Reference Number | PDF Version | Date | Reference From | Subject | Submissions From The Parties |
---|---|---|---|---|---|
TTC1 | 01.12.94 | South Wales & West Railway | Application of Rules of the Route (possession times) by Great Western Zone | ||
TTC2 | 15.12.94 | Central Trains | Application of Rules of the Plan (sectional running times) by Midland Zone | ||
TTC3 | 15.12.94 | West Anglia Great Northern Railway | Application of Rules of the Route by East Coast Zone | ||
TTC4 | (Feb. 95) | LTS Rail | Application of Rules of the Plan (Barking resignalling Easter 1995) (settled out of court) | ||
TTC5 | 28.06.95 | Regional Railways North East | Application of Rules of the Plan (Doncaster-Cleethorpes) by LNE Zone | ||
TTC6 | (Sep. 95) | Loadhaul | Responses received to bids (settled out of court) | ||
TTC7 | (Sep. 95) | Network South Central | Flexing of trains (settled out of court) | ||
TTC8 | (Sep. 95) | Network South Central | Rules of the Route (settled out of court) | ||
TTC9 | 10.11.95 | Regional Railways North East | Application of Rules of the Plan by LNE Zone | ||
TTC10 | (Feb. 96) | Regional Railways North East | Application of Rules of the Route (at Huncoat) by LNE Zone (settled out of court) | ||
TTC11 | 22.03.96 | Rail express systems Ltd | Railtrack offer in the first iteration of the Winter 1996 timetable | ||
TTC12 | 20.05.96 | North London Railways | Railtrack offer in the first iteration of the Winter 1996 timetable | ||
TTC13 | 04.06.96 | Great Western Trains | Railtrack's publication of the level 1 Train Regulation Statement | ||
TTC14 | 18.06.96 | West Anglia Great Northern | Railtrack's proposals for the Rules of the Route/Plan for the Summer 1997 timetable | ||
TTC15 | (May 96) | Regional Railways North East | Railtrack's proposals for the Rules of the Route/Plan for the Summer 1997 timetable (settled out of court) | ||
TTC16 | (June 96) | Reference by Central Trains submitted after deadline of 7.6.96. | Application declined | ||
TTC17 | 01.07.96 | The Committee sought representations from all Industry Parties regarding an aspect of process | Introduction by Railtrack of significant changes and new material to Section 6 of the Route Compendium. | ||
TTC18 | 18.10.96 | South Wales & West Railway: | (1) Railtrack decision in the 1st iteration offer of the Summer 1997 timetable [published as determination No.18] (2) Insufficient information from Railtrack in respect of offers made to other operators in the 1st iteration, Summer 1997 timetable [published as determination No.19] | ||
TTC19 | (Oct. 96) | Anglia Railways Train Services | Railtrack decision in the 1st iteration offer of the Summer 1997 timetable (settled out of court) | ||
TTC20 | (Oct. 96) | North London Railways | Method of application of EMU timing loads in 1st iteration of Summer 1997 Timetable (settled out of court) | ||
TTC21 | 22 & 25 .10.96 | Thames Trains | Railtrack decisions in the 1st iteration offer of the Summer 1997 timetable | ||
TTC22 | 25.10.96 | Regional Railways North East | Railtrack decisions in the 1st iteration offer of the Summer 1997 timetable | ||
TTC23 | (Oct. 96) | Central Trains | Railtrack decisions in the 1st iteration offer of the Summer 1997 timetable (settled out of court) | ||
TTC24 | 28.10.96 | Regional Railways North East | Railtrack’s proposals for extraordinary Possessions in January-March 1997 | ||
TTC25 | 28.10.96 | Regional Railways North East | Railtrack’s proposals for Rules of the Route/Plan for the Winter 1997 timetable | ||
TTC26 | (Oct. 96) | South Wales & West Railway | Access Planning Process: Rules of the Plan for the Winter 1997 timetable (settled out of court) | ||
TTC27 | (Feb. 97) | Anglia Railways | Railtrack's decision in 1st iteration of the Winter 1997 timetable (settled out of court) | ||
TTC28 | (Feb. 97) | EWS (Rail Express Systems) | Railtrack's decision on Royal Mail services in 1st iteration of the Winter 1997 timetable (settled out of court) | ||
TTC29 | (Feb. 97) | North West Regional Railways | Railtrack's decision in 1st iteration of the Winter 1997 timetable: Access to Crewe CET siding (settled out of court) | ||
TTC30 | (Feb. 97) | Railfreight Distribution | Railtrack's (lack of) decision in 1st iteration of the Winter 1997 timetable (settled out of court) | ||
TTC31 | (Feb. 97) | Great Western Trains | Railtrack's decision in 1st iteration of the Winter 1997 timetable in regard to some SO services (settled out of court) | ||
TTC32 | 04.03.97 | South Wales & West Railway and Railtrack | Railtrack's decision in 1st iteration of the Winter 1997 timetable (see also AD12) | ||
TTC33 | (Mar. 97) | English Welsh & Scottish Railway | Railtrack's decision to amend unilaterally an offer previously agreed by EWS (on Kings Lynn line) (settled out of court) | ||
TTC34 | (May 97) | Great Western Trains | Railtrack’s proposals for the Summer 1998 Rules of the Route (settled out of court) | ||
TTC35 | 12.06.97 | Central Trains | Railtrack’s failure to include in its consultation on Rules of the Route a party that was negotiating Access Rights for a relevant Route | ||
TTC36 | (May 97) | English Welsh & Scottish Railway | Railtrack’s proposals for the Summer 1998 Rules of the Route (settled out of court) | ||
TTC37 | (May 97) | Great Eastern Railway and Railtrack | Railtrack’s proposals for the Summer 1998 Rules of the Plan (withdrawn; resubmitted as AD15) | ||
TTC38 | 13.06.97 | Regional Railways North East | Railtrack’s Summer 1998/99 National Rules of the Plan document | ||
