 (Jan 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2015/16 (settled out of court)
TTP773 TTP773 01.04.15 XC Trains Network Rail's planning of Variation for Week 6
TTP774 (Feb 15) Grand Central Railway Network Rail's decision regarding engineering access at Doncaster in Week 23, 2015/16 (settled out of court)
TTP775 (Feb 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court)
TTP776 (Feb 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court)
TTP777 (Feb 15) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court)
TTP778 (Feb 15) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court)
TTP779 (Feb 15) Northern Rail Network Rail's decision regarding engineering access between Ashton Moss Junction and Stalybridge in Weeks 25 - 28, 2015/16 (settled out of court)
TTP780 (Feb 15) Grand Central Railway Network Rail's planning of Variation for Week 9 (settled out of court)
TTP781 (Feb 15) DB Schenker Rail (UK) Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court)
TTP782 (Feb 15) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP783 (Feb 15) Freightliner Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP784 (Feb 15) Heathrow Express Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP785 (Feb 15) XC Trains Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP786 (Feb 15) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP787 (Feb 15) West Coast Trains Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP788 (Feb 15) London & Birmingham Railway Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP789 (Feb 15) East Coast Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP790 (Feb 15) First Greater Western Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP791 (Feb 15) Govia Thameslink Railway Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP792 (Feb 15) GB Railfreight Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP793 (Feb 15) Northern Rail Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP794 (Feb 15) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP795 (Feb 15) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP796 (Feb 15) Arriva Trains Wales Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP797 (Feb 15) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP798 (Feb 15) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP799 (Feb 15) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP800 (Feb 15) First ScotRail Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP801 (Feb 15) Southern Railway Network Rail's Engineering Access Statement decisions for 2016, Version 2 (settled out of court)
TTP802 (Feb 15) Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court)
TTP803 (Feb 15) XC Trains Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court)
TTP804 (Feb 15) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court)
TTP805 (Feb 15) Southern Railway Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court)
TTP806 (Feb 15) Govia Thameslink Railway Network Rail's Timetable Planning Rules decisions for 2016, Version 2 (settled out of court)
TTP807 TTP807TTP807 01.06.15 GB Railfreight Network Rail's decision amending Timetable Planning Rules decisions for 2016, Version 2 in respect of West Ealing areaNetwork Rail appealed to ORR in respect of paras. 6.1.1, 6.1.2, 6.1.3 and 6.1.5 of the determinationORR appeal determination
TTP808 TTP808TTP808 01.06.15 Freightliner & Freightliner Heavy Haul Network Rail's decision amending Timetable Planning Rules decisions for 2016, Version 2 in respect of West Ealing areaNetwork Rail appealed to ORR in respect of paras. 6.1.1, 6.1.2, 6.1.3 and 6.1.5 of the determinationORR appeal determination
TTP809 (Mar 15) XC Trains Network Rail's decision regarding engineering access in the Aldwarke Junction area in Weeks 19 - 21, 2015/16 (settled out of court)
TTP810 (Mar 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2015/16 (settled out of court)
TTP811 (Mar 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2015/16 (settled out of court)
TTP812 (Mar 15) East Coast Network Rail's decision in a Batch Document amending the Engineering Access Statement 2016 on the LNE Route (settled out of court)
TTP813 (Mar 15) DB Schenker Rail (UK) Network Rail's decision in a Batch Document amending the Engineering Access Statement 2016 on the LNE Route (settled out of court)
TTP814 (Mar 15) Freightliner Heavy Haul Network Rail's decision in a Batch Document amending the Engineering Access Statement 2016 on the LNE Route (settled out of court)
TTP815 (Mar 15) Govia Thameslink Railway Network Rail's decision in a Batch Document amending the Engineering Access Statement 2016 on the LNE Route (settled out of court)
TTP816 (Apr 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2015/16 (settled out of court)
TTP817 (Apr 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2015/16 (settled out of court)
TTP818 (Apr 15) DB Schenker Rail (UK) Network Rail's decisions regarding engineering access in South Wales in Weeks 33 & 34, 2015/16 (settled out of court)
TTP819 (Apr 15) GB Railfreight Network Rail's decision (Version 2.1) amending Sussex Timetable Planning Rules for 2016 (settled out of court)
TTP820 (May 15) Freightliner & Freightliner Heavy Haul Network Rail's decision (Version 2.1) amending Sussex Timetable Planning Rules for 2016 (settled out of court)
TTP821 (May 15) DB Schenker Rail (UK) Network Rail's decisions amending the Engineering Access Statement for 2016 (settled out of court)
TTP822 (May 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2015/16 (settled out of court)
TTP823 (May 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2015/16 (settled out of court)
TTP824 (May 15) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2015/16 (settled out of court)
TTP825 (May 15) Freightliner Heavy Haul Network Rail's offer for Week 22, 2015/16 (settled out of court)
TTP826 (May 15) First Greater Western Network Rail's decisions amending the Engineering Access Statement for 2016 (settled out of court)
TTP827 (June 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2015/16 (settled out of court)
TTP828 (June 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2015/16 (settled out of court)
TTP829 (June 15) DB Schenker Rail (UK) Network Rail's decision regarding Restriction of Use in Angerstein Junction area in Week 15, 2015/16 (settled out of court)
TTP830 (June 15) East Coast Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2015/16 (settled out of court)
TTP831 (June 15) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2015/16 (settled out of court)
TTP832 (June 15) Freightliner Heavy Haul Network Rail's offer for Week 25, 2015/16 (settled out of court)
TTP833 (June 15) DB Schenker Rail (UK) Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court)
TTP834 TTP834 06.10.15 Arriva Trains Wales Network Rail's decisions regarding the New Working Timetable Publication for 2016
TTP835 (June 15) Freightliner Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court)
TTP836 (June 15) GB Railfreight Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court)
TTP837 (June 15) Freightliner Heavy Haul Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court)
TTP838 (June 15) Serco Caledonian Sleepers Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court)
TTP839 (July 15) Freightliner Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2015/16 (settled out of court)
TTP840 (July 15) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2015/16 (settled out of court)
TTP841 (July 15) Arriva Trains Wales Network Rail's decisions regarding engineering access in the Cardiff area in Weeks 52 & 53, 2015/16 (settled out of court)
TTP842 (July 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 44, 2015/16 (settled out of court)
TTP843 (July 15) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 44, 2015/16 (settled out of court)
TTP844 (July 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2015/16 (settled out of court)
TTP845 (July 15) Southern Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2015/16 (settled out of court)
TTP846 (July 15) Arriva Trains Wales Network Rail's decision regarding engineering access in the Cardiff area in Week 51, 2015/16 (settled out of court)
TTP847 (July 15) Govia Thameslink Railway Network Rail's decisions regarding engineering access in Weeks 50 & 51, 2015/16 (settled out of court)
TTP848 (July 15) Southern Railway Network Rail's decisions regarding engineering access in Weeks 50 & 51, 2015/16 (settled out of court)
TTP849 (July 15) London Overground Rail Operations Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court)
TTP850 (July 15) Hull Trains Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court)
TTP851 (July 15) Freightliner Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP852 (July 15) Southern Railway Network Rail's decisions regarding the New Working Timetable Publication for 2016 (settled out of court)
TTP853 (July 15) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP854 (July 15) DB Schenker Rail (UK) Network Rail's Timetable Planning Rules decisions for 2016, Version 4 (settled out of court)
TTP855 (July 15) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2016, Version 4 (settled out of court)
TTP856 (July 15) East Coast Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP857 (July 15) Heathrow Express Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP858 (July 15) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP859 (July 15) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP860 (July 15) First Greater Western Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP861 (July 15) Govia Thameslink Railway Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP862 (July 15) West Coast Trains Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP863 (July 15) XC Trains Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP864 (July 15) Serco Caledonian Sleepers Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP865 (July 15) GB Railfreight Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP866 (July 15) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP867 (July 15) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP868 (July 15) Arriva Trains Wales Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP869 (July 15) Northern Rail Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP870 (July 15) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2016, Version 4 (settled out of court)
TTP871 (July 15) Serco Caledonian Sleepers Network Rail's Timetable Planning Rules decisions for 2016, Version 4 (settled out of court)
