Rule, Clause or Condition | Determination | Date of Hearing | Points Made Within Determination |
---|---|---|---|
B2.1. Determination of Causes of Delays or Cancellations | AD3 | Feb 1996 |
The Committee determined that, in the case of Trust Attribution code XA applied to incidents of vandalism, including stone throwing from without Railway premises, the attribution should be to Railtrack, if the train is standing on Railtrack controlled infrastructure, and in all other cases to the Operator of the Train. |
B2.1. Determination of Causes of Delays or Cancellations | AD29 | April 2003 |
In advance of the inauguration of the Delay Attribution Board, the Access Dispute Resolution Committee was asked to determine the proper allocation of delays resulting from the non-deliberate closing of the Main reservoir pipe on an EMU whilst in service. The Committee determined that, in all the circumstances of this case, there were no reasonable grounds for allocating the incident other than to the Train Operator as “originating from or affecting rolling stock operated by…the Train Operator”. |
B2.1. Determination of Causes of Delays or Cancellations | AD39 | October 2004 |
The Committee considered that AD27 had established a distinction that was of direct relevance to this case, namely that the (largely mechanistic) process that, in accordance with the terms of the Track Access Agreement, attributes an Incident that causes Delay to one or other of the contracting parties, is something totally different in kind from the discovery and attribution of the cause of that Incident. Attribution to the right contracting party is a function of the operation of Schedule 8 in relation to quantified Delays that have occurred, and as such is the proper province of the TRUST Delay Attribution Guide. Establishing possible chains of causality, relates, speculatively, to matters which may or may not have lead to Delay, and which are not therefore themselves Delay Incidents; as such they have no part in the operation of Schedule 8, nor are they within the province of the TRUST Delay Attribution Guide. In respect of the current case, the Committee was of the view that, until the fire on the train was reported (at 23:56, by the local Fire brigade), there was no Delay Incident. Thereafter, there was Delay, and that Delay should properly all be attributed to the fact of the Fire on the Train, and not to any speculation as to how the fire came to be on the train. (AD39, paras 8, 9) |
B2.1. Determination of Causes of Delays or Cancellations | ADP07 | August 2005 |
The Panel therefore concluded that the conclusion that the former Access Dispute Resolution Committee had reached on the practical force of the DAG, in its Determination AD39, was still valid, and did not require to be reversed as a consequence of the amendment to Network Code Condition B1.3 to incorporate the DAG into the Network Code. Thus, the Panel’s …“standing in the case derived from the fact that delay attribution is first and foremost a matter of the application of the relevant section (in this case section 5 of Schedule 8) of the Track Access Agreement between the parties. The Delay Attribution Guide is a convenient accumulation of the case law in relation to Delay Attribution, but….it relates to the way in which incidents that have occurred should, in accordance with the Track Access Agreement, be charged to the account of one or other party. It is not any part of a mechanism by which one or other party is held responsible in law for an incident” [quote taken from AD39 para 6] (ADP07, para 10) |
B2.1. Determination of Causes of Delays or Cancellations | ADP07 | August 2005 |
Taking account of all the preceding factors, the Panel determined that
(ADP07, para17) |
B2.1. Determination of Causes of Delays or Cancellations | ADP07 | August 2005 |
The Panel therefore finds that, in the circumstance where a single train, or set of train crew, operates a through service utilising the Track Access rights of more than one Train Operator,
(ADP07, para18) |
B2.1. Determination of Causes of Delays or Cancellations | ADP11 | November 2005 |
… because delay only occurs once there is an actual incident, it should be attributed, as between the Train Operator and Network Rail, by reference to which body has the responsibility for the factor which makes the decisive difference between no Delay Incident and an actual Delay Incident. (ADP11, para16.2) |
B2.1. Determination of Causes of Delays or Cancellations | ADP11 | November 2005 |
Taking account of all the preceding factors, the Panel determined that:
(ADP11, para 18) |
B2.1. Determination of Causes of Delays or Cancellations | ADP16 | April 2006 |
Taking account of the arguments advanced by the parties, and the previous determination ADP07, the Panel determined that:
(ADP16, para 14) |
B2.1. Determination of Causes of Delays or Cancellations | ADP19 | October 2006 |