TTC39 | 10.10.97 | English Welsh & Scottish Railway | Railtrack’s proposals for the Summer 1998 Rules of the Plan (and National Rules of the Plan document) | ||
TTC40 | 10.10.97 | Regional Railways North East | Railtrack’s decision in 1st iteration of the Summer 1998 timetable | ||
TTC41 | (Sep. 97) | Regional Railways North East | Railtrack’s decision in 1st iteration of the Summer 1998 timetable (settled out of court) | ||
TTC42 | (Sep. 97) | North London Railways (Silverlink Trains) | Railtrack’s decision in 1st iteration of the Summer 1998 timetable (settled out of court) | ||
TTC43 | (Sep. 97) | Anglia Railways | Railtrack’s decision in 1st iteration of the Summer 1998 timetable (settled out of court) | ||
TTC44 | (Sep. 97) | English Welsh & Scottish Railway | Railtrack’s decision in 1st iteration of the Summer 1998 timetable (settled out of court) | ||
TTC45 | (Sep. 97) | North Western Trains | Railtrack’s decision in 1st iteration of the Summer 1998 timetable (settled out of court) | ||
TTC46 | 15.10.97 | Eurostar (U.K.) | i) Railtrack’s failure to respond to a Bid (settled out of court) ii) Railtrack’s decision in 1st iteration of the Summer 1998 timetable (timed out; not submitted within prescribed time scales) Note: The Committee, having established that (i) Railtrack had now made a response, and that (ii) above was timed out, decided not to issue a determination, but to issue an Extraordinary Note about certain unsatisfactory features that it had detected. | ||
TTC47 | (Oct. 97) | Virgin Trains (West Coast) | Railtrack’s decision in 1st iteration of the Summer 1998 timetable (settled out of court) | ||
TTC48 | (Oct. 97) | Regional Railways North East | Railtrack’s proposals for the Winter 1998 Rules of the Route/Plan: (settled out of court) | ||
TTC49 | (Dec. 97) | Eurostar (UK) | Railtrack’s decision in 2nd iteration of the Summer 1998 timetable: (settled out of court) | ||
TTC50 | (Dec. 97) | Thameslink Rail | Railtrack’s decision in 2nd iteration of the Summer 1998 timetable: (settled out of court) | ||
TTC51 | (Dec. 97) | English Welsh & Scottish Railway | Railtrack’s decision on retimings of services for engineering work: (settled out of court) | ||
TTC52 | (Feb. 98) | Great Western Trains | Railtrack’s decision in 1st iteration of the Winter 1998 timetable: (settled out of court) | ||
TTC53 | (Feb. 98) | Anglia Railways | Railtrack’s decision in 1st iteration of the Winter 1998 timetable: (settled out of court) | ||
TTC54 | (Feb. 98) | Thames Trains | Railtrack’s decision in 1st iteration of the Winter 1998 timetable: (settled out of court) | ||
TTC55 | (Apr. 98) | English Welsh & Scottish Railway | Railtrack’s decision in response to a Spot Bid (settled out of court) | ||
TTC56 | (May 98) | Wales & West Railway | Railtrack’s decision in 2nd iteration of the Winter 1998 timetable: (settled out of court) | ||
TTC57 | (May 98) | Central Trains | Railtrack’s proposals for the Rules of the Route/Plan for 1999/2000: (settled out of court) | ||
TTC58 | 09.07.98 | English Welsh & Scottish Railway | Railtrack’s National Rules of the Plan (1999). EWS challenged whether Railtrack had properly complied with Determination 39 | ||
TTC59 | (May 98) | Northern Spirit | Railtrack’s proposals for the Rules of the Route/Plan for 1999/2000: (settled out of court) | ||
TTC60 | (Oct. 98) | Eurostar (U.K.) | Railtrack’s decision in 1st iteration of the Summer 1999 timetable: (settled out of court) | ||
TTC61 | (Oct. 98) | Great Western Trains | Railtrack’s decision in 1st iteration of the Summer 1999 timetable: (settled out of court) | ||
TTC62 | (Oct. 98) | Wales & West | Railtrack’s decision in 1st iteration of the Summer 1999 timetable: (settled out of court) | ||
TTC63 | 23.10.98 | Anglia Railways | Railtrack’s decision in the 1st iteration of the Summer 1999 timetable regarding Boat Trains to/from Harwich | ||
TTC64 | (Oct. 98) | English Welsh & Scottish Railway | Railtrack’s decision in 1st iteration of the Summer 1999 timetable: (settled out of court) | ||
TTC65 | (Oct. 98) | North Western Trains | Railtrack’s proposals for the Rules of the Route/Plan for Winter 1999: (settled out of court) | ||
TTC66 | (Oct. 98) | English Welsh & Scottish Railway | Railtrack’s proposals for the Rules of the Route/Plan for Winter 1999: (settled out of court) | ||
TTC67 | 30.10.98 | Northern Spirit | Application of Rules of the Plan (Sectional Running Times) by Railtrack N.W.Zone | ||
TTC68 | (Oct. 98) | Connex South Central | Railtrack’s proposals for the Rules of the Route/Plan for Winter 1999: (settled out of court) | ||
TTC69 | (Oct. 98) | Wales & West | Railtrack’s proposals for the Rules of the Route/Plan for Winter 1999: (settled out of court) | ||
TTC70 | (Oct. 98) | West Anglia Great Northern | Railtrack’s proposals for the Rules of the Route/Plan for Winter 1999: (settled out of court) | ||
TTC71 | (Dec. 98) | Great Western Trains | Railtrack’s decision in 2nd iteration of the Summer 1999 timetable: (settled out of court) | ||
TTC72 | (Dec. 98) | Anglia Railways | Railtrack’s decision in 2nd iteration of the Summer 1999 timetable: (settled out of court) | ||
TTC73 | (Feb. 99) | Northern Spirit | Railtrack’s decision in 1st iteration of the Winter 1999 timetable: (settled out of court) | ||
TTC74 | (May 99) | Eurostar (U.K.) | Railtrack’s decision in 2nd iteration of the Winter 1999 timetable: (settled out of court) | ||
TTC75 | 08.06.99 | Thameslink Rail | Railtrack’s decision in 2nd iteration of the Winter 1999 timetable: Standard hour off-peak paths Gatwick – Brighton | ||
TTC76 | (May 99) | ScotRail Railways | Railtrack’s decision in 2nd iteration of the Winter 1999 timetable: (settled out of court) | ||