TTP872 TTP872 23.03.16 Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2016, Version 4
TTP873 (Aug 15) Freightliner Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2015/16 (settled out of court)
TTP874 (Aug 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2015/16 (settled out of court)
TTP875 (Aug 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Week 47 (settled out of court)
TTP876 (Aug 15) West Coast Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2015/16 (settled out of court)
TTP877 (Aug 15) First Greater Western Network Rail's offer for Week 33, 2015/16 (settled out of court)
TTP878 (Aug 15) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2015/16 (settled out of court)
TTP879 (Sept 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2015/16 (settled out of court)
TTP880 (Sept 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 52 & 53, 2015/16 (settled out of court)
TTP881 (Sept 15) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Week 53, 2015/16 (settled out of court)
TTP882 (Sept 15) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 53, 2015/16 (settled out of court)
TTP883 (Sept 15) Freightliner Network Rail's offer for Week 40, 2015/16 (settled out of court)
TTP884 (Sept 15) XC Trains Network Rail's decision regarding engineering access in the Bromsgrove area in Week 30, 2016/17 (settled out of court)
TTP885 (Oct 15) DB Schenker Rail (UK) Network Rail's decision amending the Engineering Access Statement 2016 between Barnt Green and Abbotswood Junction (25 October - 7 November 2016) (settled out of court)
TTP886 (Oct 15) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2016/17 (settled out of court)
TTP887 (Oct 15) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2016/17 (settled out of court)
TTP888 (Oct 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2016/17 (settled out of court)
TTP889 (Oct 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2016/17 (settled out of court)
TTP890 (Oct 15) XC Trains Network Rail's decision regarding engineering access in the Leamington Spa area in Week 15, 2016/17 (settled out of court)
TTP891 (Oct 15) DB Schenker Rail (UK) Network Rail's decision regarding engineering access in the Oxford area in Weeks 17 - 19, 2016/17 (settled out of court)
TTP892 (Oct 15) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2016/17 (settled out of court)
TTP893 (Oct 15) East Coast Network Rail's decision regarding engineering access in the Hornsey area in Week 9, 2016/17 (settled out of court)
TTP894 (Nov 15) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 8, 2016/17 (settled out of court)
TTP895 (Nov 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2016/17 (settled out of court)
TTP896 (Nov 15) Grand Central Railway Network Rail's decision regarding capacity allocation during engineering work in the Hornsey area in Week 9, 2016/17 (settled out of court)
TTP897 (Nov 15) DB Schenker Rail (UK) Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court)
TTP898 (Nov 15) Freightliner Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court)
TTP899 (Nov 15) Abellio Greater Anglia Network Rail's decisions regarding engineering access in the Shenfield area in Weeks 25 - 32, 2016/17 (settled out of court)
TTP900 (Nov 15) London Overground Rail Operations Network Rail's decisions regarding engineering access in the Shenfield area in Weeks 25 - 32, 2016/17 (settled out of court)
TTP901 (Nov 15) Freightliner Heavy Haul Network Rail's decision regarding Removal of Train Slots from the Working Timetable (settled out of court)
TTP902 (Nov 15) Freightliner Network Rail's decisions regarding engineering access in the Shenfield area in Weeks 25 - 32, 2016/17 (settled out of court)
TTP903 (Nov 15) GB Railfreight Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court)
TTP904 (Nov 15) Serco Caledonian Sleeper Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court)
TTP905 (Nov 15) Freightliner Heavy Haul Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court)
TTP906 (Dec 15) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Week 9, 2016/17 (settled out of court)
TTP907 (Dec 15) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2016/17 (settled out of court)
TTP908 (Dec 15) West Coast Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2016/17 (settled out of court)
TTP909 (Dec 15) First Greater Western Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2016 (settled out of court)
TTP910 (Dec 15) First Greater Western Network Rail's decision amending engineering access between Heywood Road Junction and Fairwood Junction via Westbury (settled out of court)
TTP911 (Dec 15) Arriva Trains Wales Network Rail's decisions regarding engineering access in Weeks 19 & 20, 2016/17 (settled out of court)
TTP912 (Jan 16) Grand Central Railway Network Rail's offer for Week 3, 2016/17 (settled out of court)
TTP913 (Jan 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2016/17 (settled out of court)
TTP914 (Jan 16) First Greater Western Network Rail's decision regarding engineering access in the Maliphant area in Week 30, 2016/17 (settled out of court)
TTP915 (Jan 16) DB Schenker Rail (UK) Network Rail's decision regarding engineering access between Gaer Junction and Marshfield in Week 29, 2016/17 (settled out of court)
TTP916 (Jan 16) Abellio Greater Anglia Network Rail's decisions regarding engineering access for High Output Ballast Cleaner activity in Weeks 4 - 8, 2016/17 (settled out of court)
TTP917 (Jan 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2016/17 (settled out of court)
TTP918 (Jan 16) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 & 19, 2016/17 (settled out of court)
TTP919 (Jan 16) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 17, 2016/17 (settled out of court)
TTP920 (Jan 16) XC Trains Network Rail's offer for Week 5, 2016/17 (settled out of court)
TTP921 (Jan 16) Freightliner Network Rail's rejection of a Train Operator Variation Request (settled out of court)
TTP922 (Feb 16) GB Railfreight Network Rail's rejection of a Train Operator Variation Request (settled out of court)
TTP923 (Feb 16) First Greater Western Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court)
TTP924 (Feb 16) Heathrow Express Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP925 (Feb 16) DB Schenker Rail (UK) Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP926 (Feb 16) DB Schenker Rail (UK) Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court)
TTP927 (Feb 16) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2016/17 (settled out of court)
TTP928 (Feb 16) Freightliner Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP929 (Feb 16) Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court)
TTP930 (Feb 16) Direct Rail Services Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP931 (Feb 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2016/17 (settled out of court)
TTP932 (Feb 16) East Coast Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP933 (Feb 16) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 22 & 23, 2016/17 (settled out of court)
TTP934 (Feb 16) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2016/17 (settled out of court)
TTP935 (Feb 16) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP936 (Feb 16) MTR Crossrail Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP937 (Feb 16) First/Keolis Transpennine Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP938 (Feb 16) West Coast Trains Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP939 (Feb 16) First Greater Western Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP940 (Feb 16) Serco Caledonian Sleepers Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP941 (Feb 16) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP942 (Feb 16) XC Trains Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP943 (Feb 16) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP944 (Feb 16) GB Railfreight Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP945 (Feb 16) Govia Thameslink Railway Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP946 (Feb 16) London & Birmingham Railway Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP947 (Feb 16) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP948 (Feb 16) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP949 (Feb 16) Northern Rail Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP950 (Feb 16) Abellio ScotRail Network Rail's Engineering Access Statement decisions for 2017, Version 2 (settled out of court)
TTP951 (Feb 16) Serco Caledonian Sleepers Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court)
TTP952 (Feb 16) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2017, Version 2 (settled out of court)
TTP953 (Mar 16) Abellio Greater Anglia Network Rail's decisions regarding engineering access for High Output Track Relaying System activity in Weeks 27 & 28, 2016/17 (settled out of court)
TTP954 (Mar 16) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2016/17 (settled out of court)
TTP955 (Mar 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2016/17 (settled out of court)
TTP956 (Mar 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2016/17 (settled out of court)
TTP957 (Mar 16) Freightliner Heavy Haul Network Rail's offer for Week 9, 2016/17 (settled out of court)
TTP958 (Apr 16) Arriva Rail North Network Rail's decisions regarding engineering access in Weeks 6 & 7, 2017/18 (settled out of court)
TTP959 (Apr 16) Grand Central Railway Network Rail's decisions regarding engineering access in Weeks 7 - 10, 2017/18 (settled out of court)
TTP960 (Apr 16) DB Cargo (UK) Network Rail's decisions regarding engineering access for Bromsgrove Electrification Scheme between Week 29, 2016/17 and Week 7, 2017/18 (settled out of court)
TTP961 (Apr 16) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2016/17 (settled out of court)
TTP962 (Apr 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2016/17 (settled out of court)
TTP963 (Apr 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2016/17 (settled out of court)
TTP964 (Apr 16) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2016/17 (settled out of court)
TTP965 (May 16) First Greater Western Network Rail's decision amending the Timetable Planning Rules for 2017 (Cardiff West area) (settled out of court)
TTP966 (May 16) First Greater Western Network Rail's offer for Week 14, 2016/17 (settled out of court)
TTP967 (May 16) Freightliner Network Rail's offer for Weeks 18 - 20, 2016/17 (settled out of court)