The Panel considered that, in respect of all the detail of this dispute, there was a need to bear in mind the clear distinction between the provisions of the Network Code, which are incorporated within and form a mandatory element of every Network Rail Track Access Contract approved by the Office of Rail Regulation, and the specific, and sometimes bespoke, provisions of the individual Track Access Contract with the individual Train Operator. In particular, the Panel differentiated:
(ADP19, para 9) |
B2.1. Determination of Causes of Delays or Cancellations | ADP30 | February 2008 |
… the Determination made in the name of the Panel is that:
(ADP30, para 42) |
B2.1. Determination of Causes of Delays or Cancellations | ADP39 | July 2009 |
The Panel reminded itself that the practical function of the DAG is provide criteria by which to judge circumstances in which delay has occurred, and to make a pragmatic attribution of responsibility, for the purposes of furnishing the data necessary to calculate the sums payable, in this case, under the Passenger Schedule 8 Performance Regime. On the other hand, however useful the guidance given, where the DAG does not contemplate the circumstances of a case then the correct attribution has to be based upon an assessment of how the specific circumstances in question align with the three different categories of defined contractual responsibility in Schedule 8:
The Panel acknowledged that in this case neither FSR nor Network Rail had sought to apply paragraph 5.4 and so, Schedule 8 admitting of no other options, the issue in question is which of paragraph 5.2 or 5.3 properly applies. In the absence of an appropriate code in the DAG, the Panel must decide the allocation on the basis of all relevant available information. (ADP39, paras 20, 21) |
B2.1. Determination of Causes of Delays or Cancellations | ADP39 | July 2009 |
… the responsibility for ensuring that all Train Operators work to a common set of Rules, aimed at achieving consistent safe outcomes, lies with Network Rail. However, the responsibility for translating the achievement of those outcomes, insofar as they impact upon the ways in which trains are driven, is a matter for the Train Operator, which bears the responsibility for assuring that its employees (in this case its drivers) are trained, supervised, and maintained to the necessary level of professional competence to meet its obligations to Network Rail; if that larger responsibility for the professional competence of its drivers lies with the Train Operator, it must follow that, if the proper discharge of that professional competence results in a train delay, then that delay is inevitably within “the control of the Train Operator in its capacity as an operator of trains”, and therefore the attribution of the delay has to be to the Train Operator, in accordance with Passenger Schedule 8 paragraph 5.3.; by contrast, Network Rail has no control over the nature or quality of the judgements to be made by the driver, either on the day or in the formation of the relevant professional competence. Furthermore, in this instance, Network Rail has not failed in any respect in the normal operation of the Network, that would justify these delays being attributed to “circumstances within the control of Network Rail in its capacity as operator of the Network”. It would therefore be quite wrong to designate these delays “Network Rail responsibility incidents”. (ADP39, paras 23.7, 23.8, 23.9, 23.10) |
B2.4.4 Guidance from the Board | AD39 | October 2004 |
The Committee noted that the findings of the Delay Attribution Board have, under the terms of Track Access Condition B2.4, the status of guidance and are not a determination. In the circumstances envisaged in Track Access Condition B2.4.4 the Industry Committee is not acting as a court of appeal, but as the determining body of first instance. In these circumstances the Committee considered that it … should rather confine itself to a consideration of the cases as made directly by the parties. (AD39, para 4) |
Please make your selection below - click a section heading to expand. Where a heading does not have a “+” symbol next to it, that section/provision has not been the subject of consideration by a Dispute Panel and that therefore there is no documented case law to consult.
Attention is drawn to the way in which, over time, and as documented below, Committees and Panels have differentiated between three complementary, but discrete, processes, namely:
-
The investigation of causes of problems, or delays, often as a precursor to remedial action
-
The allocation of instances of delay, in accordance with principles most recently codified in the Delay Attribution Guide; and (to the extent applicable)
-
Determining levels of compensation payments due from Network Rail to Train Operator, or from Train Operator to Network Rail,, under the terms of the applicable Track Access Contract.
To search the Directory expand the page by clicking ‘open all’ on the right-hand side below, then use ‘ctrl + f’ to search for keywords or cases.