TTC77 | (May 99) | Great Western Trains | Railtrack’s decision in 2nd iteration of the Winter 1999 timetable: (settled out of court) | ||
TTC78 | (May 99) | English Welsh & Scottish Railway | Railtrack’s decision in 2nd iteration of the Winter 1999 timetable: (settled out of court) | ||
TTC79 | (Aug. 99) | Northern Spirit | Railtrack’s proposals for the Rules of the Route/Plan for 2000/01: As the matters were solely concerned with the Rules for the Winter period 2000/01, the Committee exhorted the parties to continue discussions; if not resolved, Northern Spirit could bring a reference following publication of the Winter Rules Revisions. (deferred; subsequently resubmitted as ttc86) | ||
TTC80 | 16.09.99 | English Welsh & Scottish Railway | Railtrack’s proposals for the Rules of the Route/Plan for the Summer 2000 timetable: The Committee did not make a determination but issued an Extraordinary Note about certain unsatisfactory features that it had detected. The Parties were instructed to resume discussions on the basis of a common understanding of information relating to Rules of the Route, Railtrack’s proposed timings and the working arrangements at the affected locations. In the event of the Parties failing to resolve the dispute they were advised to make a further jointly agreed submission, with a request that the Dispute Hearing be reconvened. | ||
TTC81 | (Aug. 99) | Great Western Trains | Railtrack’s decision on Draft Timetable for Summer 2000: (settled out of court) | ||
TTC82 | 15.09.99 | Great Western Trains | Railtrack’s decision on Draft Timetable for Summer 2000: Paddington - Worcester services | ||
TTC83 | (Sep. 99) | Thames Trains | Railtrack’s decision on Draft Timetable for Summer 2000: (settled out of court) | ||
TTC84 | (Nov. 99) | Eurostar (U.K.) | Railtrack’s proposals for the Rules of the Route/Plan for Winter 2000/01: (settled out of court) | ||
TTC85 | 21.12.99 | Great Western Trains | Railtrack’s proposals for the Rules of the Route/Plan for Winter 2000/01: Pathing and headways | ||
TTC86 | (Dec. 99) | Northern Spirit | Railtrack’s proposals for the Rules of the Route/Plan for Winter 2000/01: (settled out of court) | ||
TTC87 | 20.12.99 & 27.01.00 | English Welsh & Scottish Railway | Railtrack’s decision for the Rules of the Route/Plan for Winter 2000/01 - Engineering allowances: Camden - Rugby | ||
TTC88 | 05.01.00 | Rail Express Systems | Railtrack’s decision in respect of Bids for the Summer 2000 timetable: Weekly service Waterloo – Salisbury | ||
TTC89 | 12.01.00 | Thames Trains | Railtrack’s decision in respect of Bids for the Summer 2000 timetable: Paddington - Oxford service | ||
TTC90 | (Dec. 99) | Great North Eastern Railway | Railtrack’s decision in respect of Bids for the Summer 2000 timetable: (settled out of court) | ||
TTC91 | 12.01.00 | Great Western Trains | Railtrack’s decision in respect of Bids for the Summer 2000 timetable: Paddington - Oxford - Worcester service | ||
TTC92 | (Dec. 99) | Freightliner | Railtrack’s decision in respect of Bids for the Summer 2000 timetable: (settled out of court) | ||
TTC93 | 11.01.00 | Great North Eastern Railway | Railtrack’s decision in respect of Bids for the Summer 2000 timetable: Flexing of services to Glasgow | ||
TTC94 | (Dec. 99) | English Welsh & Scottish Railway | Railtrack’s decision in respect of Bids for the Summer 2000 timetable: (settled out of court) | ||
TTC95 | 17.01.00 | Northern Spirit | Railtrack’s decision in respect of Bids for the Summer 2000 timetable: Application of Performance allowances | ||
TTC96 | (Apr. 00) | Thames Trains | Railtrack’s decision in respect of Bids for the Winter 2000/01 timetable: (settled out of court) | ||
TTC97 | (Apr. 00) | Wales & West Passenger Trains | Railtrack’s decision in respect of Bids for the Winter 2000/01 timetable: (settled out of court) | ||
TTC98 | (July 00) | Anglia Railways | Train Regulation Statements: Alleged that Railtrack was not complying with the provisions of Condition H11: (settled out of court) | ||
TTC99 | (July 00) | Connex South Eastern | Railtrack’s proposals for the Rules of the Route 2001/02: (settled out of court) | ||
TTC100 | (July 00) | The Chiltern Railway Company | Railtrack’s proposals for the Rules of the Route 2001/02: (settled out of court) | ||
TTC101 | (July 00) | West Anglia Great Northern | Railtrack’s proposals for the Rules of the Route/Plan 2001/02: (withdrawn by referrer) | ||
TTC102 | (July 00) | Silverlink | Railtrack’s proposals for the Rules of the Route 2001/02: (settled out of court) | ||
TTC103 | (July 00) | Great Western Trains | Railtrack’s proposals for the Rules of the Route 2001/02: (settled out of court) | ||
TTC104 | (July 00) | Wales & West Passenger Trains | Railtrack’s proposals for the Rules of the Route 2001/02: (settled out of court) | ||
TTC105 | 07.12.00 | Freightliner | Railtrack’s proposals for the Rules of the Route 2001/02 | ||
TTC106 | 07.12.00 | English Welsh & Scottish Railway | Railtrack’s proposals for the Rules of the Route 2001/02: | ||
TTC107 | (Aug. 00) | Eurostar (U.K.) | Railtrack’s proposals for the Rules of the Route 2001/02: (settled out of court) | ||
TTC108 | (Aug. 00) | Thames Trains | Railtrack’s decision to reject services for the Summer 2001 timetable: (withdrawn by the referrer) | ||
TTC109 | 01.11.00 | North Western Trains | Railtrack’s decision in respect of the Rules of the Plan 2001/02 | ||
TTC110 | 01.11.00 | Northern Spirit | Railtrack’s decision in respect of the Rules of the Plan 2001/02 | ||