TTP968 (May 16) Abellio Greater Anglia Network Rail's decision regarding engineering access in Week 40, 2016/17 (settled out of court)
TTP969 (May 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2016/17 (settled out of court)
TTP970 (May 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2016/17 (settled out of court)
TTP971 (June 16) First Greater Western Network Rail's decision amending engineering access at Paddington over Christmas/New Year 2016/17 (settled out of court)
TTP972 (June 16) Abellio Greater Anglia Network Rail's decision regarding engineering access in Week 24, 2016/17 (settled out of court)
TTP973 (June 16) Freightliner Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court)
TTP974 (June 16) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court)
TTP975 (June 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court)
TTP976 (June 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court)
TTP977 (June 16) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2016/17 (settled out of court)
TTP978 TTP978 16.08.16 Abellio Greater Anglia Network Rail's decisions regarding engineering access in Weeks 25 - 32, 2016/17
TTP979 (June 16) DB Cargo (UK) Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court)
TTP980 (June 16) Freightliner Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court)
TTP981 (June 16) Serco Caledonian Sleepers Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court)
TTP982 (June 16) GB Railfreight Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court)
TTP983 (June 16) Freightliner Heavy Haul Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court)
TTP984 (June 16) Grand Central Railway Network Rail's decisions amending the Confirmed Period Possession Plan for Weeks 30 & 31, 2016/17 (settled out of court)
TTP985 TTP985TTP985 05.08.16 Abellio Greater Anglia Network Rail's decisions regarding the New Working Timetable Publication for 2017MTR Crossrail and Network Rail appealed to ORR in respect of the Panel's determination ORR appeal determination
TTP986 (July 16) First Greater Western Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court)
TTP987 (July 16) XC Trains Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court)
TTP988 (July 16) Govia Thameslink Railway Network Rail's decisions regarding the New Working Timetable Publication for 2017 (settled out of court)
TTP989 (July 16) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2016/17 (settled out of court)
TTP990 (July 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2016/17 (settled out of court)
TTP991 (July 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Week 42, 2016/17 (settled out of court)
TTP992 (July 16) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2016/17 (settled out of court)
TTP993 (July 16) Freightliner Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP994 (July 16) West Coast Trains Network Rail's decision amending access between Preston Fylde Junction and Blackpool North between 3 October 2016 and 8 December 2017 (settled out of court)
TTP995 (July 16) DB Cargo (UK) Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP996 (July 16) DB Cargo (UK) Network Rail's Timetable Planning Rules decisions for 2017, Version 4 (settled out of court)
TTP997 (July 16) Serco Caledonian Sleepers Network Rail's Timetable Planning Rules decisions for 2017, Version 4 (settled out of court)
TTP998 (July 16) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2017, Version 4 (settled out of court)
TTP999 (July 16) DB Cargo (UK) Network Rail's decision regarding engineering access at Ashford East Junction in Week 24, 2016/17 (settled out of court)
TTP1000 (July 16) XC Trains Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1001 (Aug 16) East Coast Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1002 (Aug 16) Arriva Rail North Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1003 (Aug 16) Abellio Greater Anglia Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1004 (Aug 16) Freightliner Network Rail's offer for Week 32, 2016/17 (settled out of court)
TTP1005 (Aug 16) West Coast Trains Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1006 (Aug 16) Govia Thameslink Railway Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1007 (Aug 16) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1008 (Aug 16) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1009 (Aug 16) GB Railfreight Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1010 (Aug 16) Heathrow Express Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1011 (Aug 16) First Greater Western Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1012 (Aug 16) First Transpennine Express Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1013 (Aug 16) Serco Caledonian Sleepers Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1014 (Aug 16) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1015 (Aug 16) Stagecoach South Western Trains Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1016 (Aug 16) London Overground Rail Operations Network Rail's Engineering Access Statement decisions for 2017, Version 4 (settled out of court)
TTP1017 (Aug 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2016/17 (settled out of court)
TTP1018 (Aug 16) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2016/17 (settled out of court)
TTP1019 (Aug 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2016/17 (settled out of court)
TTP1020 (Aug 16) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2016/17 (settled out of court)
TTP1021 (Aug 16) First Greater Western Network Rail's decision amending engineering access at Bath Spa, Easter 2017 (settled out of court)
TTP1022 (Aug 16) Abellio Greater Anglia Network Rail's decision regarding engineering access on Manor Park Up Passenger Avoiding line in Week 2, 2017/18 (settled out of court)
TTP1023 (Sept 16) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2016/17 (settled out of court)
TTP1024 (Sept 16) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2016/17 (settled out of court)
TTP1025 (Sept 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2016/17 (settled out of court)
TTP1026 (Sept 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2016/17 (settled out of court)
TTP1027 (Oct 16) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2017/18 (settled out of court)
TTP1028 (Oct 16) Abellio Greater Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2017/18 (settled out of court)
TTP1029 (Oct 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2017/18 (settled out of court)
TTP1030 (Oct 16) West Coast Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2017/18 (settled out of court)
TTP1031 (Oct 16) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Week 1, 2017/18 (settled out of court)
TTP1032 (Oct 16) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2017/18 (settled out of court)
TTP1033 (Nov 16) London Overground Rail Operations Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2017/18 (settled out of court)
TTP1034 (Nov 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2017/18 (settled out of court)
TTP1035 (Nov 16) Grand Central Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 7, 2017/18 (settled out of court)
TTP1036 (Nov 16) DB Cargo (UK) Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court)
TTP1037 (Nov 16) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2017/18 (settled out of court)
TTP1038 (Nov 16) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2017/18 (settled out of court)
TTP1039 (Nov 16) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2017/18 (settled out of court)
TTP1040 (Dec 16) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Week 9, 2017/18 (settled out of court)
TTP1041 (Dec 16) GB Railfreight Network Rail's rejection of a Train Operator Variation Request (settled out of court)
TTP1042 (Dec 16) Freightliner Heavy Haul Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court)
TTP1043 (Dec 16) First Greater Western Network Rail's decision regarding engineering access between Wootton Bassett and Westerleigh Junction in August 2017 (settled out of court)
TTP1044 (Dec 16) GB Railfreight Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court)
TTP1045 (Dec 16) Serco Caledonian Sleepers Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court)
TTP1046 (Dec 16) XC Trains Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court)
TTP1047 (Dec 16) Govia Thameslink Railway Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2017 (settled out of court)
TTP1048 (Dec 16) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2017/18 (settled out of court)
TTP1049 (Dec 16) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2017/18 (settled out of court)
TTP1050 (Jan 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2017/18 (settled out of court)
TTP1051 (Jan 17) Arriva Trains Wales Network Rail's decision regarding Abergele station Down Platform line in Weeks 41 - 49, 2016/17 (settled out of court)
TTP1052 (Jan 17) First Greater Western Network Rail's decision to redate Severn Tunnel possession P2017/2165162 (settled out of court)
TTP1053 (Jan 17) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2017/18 (settled out of court)
TTP1054 (Jan 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2017/18 (settled out of court)
TTP1055 (Jan 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2017/18 (settled out of court)
TTP1056 (Jan 17) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan for Week 17, 2017/18 (settled out of court)
TTP1057 (Jan 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Week 17, 2017/18 (settled out of court)
TTP1058 (Jan 17) Freightliner Network Rail's offer for Week 2, 2017/18 (settled out of court)
TTP1059 (Feb 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2017/18 (settled out of court)
TTP1060 (Feb 17) London & South Eastern Railway Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2017/18 (settled out of court)
TTP1061 (Feb 17) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24 2017/18 (settled out of court)
TTP1062 (Feb 17) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan for Week 24, 2017/18 (settled out of court)
TTP1063 (Feb 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Week 23, 2017/18 (settled out of court)
TTP1064 TTP1064TTP1064 20.04.17 Abellio Scotrail Network Rail's Timetable Planning Rules decisions for 2018, Version 2Abellio Scotrail appealed to ORR concerning the Panel's determinationORR appeal determination
TTP1065 TTP1065 20.04.17 DB Cargo (UK) Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064)
TTP1066 TTP1066 20.04.17 First Greater Western Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064)
TTP1067 (Feb 17) London & South Eastern Railway Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court)
TTP1068 TTP1068 20.04.17 Transport for London Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064)
TTP1069 TTP1069 20.04.17 GB Railfreight Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064)
TTP1070 (Feb 17) Serco Caledonian Sleepers Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court)
TTP1071 (Feb 17) East Coast Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court)
TTP1072 (Feb 17) Stagecoach South Western Trains Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court)
TTP1073 TTP1073 20.04.17 XC Trains Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064)
TTP1074 (Feb 17) Govia Thameslink Railway Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court)
TTP1075 (Feb 17) Arriva Rail North Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (for other relevant documents see TTP1064) (settled out of court)
TTP1076 (Feb 17) DB Cargo (UK) Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1077 (Feb 17) Freightliner Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1078 (Feb 17) Heathrow Express Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1079 (Feb 17) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1080 (Feb 17) East Coast Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1081 (Feb 17) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1082 (Feb 17) Arriva Trains Wales Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1083 (Feb 17) XC Trains Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1084 (Feb 17) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1085 (Feb 17) Stagecoach South Western Trains Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1086 05.06.17 GB Railfreight Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1087 (Feb 17) Serco Caledonian Sleepers Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1088 (Feb 17) Abellio East Anglia Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1089 (Feb 17) Arriva Rail North Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1090 (Feb 17) First Transpennine Express Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1091 (Feb 17) Arriva Rail London Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1092 (Feb 17) First Greater Western Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1093 (Feb 17) Govia Thameslink Railway Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1094 (Feb 17) Abellio ScotRail Network Rail's Engineering Access Statement decisions for 2018, Version 2 (settled out of court)
TTP1095 (Feb 17) First Transpennine Express Network Rail's Timetable Planning Rules decisions for 2018, Version 2 (settled out of court)
TTP1096 (Mar 17) Arriva Trains Wales Network Rail's decision to redate possession P2017/2163691 (settled out of court)
TTP1097 (Mar 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2017/18 (settled out of court)
TTP1098 (Mar 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2017/18 (settled out of court)
TTP1099 (Mar 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2017/18 (settled out of court)
TTP1100 (Apr 17) Freightliner Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court)
TTP1101 (Apr 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court)
TTP1102 (Apr 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court)
TTP1103 (Apr 17) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court)
TTP1104 (Apr 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2017/18 (settled out of court)
TTP1105 (May 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2017/18 (settled out of court)
TTP1106 (May 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2017/18 (settled out of court)
TTP1107 (May 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2017/18 (settled out of court)
TTP1108 (May 17) First Greater Western Network Rail's decisions regarding engineering access in the Port Talbot area between Week 51 of 2017/18 and Week 5 of 2018/19. (settled out of court)
TTP1109 (June 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court)
TTP1110 (June 17) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court)
TTP1111 (June 17) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court)
TTP1112 (June 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court)
TTP1113 (June 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2017/18 (settled out of court)
TTP1114 (June 17) First Greater Western Network Rail's decision regarding possession P2017/2163274 (commissioning of signalling in the Port Talbot area) (settled out of court)
TTP1115 (June 17) Abellio East Anglia Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1116 (June 17) DB Cargo (UK) Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1117 (June 17) Freightliner Heavy Haul Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1118 (June 17) Serco Caledonian Sleepers Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1119 (June 17) GB Railfreight Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1120 (June 17) XC Trains Network Rail's decision regarding engineering access in the Filton Bank area in Week 35 of 2018/19 (settled out of court)
TTP1121 (July 17) Stagecoach South Western Trains Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1122 TTP1122 08.09.17 XC Trains Network Rail's decisions regarding the New Working Timetable Publication for 2018
TTP1123 (July 17) Grand Central Railway Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1124 (July 17) Arriva Rail North Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1125 (July 17) Abellio Scotrail Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1126 (July 17) First Greater Western Network Rail's decisions regarding the New Working Timetable Publication for 2018 (settled out of court)
TTP1127 TTP1127 05.09.17 GB Railfreight Network Rail's rejection of a Train Operator Variation Request
TTP1128 (July 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2017/18 (settled out of court)
TTP1129 (July 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2017/18 (settled out of court)
TTP1130 (July 17) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2017/18 (settled out of court)
TTP1131 (July 17) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2017/18 (settled out of court)
TTP1132 (July 17) First Greater Western Network Rail's decisions regarding engineering access in the Cardiff area in Weeks 46 - 50, 2017/18 (settled out of court)
TTP1133 (July 17) Freightliner Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1134 (July 17) Freightliner Network Rail's offer for Week 29, 2017/18 (settled out of court)
TTP1135 (July 17) DB Cargo (UK) Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1136 (July 17) DB Cargo (UK) Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court)
TTP1137 (July 17) Freightliner Network Rail's rejection of a Train Operator Variation Request (settled out of court)
TTP1138 (Aug 17) Abellio East Anglia Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1139 (Aug 17) Abellio Scotrail Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1140 (Aug 17) XC Trains Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court
TTP1141 (Aug 17) East Coast Main Line Company Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1142 (Aug 17) Arriva Rail North Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1143 (Aug 17) First Greater Western Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1144 (Aug 17) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1145 (Aug 17) Stagecoach South Western Trains Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1146 (Aug 17) Serco Caledonian Sleepers Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1147 (Aug 17) GB Railfreight Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1148 (Aug 17) First Transpennine Express Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1149 (Aug 17) Govia Thameslink Railway Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1150 (Aug 17) Arriva Rail London Network Rail's Engineering Access Statement decisions for 2018, Version 4 (settled out of court)
TTP1151 (Aug 17) Stagecoach South Western Trains Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court)
TTP1152 (Aug 17) Arriva Rail North Network Rail's Timetable Planning Rules decisions for 2018, Version 4
TTP1153 (Feb 18) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court)
TTP1154 (Aug 17) Abellio Scotrail Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court)
TTP1155 (Aug 17) East Midlands Trains Network Rail's Timetable Planning Rules decisions for 2018, Version 4 (settled out of court)
TTP1156 (Aug 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court)
TTP1157 (Aug 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court)
TTP1158 (Aug 17) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court)
TTP1159 (Aug 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court)
TTP1160 (Aug 17) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2017/18 (settled out of court)
TTP1161 (Aug 17) First Greater Western Network Rail's decision regarding South Wales Immunisation and Modernisation Works in Week 39, 2017/18 (settled out of court)
TTP1162 (Aug 17) Freightliner Network Rail's offer for Weeks 25 - 29, 2017/18 (settled out of court)
TTP1163 (Aug 17) First Greater Western Network Rail's decision regarding possession P2017/2412232 for Week 25, 2017/18 (settled out of court)
TTP1164 (Aug 17) Freightliner Network Rail's decisions regarding engineering access between Gospel Oak and Barking in Weeks 25 - 29, 2017/18 (settled out of court)
TTP1165 (Aug 17) XC Trains Network Rail's decision regarding possession P2017/2285097 for Week 25, 2017/18 (settled out of court)
TTP1166 (Sept 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court)
TTP1167 (Sept 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court)
TTP1168 (Sept 17) D B Cargo (UK) Network Rail's decisions in Confirmed Period Possession Plan for Week 50, 2017/18 (settled out of court)
TTP1169 (Sept 17) First MTR South Western Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court)
TTP1170 (Sept 17) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court)
TTP1171 (Sept 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2017/18 (settled out of court)
TTP1172 (Sept 17) GB Railfreight Network Rail's rejection of a Train Operator Variation Request (settled out of court)
TTP1173 (Sept 17) First Greater Western Network Rail's decision regarding engineering access in the Cardiff area in Weeks 29 & 30, 2017/18 (settled out of court)