TTC111 | (Oct. 00) | Thames Trains | Railtrack’s decision in respect of Bids for the Summer 2001 timetable: (settled out of court) | ||
TTC112 | (Dec. 00) | Great Western Trains | Railtrack’s decision in respect of Bids for the Summer 2001 timetable: (settled out of court) | ||
TTC113 | (Dec. 00) | Freightliner | Railtrack’s decision in respect of Bids for the Summer 2001 timetable: (settled out of court) | ||
TTC114 | (Dec. 00) | English Welsh & Scottish Railway | Railtrack’s decision in respect of Bids for the Summer 2001 timetable: (settled out of court) | ||
TTC115 | (Mar. 01) | Great Western Trains | Railtrack’s decision in respect of Bids for the Winter 2001/02 timetable: (settled out of court) | ||
TTC116 | (Mar. 01) | Thameslink Rail | Railtrack’s decision in respect of a Spot Bid: (settled out of court) | ||
TTC117 | (Mar. 01) | Great Western Trains | Railtrack’s decision in respect of Bids for the Winter 2001/02 timetable: (settled out of court) | ||
TTC118 | (May 01) | North Western Trains | Railtrack’s decision in respect of the National Rules of the Plan (section3, clause 5.3) for the 2002 timetable: (settled out of court) | ||
TTC119 | (May 01) | Arriva Trains Northern | Railtrack’s decision on proposed amendments to the Rules of the Route 2001/02: (settled out of court) | ||
TTC120 | (June 01) | English Welsh & Scottish Railway | Railtrack’s decision in respect of Bids for the Winter 2001/02 timetable: (settled out of court) | ||
TTC121 | (July 01) | Great Western Trains | Railtrack’s decision in respect of a proposal for possessions at Reading on 28/29.7.01: (settled out of court) | ||
TTC122 | (July 01) | Connex South Central | Railtrack’s decision to withdraw section 3 guidelines for granting possessions; Southern Zone Rules of the Route 2002/03: (settled out of court) | ||
TTC123 | (July 01) | Connex South Eastern | Railtrack’s decision to withdraw section 3 guidelines for granting possessions; Southern Zone Rules of the Route 2002/03: (settled out of court) | ||
TTC124 | (Aug. 01) | Thames Trains | Railtrack’s decision in respect of version 2 of the Rules of the Route for 2002/03: (settled out of court) | ||
TTC125 | (Aug. 01) | Great Western Trains | Railtrack’s decision in respect of version 2 of the Rules of the Route for 2002/03: (settled out of court) | ||
TTC126 | (Aug. 01) | Central Trains | Railtrack’s decision in respect of version 2 of the Rules of the Route for 2002/03: (settled out of court) | ||
TTC127 | (Aug. 01) | North Western Trains | Railtrack’s decision in respect of version 2 of the Rules of the Route for 2002/03: (settled out of court) | ||
TTC128 | (Aug. 01) | Great North Eastern Railway | Railtrack’s decision in respect of version 2 of the Rules of the Route for 2002/03: (settled out of court) | ||
TTC129 | 08.02.02 | English Welsh & Scottish Railway | Railtrack’s decision in respect of the Rules of the Route/Plan for 2002/03 [Anglo-Scottish Maintenance Strategy on the West Coast Main Line]: (settled out of court) | ||
TTC130 | (Aug. 01) | Freightliner | Railtrack’s decision in respect of version 2 of the Rules of the Route for 2002/03: (settled out of court) | ||
TTC131 | (Aug. 01) | Arriva Trains Northern | Railtrack’s decision in respect of version 2 of the Rules of the Route for 2002/03: (settled out of court) | ||
TTC132 | 30.11.01 | Eurostar (U.K.) | Railtrack’s decision to suspend Train Slots for Eurostar night services in the Draft Timetable for Summer 2002: | ||
TTC133 | (Oct. 01) | Rail Express Systems | Railtrack’s decision in respect of a Spot Bid for 1S06 Royal Mail train: (settled out of court) | ||
TTC134 | (Oct. 01) | Thames Trains | A Railtrack ‘decision’ in respect of the Draft Timetable for Summer 2002: (settled out of court) | ||
TTC135 | (Nov. 01) | South Central | A Railtrack ‘decision’ in respect of the Draft Timetable for Summer 2002: (settled out of court) | ||
TTC136 | 14.03.02 | Arriva Trains Northern | Railtrack’s decision in respect of the Rules of the Route/Plan for Winter 2002/03 | ||
TTC137 | (Dec. 01) | Connex South Eastern | Railtrack’s decision in respect of Bids for the Summer 2002 timetable: (settled out of court) | ||
TTC138 | (Dec. 01) | Thameslink Rail | Railtrack’s decision in respect of Bids for the Summer 2002 timetable: (settled out of court) | ||
TTC139 | (Dec. 01) | ScotRail Railways | Railtrack’s decision in respect of Bids for the Summer 2002 timetable: (settled out of court) | ||
TTC140 | (Dec. 01) | Great Western Trains | Railtrack’s decision in respect of Bids for the Summer 2002 timetable: (settled out of court) | ||
TTC141 | (Dec. 01) | Wessex Trains | Railtrack’s decision in respect of the use of Platform 0 at Cardiff Central for the Summer 2002 timetable: (settled out of court) | ||
TTC142 | (Dec. 01) | Freightliner | Railtrack’s decision in respect of Bids for the Summer 2002 timetable: (settled out of court) | ||
TTC143 | (Mar.02) | Great Western Trains | Railtrack’s decision in respect of changes to the Rules of the Route for September 2002: (settled out of court) | ||
TTC144 | 24.05.02 | Grand Central Railway | Railtrack’s decision in respect of Bids for the Winter 2002 timetable: | ||
TTC145 | (Apr.02) | Arriva Trains Northern | Railtrack’s decision in respect of the Rules of the Route/Plan for the Winter Two timetable 2002/03: (settled out of court) | ||
TTC146 | (Apr.02) | Central Trains | Railtrack’s decision in respect of Bids for the Winter One timetable 2002/03: (settled out of court) | ||