TTP1174 TTP1174TTP1174 11.10.17 XC Trains Network Rail's reconsidered decision regarding the New Working Timetable Publication for 2018Network Rail appealed to ORR in respect of the Panel's determination ORR appeal decision
TTP1175 (Oct 17) Freightliner Network Rail's offer for Week 39, 2017/18 (settled out of court)
TTP1176 (Oct 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court)
TTP1177 (Oct 17) DB Cargo (UK) Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court)
TTP1178 (Oct 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court)
TTP1179 (Oct 17) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court)
TTP1180 (Oct 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2018/19 (settled out of court)
TTP1181 (Oct 17) XC Trains Network Rail's decision regarding engineering access in the Coventry area in Week 22, 2018/19 (settled out of court)
TTP1182 (Oct 17) Arriva Trains Wales Network Rail's decisions regarding engineering access between Pilning and Fishguard Harbour in Weeks 5 - 8, 2018/19 (settled out of court)
TTP1183 (Nov 17) Arriva Trains Wales Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court)
TTP1184 (Nov 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court)
TTP1185 (Nov 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court)
TTP1186 (Nov 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court)
TTP1187 (Nov 17) DB Cargo (UK) Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court)
TTP1188 (Nov 17) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2018/19 (settled out of court)
TTP1189 (Oct 17) XC Trains Network Rail's decisions regarding engineering access between Newport and Cardiff in Weeks 6 - 8, 2018/19 (settled out of court)
TTP1190 (Oct 17) First Greater Western Network Rail's decisions regarding engineering access between Newport and Cardiff in Weeks 6 - 8, 2018/19 (settled out of court)
TTP1191 (Nov 17) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court)
TTP1192 (Nov 17) DB Cargo (UK) Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court)
TTP1193 (Nov 17) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court)
TTP1194 (Nov 17) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court)
TTP1195 (Nov 17) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2018/19 (settled out of court)
TTP1196 (Nov 17) Freightliner Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1197 (Dec 17) Freightliner Heavy Haul Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018
TTP1198 (Dec 17) DB Cargo (UK) Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1199 (Dec 17) First Greater Western Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1200 (Dec 17) West Coast Trains Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1201 (Dec 17) Grand Central Railway Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1202 (Dec 17) XC Trains Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1203 (Dec 17) Arriva Rail North Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1204 (Dec 17) GB Railfreight Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1205 (Dec 17) Serco Caledonian Sleepers Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1206 (Dec 17) Govia Thameslink Railway Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1207 (Dec 17) First Transpennine Express Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2018 (settled out of court)
TTP1208 (Dec 17) Abellio East Anglia Network Rail's offer for Week 1, 2018/19 (settled out of court)
TTP1209 (Jan 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2018/19 (settled out of court)
TTP1210 (Jan 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2018/19 (settled out of court)
TTP1211 (Jan 18) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2018/19 (settled out of court)
TTP1212 (Jan 18) XC Trains Network Rail's decision for Week 31 of 2018/19 (settled out of court)
TTP1213 (Jan 18) DB Cargo (UK) Network Rail's decision for Week 18 of 2018/19 (settled out of court)
TTP1214 (Jan 18) Abellio East Anglia Network Rail's decisions for Weeks 29 - 32 of 2018/19 (settled out of court)
TTP1215 (Jan 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2018/19 (settled out of court)
TTP1216 (Jan 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2018/19 (settled out of court)
TTP1217 (Jan 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2018/19 (settled out of court)
TTP1218 (Jan 18) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2018/19 (settled out of court)
TTP1219 (Feb 18) Abellio East Anglia Network Rail's decisions for Weeks 41 - 52 of 2018/19 (settled out of court)
TTP1220 (Feb 18) DB Cargo (UK) Network Rail's decisions for Weeks 4 & 5 of 2018/19 (settled out of court)
TTP1221 (Feb 18) DB Cargo (UK) Network Rail's decision for Week 22 of 2018/19 (settled out of court)
TTP1222 (Feb 18) XC Trains Network Rail's decision for Week 27 of 2018/19 (settled out of court)
TTP1223 (Feb 18) XC Trains Network Rail's decisions for Weeks 4 & 5 of 2018/19 (settled out of court)
TTP1224 (Feb 18) Arriva Trains Wales Network Rail's decisions for Weeks 4 & 5 of 2018/19 (settled out of court)
TTP1225 (Feb 18) DB Cargo (UK) Network Rail's intention to remove certain freight Train Slots from the Working Timetable (settled out of court)
TTP1226 (Feb 18) XC Trains Network Rail's decision for Week 15 of 2018/19 (settled out of court)
TTP1227 (Feb 18) DB Cargo (UK) Network Rail's decisions for Weeks 6 - 8, 13 & 14 of 2018/19 (settled out of court)
TTP1228 (Feb 18) XC Trains Network Rail's decision for Week 16 of 2018/19 (settled out of court)
TTP1229 (Feb 18) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2018/19 (settled out of court)
TTP1230 (Feb 18) DB Cargo (UK) Network Rail's decisions in Confirmed Period Possession Plan for Week 22, 2018/19 (settled out of court)
TTP1231 (Feb 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2018/19 (settled out of court)
TTP1232 (Feb 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2018/19 (settled out of court)
TTP1233 (Feb 18) GB Railfreight Network Rail's decision not to offer Variations for Week 8 of 2018/19 (settled out of court)
TTP1234 (Feb 18) Freightliner Network Rail's decision not to offer Variations for Week 8 of 2018/19 (settled out of court)
TTP1235 (Feb 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 8 of 2018/19 (settled out of court)
TTP1236 (Feb 18) DB Cargo (UK) Network Rail's decision not to offer Variations for Week 8 of 2018/19 (settled out of court)
TTP1237 (Feb 18) GB Railfreight Network Rail's decision not to offer Variations for Week 9 of 2018/19 (settled out of court)
TTP1238 (Feb 18) Freightliner Network Rail's decision not to offer Variations for Week 9 of 2018/19 (settled out of court)
TTP1239 (Feb 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 9 of 2018/19 (settled out of court)
TTP1240 (Feb 18) GB Railfreight Network Rail's decision not to offer Variations for Week 10 of 2018/19 (settled out of court)
TTP1241 (Feb 18) Freightliner Network Rail's decision not to offer Variations for Week 10 of 2018/19 (settled out of court)
TTP1242 (Feb 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 10 of 2018/19 (settled out of court)
TTP1243 (Feb 18) DB Cargo (UK) Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court)
TTP1244 (Feb 18) Freightliner Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1245 (Feb 18) XC Tains Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1246 (Feb 18) Arriva Trains Wales Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1247 (Feb 18) East Coast Main Line Company Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court)
TTP1248 TTP1248 24.05.18 First Greater Western Network Rail's Engineering Access Statement decisions for 2019, Version 2At the hearing on 24 May 2018 FGW reserved its position on matters not then put before the Panel. A second hearing was arranged for 7 August 2018 to deal with those other matters and also issues relating to Network Rail's compliance with the determination of the 24 May 2018 hearing but this second hearing was then deferred due to progress being made between the parties. On 18 February 2019 First Greater Western advised that the dispute reference could be closed.
TTP1249 (Feb 18) Grand Central Railway Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court)
TTP1250 (Feb 18) MTR Corporation (Crossrail) Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1251 (Feb 18) Trenitialia c2c Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court)
TTP1252 (Feb 18) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1253 (Feb 18) Abellio East Anglia Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court)
TTP1254 (Feb 18) Serco Caledonian Sleepers Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1255 (Feb 18) GB Railfreight Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1256 (Feb 18) Arriva Rail North Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1257 (Feb 18) First MTR South Western Trains Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1258 (Feb 18) First Transpennine Express Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court)
TTP1259 (Feb 18) Abellio Scotrail Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1260 (Feb 18) Govia Thameslink Railway Network Rail's Engineering Access Statement decisions for 2019, Version 2 (settled out of court)
TTP1261 (Feb 18) London & South Eastern Railway Network Rail's Engineering Access Statement decisions for 2019, Version 2
TTP1262 (Feb 18) DB Cargo (UK) Network Rail's decision for Week 15 of 2018/19 (settled out of court)
TTP1263 (Feb 18) DB Cargo (UK) Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court)
TTP1264 (Feb 18) Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court)
TTP1265 (Feb 18) First MTR South Western Trains Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court)
TTP1266 (Feb 18) Arriva Rail North Network Rail's Timetable Planning Rules decisions for 2019, Version 2
TTP1267 (Feb 18) First Greater Western Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court)
TTP1268 (Feb 18) Arriva Trains Wales Network Rail's Timetable Planning Rules decisions for 2019, Version 2 (settled out of court)
TTP1269 (Feb 18) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2019, Version 2
TTP1270 (Mar 18) GB Railfreight Network Rail's decision not to offer Variations for Week 11 of 2018/19 (settled out of court)
TTP1271 (Mar 18) Freightliner Network Rail's decision not to offer Variations for Week 11 of 2018/19 (settled out of court)