TTC147 | (Apr.02) | Great North Eastern Railway | Railtrack’s decision in respect of Bids for the Winter 2002/03 timetable: (settled out of court) | ||
TTC148 | (Apr.02) | Wessex Trains | Railtrack’s decision in respect of Bids for the Winter 2002/03 timetable: (withdrawn by referrer) | ||
TTC149 | (Apr. 02) | English Welsh & Scottish Railway | Railtrack’s decision in respect of Bids for the Winter 2002/03 timetable: (settled out of court) | ||
TTC150 | (May 02) | Great Western Trains | Railtrack’s decision in respect of Bids for the Winter 2002 timetable: (settled out of court) | ||
TTC151 | (July 02) | Great North Eastern Railway | Railtrack’s decision in respect of the Rules of the Plan for 2003/04: (settled out of court) | ||
TTC152 | (July 02) | Great Western Trains | Railtrack’s decision in respect of the Rules of the Route/Plan for 2003/04: (settled out of court) | ||
TTC153 | (July 02) | ScotRail Railways | Railtrack’s decision in respect of the Rules of the Route/Plan for 2003/04: (settled out of court) | ||
TTC154 | (July 02) | West Coast Trains | Railtrack’s decision in respect of the Rules of the Route for 2003/04: (settled out of court) | ||
TTC155 | 22.10.02 | Thames Trains | Railtrack’s decision in respect of the Rules of the Route/Plan for 2003/04: | ||
TTC156 | (July 02) | North Western Trains | Railtrack’s decision in respect of the Rules of the Route/Plan for 2003/04: (settled out of court) | ||
TTC157 | (July 02) | Silverlink Train Services | Railtrack’s decision in respect of the Rules of the Route for 2003/04: (settled out of court) | ||
TTC158 | (July 02) | Central Trains | Railtrack’s decision in respect of the Rules of the Route/Plan for 2003/04: (settled out of court) | ||
TTC159 | (July 02) | Great North Eastern Railway | Railtrack’s decision in respect of the Rules of the Route for 2003/04: (settled out of court) | ||
TTC160 | (July 02) | West Anglia Great Northern | Railtrack’s decision in respect of the Rules of the Route/Plan for 2003/04: (settled out of court) | ||
TTC161 | 20.09.02 | Arriva Trains Northern | Railtrack’s decision in respect of the Rules of the Route/Plan for 2003/04: | ||
TTC161A | 20.09.02 | Arriva Trains Northern | Two determinations were issued: Determination 161A - granted the parties additional time to reach agreement on matters relating to Sections 5 & 7 of the Rules of the Route, and gave specific deadlines by which the parties should refer unresolved issues back to the Committee for determination; | ||
TTC161B | 20.09.02 | Arriva Trains Northern | Determination 161B - contained decisions relating to the National Rules of the Plan | ||
TTC161C | 25.10.02 | Arriva Trains Northern | Unresolved issues relating to Section 5 of the Rules of the Route for 2003/04, referred back in accordance with Determination 161A: (settled out of court) | ||
TTC162 | (July 02) | English Welsh & Scottish Railway | Railtrack’s decision in respect of the Rules of the Route/Plan (Version 2) 2003/04: (settled out of court) | ||
TTC163 | [not used] | ||||
TTC164 | (Aug.02) | English Welsh & Scottish Railway | Railtrack’s decision in respect of Bids for the Winter Two 2002/03 timetable: (settled out of court) | ||
TTC165 | (Sept.02) | English Welsh & Scottish Railway | National Rules of the Plan, Section 3: possession strategy for Dolphingstone: (settled out of court) | ||
TTC166 | (Oct.02) | Freightliner | Railtrack’s decision in respect of the Rules of the Route/Plan (Version 3) 2003/04: (settled out of court) | ||
TTC167 | (Dec.02) | CrossCountry Trains | Railtrack’s decision in respect of the Rules of the Route (Version 4) 2003/04: (settled out of court) | ||
TTC168 | 23.01.03 | Grand Central Railway | Railtrack’s decision in respect of Bids for the Summer 2003 timetable: | ||
TTC169 | (Dec.02) | Great North Eastern Railway | Railtrack’s decision in respect of the Rules of the Route/Plan (Version 4) 2003/04: (settled out of court) | ||
TTC170 | (Dec.02) | Arriva Trains Northern | Railtrack’s decision in respect of the Rules of the Route/Plan (Version 4) 2003/04: (withdrawn by referrer) | ||
TTC171 | (Dec.02) | Thames Trains | Railtrack’s decision in respect of the Rules of the Route (Version 4) 2003/04: (withdrawn by referrer) | ||
TTC172 | (Dec.02) | Freightliner | Railtrack’s decision in respect of Bids for the Summer 2003 timetable: (withdrawn by referrer) | ||
TTC173 | (Dec.02) | Great Western Trains | Railtrack’s decision in respect of Bids for the Summer 2003 timetable: (withdrawn by referrer) | ||
TTC174 | (Dec.02) | English Welsh & Scottish Railway | Railtrack’s decision in respect of Bids for the Summer 2003 timetable: (settled out of court) | ||
TTC175 | (Apr.03) | English Welsh & Scottish Railway | Network Rail’s decision in respect of Rules of the Route (Paddington re-signalling): (settled out of court) | ||
TTC176 | (Apr.03) | English Welsh & Scottish Railway | Network Rail’s decision in respect of Bids for the Winter One 2003/04 timetable for Anglo-Scottish services: (settled out of court) | ||
TTC177 | (Apr.03) | English Welsh & Scottish Railway | Network Rail’s decision in respect of Bids for the Winter One 2003/04 timetable for other than Anglo-Scottish services: (settled out of court) | ||
TTC178 | (Apr.03) | Freightliner | Network Rail’s decision in respect of Bids for the Winter One 2003/04 timetable: (settled out of court) | ||
TTC179 | (Apr.03) | Great Western Trains | Network Rail’s decision in respect of Bids for the Winter One 2003/04 timetable: (settled out of court) | ||
TTC180 | 04.08.03 | ScotRail Railways | Network Rail’s decision in respect of the Rules of the Route for the Winter Two period of the 2003/04 Timetable: The Committee issued a Note of Extraordinary deliberations to explain why, for technical reasons, it could not issue a formal determination. | ||
TTC181 | (July 03) | Grand Central Railway | Railtrack’s decision in respect of Bids for the Winter Two 2003/4 timetable: (settled out of court) | ||
TTC182 | 29.08.03 | Great Western Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2004: | ||
TTC183 | (July 03) | The Chiltern Railway Co. | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2004: (settled out of court) | ||
TTC184 | (July 03) | North Western Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2004: (settled out of court) | ||
TTC185 | (July 03) | Freightliner | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2004: (settled out of court) | ||
TTC186 | (Aug.03) | English Welsh & Scottish Railway | Railtrack’s decision in respect of Bids for the Winter Two 2003/04 timetable: (settled out of court) | ||
TTC187 | (Aug.03) | English Welsh & Scottish Railway | Network Rail’s decision in respect of the Rules of the Route/Plan for 2004: (settled out of court) | ||
TTC188 | (Aug.03) | Arriva Trains Northern | Network Rail’s decision in respect of the Rules of the Route/Plan for 2004: (settled out of court) | ||
TTC189 | 9/28.10.03 | Thames Trains | Network Rail’s decision in respect of the Rules of the Route for 2004: | ||
TTC190 | 10.10.03 | Silverlink Train Services | Network Rail’s decision in respect of the Rules of the Route for 2004: | ||
TTC191 | 23.12.03 | Freightliner Heavy Haul | Network Rail’s decision in respect of Bids for the Winter Two 2003/04 timetable: | ||
TTC192 | 23.09.03 | Great North Eastern Railway | Network Rail’s decision in respect of the Rules of the Route/Plan for 2004: | ||
TTC193 | (Aug.03) | English Welsh & Scottish Railway | Network Rail’s decision in disregard of Condition D3.7.5: [Note: after discussion train retimed to satisfaction of all parties]: (settled out of court) | ||
TTC194 | 26.09.03 | ScotRail Railways | Network Rail’s decision in respect of Bids for the Winter Two 2003/04 timetable: | ||
TTC195 | (Sep.03) | Freightliner | Network Rail’s decision in respect of the Rules of the Route/Plan (Version 3) for 2004: (settled out of court) | ||
TTC196 | (Sep.03) | Great North Eastern Railway | Network Rail’s decision in respect of the Rules of the Route/Plan (Version 3) for 2004: (settled out of court) | ||
TTC197 | (Sep.03) | English Welsh & Scottish Railway | Network Rail’s decision in respect of the Rules of the Route/Plan (Version 3) for 2004: (settled out of court) | ||
TTC198 | (Dec.03) | CrossCountry Trains | Network Rail’s decision in respect of an amendment to the Rules of the Route for weeks 17-22 at Stafford: (settled out of court) | ||
TTC199 | (Dec.03) | Silverlink Train Services (London lines) | Network Rail’s decision in respect of an amendment to the Rules of the Route for the late Spring Bank Holiday 2004: (settled out of court) | ||
TTC200 | (Dec.03) | Freightliner | Network Rail’s decision in respect of Bids for the Summer 2004 timetable (settled out of court) | ||
TTC201 | (Dec.03) | English Welsh & Scottish Railway | Network Rail’s decision in respect of Bids for the Summer 2004 timetable (settled out of court) | ||
TTC202 | (Dec.03) | Freightliner Heavy Haul | Network Rail’s decision in respect of Bids for the Summer 2004 timetable (settled out of court) | ||
TTC203 | 29.01.04 | Thames Trains | Network Rail’s decision in respect of Bids for the Summer 2004 timetable | ||
TTC204 | (Jan.04) | CrossCountry Trains | Network Rail’s decision in respect of an amendment to Rules of the Route for 2004: Periods 4b & 5 (Crewe-Cheadle Hulme) (settled out of court) | ||
TTC205 | 04.03.04 | English Welsh & Scottish Railway | Adherence to acceptance procedures in respect of a Spot Bid for 7O81: | ||
TTC206 | (Jan.04) | ScotRail Railways | Network Rail’s decision in respect of the Rules of the Route (Version 4) for 2004: (settled out of court) | ||
TTC207 | (Jan.04) | ScotRail Railways | Network Rail’s decision in respect of an amendment to the Rules of the Route for 2003/04 (weeks 50 & 51): (settled out of court) | ||
TTC208 | (Jan.04) | Freightliner | Network Rail’s decision in respect of the Rules of the Route (Version 4) for 2004: (settled out of court) | ||
TTC209 | (Jan.04) | Great Western Trains | Network Rail’s decision in respect of the Rules of the Route (Version 4) for 2004: (settled out of court) | ||
TTC210 | (Jan.04) | Arriva Trains Northern | Network Rail’s decision in respect of the Rules of the Route/Plan (Version 4) for 2004: (settled out of court) | ||
TTC211 | 23.03.04 | Freightliner | Network Rail’s decision in respect of short notice additional possessions on the WCML: weeks 1-8, 2004 | ||
TTC212 | 23.03.04 | English Welsh & Scottish Railway | Network Rail’s decision in respect of short notice additional possessions on the WCML: weeks 1-8, 2004 | ||
TTC213 | 23.03.04 | ScotRail Railways | Network Rail’s decision in respect of short notice additional possessions on the WCML: weeks 1-8, 2004 | ||
TTC214 | (Mar.04) | Silverlink Train Services | Network Rail’s decision in respect of short notice additional possessions on the WCML: weeks 2 & 4, 2004 (withdrawn by referrer) | ||
TTC215 | (Mar.04) | North Western Trains | Extended Disruption (Condition H7): Damaged Network at Bootle Branch Jcn (settled out of court) | ||
TTC216 | (Feb.04) | Silverlink Train Service | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (lapsed when Silverlink submitted reference NV65 to the Network and Vehicle Change Committee) | ||