TTP1272 (Mar 18) DB Cargo (UK) Network Rail's decisions for Weeks 7, 16 - 19 and 28 of 2018/19 (settled out of court)
TTP1273 (Mar 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 11 of 2018/19 (settled out of court)
TTP1274 (Mar 18) Freightliner Network Rail's decision not to offer Variations for Week 12 of 2018/19 (settled out of court)
TTP1275 (Mar 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 12 of 2018/19 (settled out of court)
TTP1276 (Mar 18) Freightliner Network Rail's decision not to offer Variations for Week 13 of 2018/19 (settled out of court)
TTP1277 (Mar 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 13 of 2018/19 (settled out of court)
TTP1278 (Mar 18) GB Railfreight Network Rail's decision not to offer Variations for Week 13 of 2018/19 (settled out of court)
TTP1279 (Mar 18) DB Cargo (UK) Network Rail's decisions in Confirmed Period Possession Plan for Week 28, 2018/19 (settled out of court)
TTP1280 (Mar 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2018/19 (settled out of court)
TTP1281 (Mar 18) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2018/19 (settled out of court)
TTP1282 (Mar 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2018/19 (settled out of court)
TTP1283 (Mar 18) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2018/19 (settled out of court)
TTP1284 (Mar 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2018/19 (settled out of court)
TTP1285 (Mar 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 14 of 2018/19 (settled out of court)
TTP1286 (Mar 18) Freightliner Network Rail's decision not to offer Variations for Week 14 of 2018/19 (settled out of court)
TTP1287 (Mar 18) Govia Thameslink Railway Network Rail's Possessions Strategy Notice for Gatwick Airport station project
TTP1288 (Mar 18) GB Railfreight Network Rail's decision not to offer Variations for Week 14 of 2018/19 (settled out of court)
TTP1289 (Apr 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 15 of 2018/19 (settled out of court)
TTP1290 (Apr 18) Freightliner Network Rail's decision not to offer Variations for Week 15 of 2018/19 (settled out of court)
TTP1291 (Apr 18) GB Railfreight Network Rail's decision not to offer Variations for Week 15 of 2018/19 (settled out of court)
TTP1292 (Apr 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 16 of 2018/19 (settled out of court)
TTP1293 (Apr 18) GB Railfreight Network Rail's decision not to offer Variations for Week 16 of 2018/19 (settled out of court)
TTP1294 (Apr 18) Freightliner Network Rail's decision not to offer Variations for Week 16 of 2018/19 (settled out of court)
TTP1295 (Apr 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 17 of 2018/19 (settled out of court)
TTP1296 (Apr 18) Freightliner Network Rail's decision not to offer Variations for Week 17 of 2018/19 (settled out of court)
TTP1297 (Apr 18) GB Railfreight Network Rail's decision not to offer Variations for Week 17 of 2018/19 (settled out of court)
TTP1298 (Apr 18) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court)
TTP1299 (Apr 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court)
TTP1300 (Apr 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court)
TTP1301 (Apr 18) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court)
TTP1302 (Apr 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2018/19 (settled out of court)
TTP1303 (Apr 18) Freightliner Heavy Haul Network Rail's decision not to offer Variations for Week 18 of 2018/19 (settled out of court)
TTP1304 (Apr 18) GB Railfreight Network Rail's decision not to offer Variations for Week 18 of 2018/19 (settled out of court)
TTP1305 (Apr 18) First Greater Western Prioritisation of Access Proposals for the New Working Timetable for 2019
TTP1306 (May 18) Abellio East Anglia Network Rail's decision for Week 14 of 2018/19 (Withdrawn)
TTP1307 (May 18) DB Cargo (UK) Network Rail's decisions for Weeks 39 and 40 of 2018/19 (settled out of court)
TTP1308 (May 18) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court)
TTP1309 (May 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court)
TTP1310 (May 18) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court)
TTP1311 (May 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court)
TTP1312 (May 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2018/19 (settled out of court)
TTP1313 12.06.18 Freightliner Network Rail's offer for Week 15, 2018/19 (settled out of court)
TTP1314 (May 18) Freightliner Heavy Haul Network Rail's offer for Week 14, 2018/19 (settled out of court)
TTP1315 (May 18) DB Cargo (UK) Network Rail's decisions for Weeks 25 - 29, 2018/19 (settled out of court)
TTP1316 (May 18) Freightliner Heavy Haul Network Rail's offer for Week 15, 2018/19 (settled out of court)
TTP1317 12.06.18 Freightliner Network Rail's offer for Week 16, 2018/19 (settled out of court)
TTP1318 (June 18) Freightliner Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court)
TTP1319 (June 18) MTR Corporation (Crossrail) Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court)
TTP1320 (June 18) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court)
TTP1321 (June 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court)
TTP1322 (June 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court)
TTP1323 (June 18) DB Cargo (UK) Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court)
TTP1324 (June 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court)
TTP1325 (June 18) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2018/19 (settled out of court)
TTP1326 (June 18) DB Cargo (UK) Network Rail's intention to remove part of a freight Train Slot from the Working Timetable (settled out of court)
TTP1327 (June 18) Arriva Trains Wales Network Rail's decisions for Weeks 33 - 35, 2018/19 (settled out of court)
TTP1328 (June 18) Freightliner Network Rail's decisions regarding the New Working Timetable Publication for 2019 (Withdrawn)
TTP1329 (June 18) West Coast Trains Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court)
TTP1330 (June 18) Serco Caledonian Sleepers Network Rail's decisions regarding the New Working Timetable Publication for 2019
TTP1331 TTP1331TTP1331TTP1331 08.11.18 GB Railfreight Network Rail's decisions regarding the New Working Timetable Publication for 2019GB Railfreight and DB Cargo (UK) have appealed to ORR in respect of the Panel's determination
TTP1332 (June 18) First Greater Western Network Rail's decisions regarding the New Working Timetable Publication for 2019
TTP1333 (June 18) Arriva Trains Wales Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court)
TTP1334 (June 18) Abellio Scotrail Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court)
TTP1335 (June 18) Freightliner Heavy Haul Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court)
TTP1336 (July 18) DB Cargo (UK) Network Rail's decisions regarding the New Working Timetable Publication for 2019 (settled out of court)
TTP1337 (June 18) XC Trains Network Rail's decision to amend the Timetable Planning Rules (settled out of court)
TTP1338 (June 18) Freightliner Heavy Haul Network Rail's decisions for Weeks 41 44 of 2018/19 (settled out of court)
TTP1339 (July 18) MTR Corporation (Crossrail) Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court)
TTP1340 (July 18) Arriva Rail London Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court)
TTP1341 (July 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court)
TTP1342 (July 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court)
TTP1343 (July 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2018/19 (settled out of court)
TTP1344 (July 18) Freightliner Heavy Haul Network Rail's failure to publish the Prior Working Timetable for May 2019 (Withdrawn)
TTP1345 (July 18) DB Cargo (UK) Network Rail's failure to publish the Prior Working Timetable for May 2019 (settled out of court)
TTP1346 (July 18) Freightliner Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1347 (July 18) Abellio East Anglia Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1348 (July 18) DB Cargo (UK) Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court)
TTP1349 (July 18) DB Cargo (UK) Network Rail's Timetable Planning Rules decisions for 2019, Version 4
TTP1350 (Aug 18) First Greater Western Network Rail's Timetable Planning Rules decisions for 2019, Version 4
TTP1351 (Aug 18) Freightliner & Freightliner Heavy Haul Network Rail's Timetable Planning Rules decisions for 2019, Version 4
TTP1352 (Aug 18) XC Trains Network Rail's Timetable Planning Rules decisions for 2019, Version 4 (settled out of court)
TTP1353 (Aug 18) Abellio East Anglia Network Rail's Timetable Planning Rules decisions for 2019, Version 4
TTP1354 (Aug 18) Arriva Trains Wales Network Rail's Timetable Planning Rules decisions for 2019, Version 4
TTP1355 (Aug 18) GB Railfreight Network Rail's Timetable Planning Rules decisions for 2019, Version 4
TTP1356 (Aug 18) Arriva Rail North Network Rail's Timetable Planning Rules decisions for 2019, Version 4
TTP1357 (Aug 18) Serco Caledonian Sleepers Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court)
TTP1358 (Aug 18) GB Railfreight Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court)
TTP1359 (Aug 18) XC Trains Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1360 (Aug 18) Arriva Rail North Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1361 (Aug 18) London North Eastern Railway Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1362 (Aug 18) Arriva Trains Wales Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1363 (Aug 18) MTR Corporation (Crossrail) Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1364 (Aug 18) First MTR South Western Railway Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1365 (Aug 18) First Transpennine Express Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1366 (Aug 18) Govia Thameslink Railway Network Rail's Engineering Access Statement decisions for 2019, Version 4 (settled out of court)
TTP1367 (Aug 18) First Greater Western Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1368 (Aug 18) Freightliner Heavy Haul Network Rail's Engineering Access Statement decisions for 2019, Version 4
TTP1369 (Aug 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2018/19 (settled out of court)
TTP1370 (Aug 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2018/19 (settled out of court)
TTP1371 (Aug 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2018/19 (settled out of court)
TTP1372 (Aug 18) MTR Corporation (Crossrail) Network Rail's decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2018/19 (settled out of court)