TTC217 | (Feb.04) | Arriva Trains Wales | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (settled out of court) | ||
TTC218 | (Feb.04) | ScotRail Railways | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (settled out of court) | ||
TTC219 | (Feb.04) | Freightliner Heavy Haul | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (settled out of court) | ||
TTC220 | (Feb.04) | Arriva Trains Northern | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (settled out of court) | ||
TTC221 | (Feb.04) | Great Northern Eastern Railway | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (settled out of court) | ||
TTC222 | (Feb.04) | Central Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (settled out of court) | ||
TTC223 | (Feb.04) | North Western Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (settled out of court) | ||
TTC224 | (Feb.04) | CrossCountry Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2005 (settled out of court) | ||
TTC225 | (Apr.04) | English Welsh & Scottish Railway | Network Rail’s decision in respect of the Rules of the Route for WCML, August 2005 (settled out of court) | ||
TTC226 | (May 04) | ScotRail Railways | Network Rail’s decision in respect of the Rules of the Route (Versions 3 & 4) for 2005 (settled out of court) | ||
TTC227 | (June 04) | Freightliner | Network Rail’s decision in respect of the Rules of the Route (Version 3) for 2005 (settled out of court) | ||
TTC228 | (June 04) | CrossCountry Trains | Network Rail’s decision in respect of the Rules of the Route (Version 3) for 2005 (settled out of court) | ||
TTC229 | (June 04) | Arriva Trains Northern | Network Rail’s amendment in accordance with Condition D2.1.9 in respect of section 7 of the Rules of the Route for 2005 (settled out of court) | ||
TTC230 | (Feb.04) | English Welsh & Scottish Railway | Network Rail’s decision in respect of the Rules of the Route (Version 3) for 2005 (settled out of court) | ||
TTC231 | (July 04) | English Welsh & Scottish Railway | Network Rail’s amendment in accordance with Condition D2.1.9 in respect of the Rules of the Route for 2005 (settled out of court) | ||
TTC232 | 01.09.04 | CrossCountry Trains | Network Rail’s decision in respect of the Rules of the Route (Version 3) for 2005 | ||
TTC233 | (Aug.04) | West Coast Trains | Network Rail’s amendment in accordance with Condition D2.1.9 in respect of the Rules of the Route for 2005 (settled out of court) | ||
TTC234 | (Aug.04) | English Welsh & Scottish Railway | Network Rail’s decision in respect of the Rules of the Route for 2005 – additional possessions in weeks 31 & 32 (settled out of court) | ||
TTC235 | (Aug.04) | Freightliner | Network Rail’s decision in respect of the Rules of the Route (Version 4) for 2005 (settled out of court) | ||
TTC236 | (Aug.04) | CrossCountry Trains | Network Rail’s decision in respect of the Rules of the Route (Version 3) for 2005, Periods 0, A & B (settled out of court) | ||
TTC237 | (Aug.04) | Arriva Trains Northern | Network Rail’s amendment in accordance with Condition D2.1.9 in respect of the Rules of the Route for 2005 (settled out of court) | ||
TTC238 | (Aug.04) | North Western Trains | Network Rail’s decision in respect of the Rules of the Route (Version 4) for 2005, Periods C & D (settled out of court) | ||
TTC239 | (Aug.04) | CrossCountry Trains | Network Rail’s decision (on 10 August 2004) in respect of the Rules of the Route for 2005 (settled out of court) | ||
TTC240 | (Aug.04) | Freightliner Heavy Haul | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC241 | (Aug.04) | ScotRail Railways | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC242 | 12.10.04 | Great Western Trains | Network Rail’s decision in respect of Bids for the December 2004 timetable | ||
TTC243 | (Aug.04) | GB Railfreight | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC244 | 12.10.04 | First Great Western Link | Network Rail’s decision in respect of Bids for the December 2004 timetable | ||
TTC245 | (Aug.04) | Freightliner | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC246 | (Aug.04) | Wessex Trains | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC247 | (Aug.04) | South Eastern Trains | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC248 | (Aug.04) | Arriva Trains Northern | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC249 | (Aug.04) | Eurostar (U.K.) | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC250 | (Aug.04) | English Welsh & Scottish Railway | Network Rail’s decision in respect of Bids for the December 2004 timetable (settled out of court) | ||
TTC251 | 06.01.05 | Great Western Trains | Network Rail’s decision in respect of further changes in weeks 1 & 2 to the Rules of the Route for 2005 | ||
TTC252 | 25.02.05 | Arriva Trains Northern | Network Rail’s decision in respect of further changes to the Rules of the Route for 2005 for the Settle & Carlisle line | ||
TTC253 | 25.02.05 | Arriva Trains Northern | Network Rail’s decision in respect of further changes to the Rules of the Route for 2005 for the Saltburn branch. The Committee commenced a hearing of this reference from Arriva Trains Northern, but it was soon apparent that much of the information that was emerging during the course of the hearing had not been fully shared between the Parties concerned at the appropriate point in time during the consultation period or subsequently. The Committee therefore instructed the Parties to enter into full and proper dialogue on all relevant issues and, after they had reached a common understanding of the facts, to advise the Committee which elements of the dispute were still unresolved, meanwhile the Committee adjourned the hearing. The Parties subsequently met and after fully sharing the information available reached a solution of their dispute, and Northern Rail formally asked that the dispute be withdrawn. This was agreed by the Committee. | ||
TTC254 | (Dec.04) | CrossCountry Trains | Network Rail’s decision in respect of further changes to the Rules of the Route for 2005 (settled out of court) | ||
TTC255 | (Dec.04) | LTS Rail | Network Rail’s decision in respect of further changes to the Rules of the Route for 2006 (settled out of court) | ||
TTC256 | 02.03.05 | Silverlink Train Services | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 | ||
TTC257 [TTP01] | (Dec.04) | Northern Rail (East) | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC258 | (Dec.04) | New Southern Railway | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC259 [TTP02] | (Dec.04) | First ScotRail | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC260 | (Dec.04) | West Anglia Great Northern | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC261 | (Dec.04) | Heathrow Connect | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC262 [TTP03] | [20.07.05] | English Welsh & Scottish Railway PENDING at 15.04.05; and subsequently heard by a Timetabling Panel on 20.07.05 | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 | ||
TTC263 | (Dec.04) | Freightliner | Network Rail’s decision in respect of the Rules of the Route (Version 2)[for Shenfield – Norwich route] for 2006 (settled out of court) | ||
TTC264 [TTP04] | [22.08.05] | Freightliner PENDING at 15.04.05; and subsequently heard by a Timetabling Panel on 22.08.05 | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 | ||
TTC265 | 23.02.05 | Arriva Trains Wales | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 | ||
TTC266 [TTP05] | (Dec.04) | Great North Eastern Railway | Network Rail’s decision in respect of items in Section 7 of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC267 | (Dec.04) | Northern Rail (West) | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC268 | (Dec.04) | First/Keolis Transpennine Express | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC269 | (Dec.04) | South Eastern Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC270 | (Jan.05) | CrossCountry Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC271 | 17.02.05 | West Coast Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 | ||
TTC272 [TTP06] | (Jan.05) | Great North Eastern Railway | Network Rail’s decision in respect of items in Sections 4 & 5 of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC273 [TTP07] | (Dec.04) | Freightliner Heavy Haul | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC274 | (Jan.05) | Eurostar (U.K.) | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC275 | 11.03.05 & 29.03.05 | Great Western Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 | ||
TTC276 | (Jan.05) | First ScotRail | Network Rail’s decision in respect of Bids for the June 2005 timetable (settled out of court) | ||
TTC277 | (Jan.05) | Great Westerrn Trains | Network Rail’s decision in respect of Bids for the June 2005 timetable (settled out of court) | ||
TTC278 | (Jan.05) | Eurostar (U.K.) | Network Rail’s decision in respect of Bids for the June 2005 timetable (settled out of court) | ||
TTC279 | (Feb.05) | English Welsh & Scottish Railway | Network Rail’s decision in respect of the changes other than twice yearly to the Rules of the Route for 2006 (settled out of court) | ||
TTC280 | (Feb.05) | Northern Rail (East) | Network Rail’s decision in respect of the changes other than twice yearly to the Rules of the Route for 2006 (settled out of court) | ||
TTC281 [TTP08] | (Jan.05) | CrossCountry Trains | Network Rail’s decision in respect of the Rules of the Route (Version 2) for 2006 (settled out of court) | ||
TTC282 | (Feb.05) | Freightliner Heavy Haul | Network Rail’s decision in respect of changes (in a batching document) to the Rules of the Route for 2006 (settled out of court) | ||
TTC283 | (Feb.05) | GB Railfreight | Network Rail’s decision in respect of changes (in a batching document) to the Rules of the Route for 2006 (settled out of court) | ||
TTC284 | (Feb.05) | CrossCountry Trains | Network Rail’s decision in respect of revised proposals for changes in weeks 11/12 of the Rules of the Route 2005 (settled out of court | ||
TTC285 [TTP09] | (Jan.05) | First ScotRail | Network Rail’s decision in respect of changes (in a batching document) to the Rules of the Route for 2006 (settled out of court) | ||
TTC286 | (Feb.05) | English Welsh & Scottish Railway | Network Rail’s decision in respect of the Rules of the Route (Version 3) for 2005 (settled out of court) | ||
TTC287 [TTP07] | (Mar.05) | Freightliner Heavy Haul | Network Rail’s decision in respect of the Rules of the Route (Version 3) for 2005 (settled out of court) | ||
TTC288 | (Mar.05) | Northern Rail (East) | Network Rail’s decision in respect of the Rules of the Route (batching document 3) for 2006 (settled out of court) | ||
TTC289 | (Mar.05) | English Welsh & Scottish Railway | Network Rail’s decision in respect of the Rules of the Route (batching document 2) for 2006 (settled out of court) | ||
TTC290 [TTP03] | [20.07.05] | English Welsh & Scottish Railway PENDING at 15.04.05; and subsequently heard by a Timetabling Panel on 20.07.05 | Network Rail’s decision in respect of the Rules of the Route (batching document 3) for 2006 |