TTP1373 (Aug 18) DB Cargo (UK) Network Rail's intention to remove certain freight Train Slots from the Working Timetable (settled out of court)
TTP1374 (Aug 18) DB Cargo (UK) Network Rail's rejection of an Access Proposal (settled out of court)
TTP1375 (Aug 18) Colas Rail Network Rail's intention to remove a freight Train Slot from the Working Timetable (settled out of court)
TTP1376 TTP1376TTP1376TTP1376 08.11.18 GB Railfreight Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019GB Railfreight and DB Cargo (UK) have appealed to ORR in respect of the Panel's determination
TTP1377 (Aug 18) Serco Caledonian Sleepers Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019
TTP1378 (Aug 18) Freightliner Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court)
TTP1379 (Aug 18) DB Cargo (UK) Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court)
TTP1380 (Aug 18) Rail Express Systems Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court)
TTP1381 (Aug 18) Abellio East Anglia Network Rail's decision for Week 45 of 2018/19 to Week 8 of 2019/20 (settled out of court)
TTP1382 (Aug 18) Freightliner Heavy Haul Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court)
TTP1383 TTP1383 30.10.18 First Greater Western Network Rail's decision for Week 23, 2018/19
TTP1384 TTP1384 30.10.18 DB Cargo (UK) Network Rail's decision for Week 23, 2018/19
TTP1385 TTP1385 30.10.18 First Greater Western Network Rail's decision for Week 24, 2018/19
TTP1386 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 43, 2018/19 (settled out of court)
TTP1387 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 45, 2018/19 (settled out of court)
TTP1388 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 46, 2018/19 (settled out of court)
TTP1389 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 47, 2018/19 (settled out of court)
TTP1390 (Sept 18) DB Cargo (UK) Network Rail's decisions for Weeks 43, 46 & 47, 2018/19 (settled out of court)
TTP1391 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 48, 2018/19 (settled out of court)
TTP1392 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 49, 2018/19 (settled out of court)
TTP1393 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 51, 2018/19 (settled out of court)
TTP1394 (Sept 18) DB Cargo (UK) Network Rail's decisions for Weeks 1 & 4, 2019/20
TTP1395 (Sept 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2018/19
TTP1396 (Sept 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2018/19 (settled out of court)
TTP1397 (Sept 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 49 - 52, 2018/19
TTP1398 (Sept 18) West Coast Trains Network Rail's decisions in re-issuing of New Working Timetable Publication for 2019 (settled out of court)
TTP1399 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 1, 2019/20 (settled out of court)
TTP1400 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 4, 2019/20 (settled out of court)
TTP1401 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 52, 2018/19 (settled out of court)
TTP1402 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 44, 2018/19 (settled out of court)
TTP1403 (Sept 18) Arriva Trains Wales Network Rail's decision for Week 5, 2019/20 (settled out of court)
TTP1404 (Oct 18) Arriva Trains Wales Network Rail's decision for Week 50, 2018/19 (settled out of court)
TTP1405 (Oct 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2019/20
TTP1406 (Oct 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2019/20
TTP1407 (Oct 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 1 - 4, 2019/20
TTP1408 (Oct 18) Arriva Trains Wales Network Rail's further decision for Week 4, 2019/20 (settled out of court)
TTP1409 (Oct 18) Arriva Trains Wales Network Rail's decision for Week 6, 2019/20 (settled out of court)
TTP1410 (Oct 18) Arriva Trains Wales Network Rail's decision for Week 9, 2019/20
TTP1411 (Oct 18) Freightliner Network Rail's offer for Week 32, 2018/19 (settled out of court)
TTP1412 (Oct 18) TfW Rail Services Network Rail's decision for Week 10, 2019/20
TTP1413 (Oct 18) TfW Rail Services Network Rail's decision for Week 2, 2019/20 (settled out of court)
TTP1414 (Oct 18) TfW Rail Services Network Rail's decision for Week 3, 2019/20 (settled out of court)
TTP1415 (Oct 18) DB Cargo (UK) Network Rail's decisions for Weeks 11, 12 & 17, 2019/20 (settled out of court)
TTP1416 (Oct 18) TfW Rail Services Network Rail's decision for Week 11, 2019/20
TTP1417 (Oct 18) TfW Rail Services Network Rail's decision for Week 12, 2019/20
TTP1418 (Oct 18) TfW Rail Services Network Rail's decision for Week 13, 2019/20
TTP1419 (Oct 18) TfW Rail Services Network Rail's decision for Week 14, 2019/20
TTP1420 (Oct 18) TfW Rail Services Network Rail's decision for Week 15, 2019/20
TTP1421 (Oct 18) TfW Rail Services Network Rail's decision for Week 16, 2019/20
TTP1422 (Oct 18) First Greater Western Network Rail's decision for Week 20, 2019/20 (settled out of court)
TTP1423 (Nov 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2019/20
TTP1424 (Nov 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2019/20
TTP1425 (Nov 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 5 - 8, 2019/20
TTP1426 (Nov 18) TfW Rail Services Network Rail's decision for Weeks 17 & 18, 2019/20
TTP1427 (Nov 18) TfW Rail Services Network Rail's decision for Week 19, 2019/20
TTP1428 (Nov 18) TfW Rail Services Network Rail's decision for Week 20, 2019/20
TTP1429 (Nov 18) TfW Rail Services Network Rail's decision for Week 21, 2019/20
TTP1430 (Nov 18) TfW Rail Services Network Rail's decision for Week 22, 2019/20
TTP1431 (Nov 18) TfW Rail Services Network Rail's decision for Week 23, 2019/20
TTP1432 (Nov 18) TfW Rail Services Network Rail's decision for Week 24, 2019/20
TTP1433 (Nov 18) DB Cargo (UK) Network Rail's decision for Week 25, 2019/20 (settled out of court)
TTP1434 (Nov 18) London North Eastern Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2019/20
TTP1435 (Nov 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2019/20
TTP1436 (Nov 18) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2019/20
TTP1437 (Nov 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 9 - 12, 2019/20
TTP1438 (Dec 18) Freightliner Heavy Haul Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court)
TTP1439 (Nov 17) Abellio Scotrail Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019
TTP1440 (Nov 17) GB Railfreight Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019
TTP1441 (Dec 18) Rail Express Systems Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019
TTP1442 (Dec 18) DB Cargo (UK) Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019 (settled out of court)
TTP1443 (Dec 18) First Greater Western Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019
TTP1444 (Dec 18) XC Trains Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019
TTP1445 (Dec 18) Arriva Rail North Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019
TTP1446 (Dec 18) West Coast Trains Network Rail's decisions regarding the Subsidiary New Working Timetable Publication for 2019
TTP1447 (Dec 18) Freightliner Network Rail's rejection of Train Operator Variation Requests (settled out of court)
TTP1448 (Dec 18) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2019/20 (settled out of court)
TTP1449 (Dec 18) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2019/20
TTP1450 (Dec 18) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2019/20
TTP1451 (Jan 19) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 13 - 16, 2019/20
TTP1452 (Jan 19) DB Cargo (UK) Network Rail's intention to remove certain freight Train Slots from the Working Timetable
TTP1453 (Jan 19) Abellio East Anglia Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20
TTP1454 (Jan 19) DB Cargo (UK) Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20 (settled out of court)
TTP1455 (Jan 19) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20 (settled out of court)
TTP1456 (Jan 19) Govia Thameslink Railway Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20 (settled out of court)
TTP1457 (Jan 19) XC Trains Network Rail's decisions in Confirmed Period Possession Plan for Weeks 17 - 20, 2019/20
TTP1458 (Jan 19) TfW Rail Services Network Rail's decision for Week 15, 2019/20
TTP1459 (Jan 19) TfW Rail Services Network Rail's decision for Week 16, 2019/20
TTP1460 (Jan 19) TfW Rail Services Network Rail's decision for Week 17, 2019/20
TTP1461 (Jan 19) TfW Rail Services Network Rail's decision for Week 38, 2019/20 (settled out of court)
TTP1462 (Jan 19) TfW Rail Services Network Rail's decision for Week 39, 2019/20 (settled out of court)
TTP1463 (Jan 19) TfW Rail Services Network Rail's decision for Week 40, 2019/20 (settled out of court)
TTP1464 (Jan 19) First Greater Western Network Rail's decisions for Weeks 15 - 17 and 38 - 40 of 2019/20 (settled out of court)
TTP1465 (Feb 19) TfW Rail Services Network Rail's decision for Week 52 of 2018/19 and Week 1 of 2019/20
TTP1466 (Feb 19) Abellio East Anglia Network Rail's decisions for Week 42 of 2019/20 to Week 6 of 2020/21
TTP1467 (Feb 19) First Greater Western Network Rail's decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2019/20
TTP1468 (Feb 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2019/20 (settled out of court)
TTP1469 (Feb 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2019/20 (settled out of court)
TTP1470 (Feb 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 21 - 24, 2019/20 (settled out of court)
TTP1471 (Feb 19) Freightliner Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1472 (Feb 19) DB Cargo (UK) Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1473 (Feb 19) DB Cargo (UK) Network Rail’s Timetable Planning Rules decisions for 2020, Version 2
TTP1474 (Feb 19) Freightliner Heavy Haul Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1475 (Feb 19) Freightliner & Freightliner Heavy Haul Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court)
TTP1476 (Mar 19) Arriva Rail North Network Rail’s Timetable Planning Rules decisions for 2020, Version 2
TTP1477 (Mar 19) London North Eastern Railway Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1478 (Mar 19) Arriva Rail North Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1479 (Mar 19) Abellio East Anglia Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1480 (Mar 19) Serco Caledonian Sleepers Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1481 (Mar 19) GB Railfreight Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1482 (Mar 19) XC Trains Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1483 (Mar 19) First Greater Western Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1484 (Mar 19) First MTR South Western Trains Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1485 (Mar 19) MTR Corporation (Crossrail) Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1486 (Mar 19) West Coast Trains Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court)
TTP1487 (Mar 19) Grand Central Railway Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1488 (Mar 19) First Transpennine Express Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1489 (Mar 19) Govia Thameslink Railway Network Rail’s Engineering Access Statement decisions for 2020, Version 2 (settled out of court)
TTP1490 (Mar 19) TfW Rail Services Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1491 (Mar 19) Abellio Scotrail Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1492 (Mar 19) London & South Eastern Railway Network Rail’s Engineering Access Statement decisions for 2020, Version 2
TTP1493 (Mar 19) TfW Rail Services Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court)
TTP1494 (Mar 19) GB Railfreight Network Rail’s Timetable Planning Rules decisions for 2020, Version 2
TTP1495 (Mar 19) First Greater Western Network Rail’s Timetable Planning Rules decisions for 2020, Version 2 (settled out of court)
TTP1496 (Mar 19) DB Cargo (UK) Network Rail’s intention to remove certain freight Train Slots from the Working Timetable (settled out of court)
TTP1497 (Mar 19) First Greater Western Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court)
TTP1498 (Mar 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court)
TTP1499 (Mar 19) London North Eastern Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court)
TTP1500 (Mar 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court)
TTP1501 (Mar 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 25 - 28, 2019/20 (settled out of court)
TTP1502 (Mar 19) Govia Thameslink Railway Network Rail’s Possessions Strategy Notice for Gatwick Airport station project
TTP1503 (Mar 19) DB Cargo (UK) Network Rail’s intention to remove certain freight Train Slots from the Working Timetable
TTP1504 (Apr 19) Arriva Rail North Network Rail’s decision to amend the Timetable Planning Rules for 2020 at Manchester Airport
TTP1505 (Apr 19) London North Eastern Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court)
TTP1506 (Apr 19) First Greater Western Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court)
TTP1507 (Apr 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court)
TTP1508 (Apr 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20
TTP1509 (Apr 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 29 - 32, 2019/20 (settled out of court)
TTP1510 (May 19) First Greater Western Network Rail’s decision for Week 33, 2019/20 (Settled out of court)
TTP1511 (May 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2019/20
TTP1512 (May 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2019/20 (settled out of court)
TTP1513 (May 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 33 - 36, 2019/20
TTP1514 (June 19) DB Cargo (UK) Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20 (settled out of court)
TTP1515 (June 19) MTR Corporation (Crossrail) Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20
TTP1516 (June 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20
TTP1517 (June 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20 (settled out of court)
TTP1518 (June 19) XC Trains Network Rail’s decision for Week 25 of 2019/20 (settled out of court)
TTP1519 (June 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 37 - 40, 2019/20
TTP1520 TTP1520 10.09.19 Freightliner Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1521 TTP1521 08.08.19 GB Railfreight Network Rail’s decision for Week 32 of 2019/20
TTP1522 (June 19) Legge Infrastructure Services Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1523 (June 19) East Midlands Trains Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1524 (June 19) Freightliner Heavy Haul Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court)
TTP1525 (June 19) Abellio Scotrail Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1526 (June 19) Rail Express Systems Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1527 (June 19) DB Cargo (UK) Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1528 (June 19) Arriva Rail London Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1529 (June 19) GB Railfreight Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court)
TTP1530 (June 19) First Greater Western Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1531 (July 19) XC Trains Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court)
TTP1532 (July 19) London North Eastern Railway Network Rail’s decisions regarding the New Working Timetable Publication for 2020 (settled out of court)
TTP1533 (July 19) TfW Rail Services Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1534 (July 19) Chiltern Railways Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1535 (July 19) Arriva Rail North Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1536 (July 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2019/20
TTP1537 (July 19) MTR Corporation (Crossrail) Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2019/20
TTP1538 (July 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2019/20
TTP1539 (July 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 41 - 44, 2019/20
TTP1540 (July 19) Freightliner Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1541 (July 19) Arriva Rail London Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1542 (July 19) GB Railfreight Network Rail’s rejection of a Train Operator Variation Request (settled out of court)
TTP1543 (July 19) Abellio East Anglia Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1544 (July 19) MTR Corporation (Crossrail) Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1545 (July 19) First Greater Western Network Rail’s Timetable Planning Rules decisions for 2020, Version 4
TTP1546 (July 19) Freightliner Network Rail's decision regarding Week 39 2019/20 (settled out of court)
TTP1547 (Aug 19) Freightliner & Freightliner Heavy Haul Network Rail’s Timetable Planning Rules decisions for 2020, Version 4
TTP1548 (Aug 19) Arriva Rail North Network Rail’s Timetable Planning Rules decisions for 2020, Version 4
TTP1549 (Aug 19) First MTR South Western Trains Network Rail’s Timetable Planning Rules decisions for 2020, Version 4
TTP1550 (Aug 19) GB Railfreight Network Rail’s Timetable Planning Rules decisions for 2020, Version 4
TTP1551 (Aug 19) TfW Rail Services Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1552 (Aug 19) Abellio Scotrail Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1553 (Aug 19) Govia Thameslink Railway Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1554 (Aug 19) First Transpennine Express Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1555 (Aug 19) DB Cargo (UK) Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1556 (Aug 19) Arriva Rail North Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1557 (Aug 19) GB Railfreight Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1558 (Aug 19) First MTR South Western Trains Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1559 (Aug 19) Freightliner Heavy Haul Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1560 (Aug 19) XC Trains Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1561 (Aug 19) London North Eastern Railway Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1562 (Aug 19) Serco Caledonian Sleepers Network Rail’s Engineering Access Statement decisions for 2020, Version 4
TTP1563 (July 19) First Transpennine Express Network Rail’s decisions regarding the New Working Timetable Publication for 2020
TTP1564 (Aug 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2019/20
TTP1565 (Aug 19) First Greater Western Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2019/20
TTP1566 (Aug 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2019/20
TTP1567 (Aug 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 45 - 48, 2019/20
TTP1568 (Sept 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2019/20
TTP1569 (Sept 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2019/20
TTP1570 (Sept 19) First Greater Western Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2019/20
TTP1571 (Sept 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 49 - 53, 2019/20
TTP1572 (Sept 19) DB Cargo (UK) Network Rail's decisions regarding Week 30 (settled out of court)
TTP1573 (Sept 19) Direct Rail Services Network Rail's decisions regarding Week 30 (settled out of court)
TTP1574 (Sept 19) XC Trains Network Rail's decision regarding length-specific TPRs (settled out of court)
TTP1575 (Sept 19) Freightliner & Freightliner Heavy Haul Network Rail's decision regarding length-specific TPRs
TTP1576 (Sept 19) XC Trains Network Rail's decision regarding length-specific TPRs (settled out of court)
TTP1577 (Sept 19) DB Cargo (UK) Network Rail's decision regarding Weeks 43-44 2019/20
TTP1578 (Sept 19) London North Eastern Railway Network Rail's decision regarding length-specific TPRs on LNE & EM Routes
TTP1579 (Oct 19) Freightliner & Freightliner Heavy Haul Network Rail's decision regarding length-specific TPRs on LNE & EM Routes
TTP1580 (Oct 19) GB Railfreight Network Rail's decision regarding length-specific TPRs
TTP1581 (Oct 19) Freightliner & Freightliner Heavy Haul Network Rail's decision regarding length-specific TPRs
TTP1582 (Oct 19) London North Eastern Railway Network Rail's decision regarding length-specific TPRs
TTP1583 (Oct 19) Grand Central Railway Network Rail's decision regarding the Week 41 2019/20 timetable offer (settled out of court)
TTP1584 (Oct 19) Abellio East Anglia Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01 - 04, 2020/21
TTP1585 (Oct 19) First Greater Western Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01 - 04, 2020/21
TTP1586 (Oct 19) Govia Thameslink Railway Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01 - 04, 2020/21
TTP1587 (Oct 19) XC Trains Network Rail’s decisions in Confirmed Period Possession Plan for Weeks 01 - 04, 2020/21
TTP1588 (Oct 19) XC Trains Network Rail's decision regarding length-specific TPRs (settled out of court)
TTP1589 (Oct 19) DB Cargo (UK) Network Rail's decision regarding Removal of Train Slots
TTP1590 (Oct 19) DB Cargo (UK) Network Rail's decision regarding Week 40, 2019/20
TTP1591 (Oct 19) DB Cargo (UK) Network Rail's decision regarding Week 02, 2020/21