Reference Number PDF Version Date Reference From Subject Submissions From The Parties
ADP1 (AD41) (Oct. 04) Central Trans Notice pursuant to the Network Code, Condition L7.1, re Local Output Commitments (STAYED pending the outcome of the appeal to the ORR against determination AD40; and then withdrawn by referrer)
ADP2 (AD42) (Oct. 04) Wessex Trains Notice pursuant to the Network Code, Condition L7.1, re Local Output Commitments (STAYED pending the outcome of the appeal to the ORR against determination AD40; and then withdrawn by referrer)
ADP3 (AD43) ADP3 01.06.05 Thameslink Rail and Network Rail Compensation for an unplanned possession resulting from flooding in Kings Cross tunnel Note: Network Rail referred the Panel’s determination on appeal to an arbitrator – see arbitration A18
ADP4 (AD44) (Mar. 05) First ScotRail Notice pursuant to the Network Code, Condition L7.1, re Local Output Commitments (settled out of court)
ADP5 (AD45) (Apr. 05) Eurostar (U.K.) Notice pursuant to the Network Code, Condition L7.1, re Local Output Commitments (STAYED pending the outcome of the appeal to the ORR against determination AD40; and then withdrawn by referrer)
ADP6 (AD46) (Apr. 05) Network Rail Payment of Access Charges in respect of Euston Station (settled out of court)
ADP7 (AD38) ADP7 06.07.05 Network Rail Delay Attribution: allocation of delay responsibility for incidents in the circumstances where a train is operated by different Train Operators for portions of a through journey
ADP8 ADP8 16.08.05 West Coast Trains Level of compensation payable pursuant to Part G of the Network Code in respect of costs of bus substitution during a period of West Coast Main Line possessions
ADP9 (May 05) Midland Mainline Alleged Network Change (settled out of court)
ADP10 (NV79 NV80) ADP10 02.08.05 Freightliner Group Claim for costs of increased resources to be incurred due to diversions necessitated by proposals in the WCML Major Project notice for 2005-2006 ORR’s decision not to hear an appeal
ADP11 ADP11 14.11.05 New Southern Railway and Network Rail Delay Attribution: allocation of delay responsibility due to external electrical interference affecting rolling stock
ADP12 (Nov.05) Freightliner Heavy Haul Vehicle Change: operation of trains with increased length between Humber and Kingsbury (settled out of court)
ADP13 ADP13 20.02.06 Network Rail (and EWS) Network Change: Remodelling of Rugby station area
ADP14 ADP14ADP14 22.02.06 First/Keolis Transpennine Express Vehicle Change: proposed introduction of Class 185 trains
ADP15 (Jan 06) Network Rail (and Thameslink Rail) Network Change: Imposition and removal of a temporary speed restriction at Silkstream Jcn, Hendon (withdrawn by referrer)
ADP16 ADP16 12.04.06 First Great Western Link Delay Attribution: Paddington
ADP17 Hearing on 09.08.06 but adjourned Silverlink Trains Services Network Code, Part E – effluent contamination at Euston station platforms
ADP18 ADP18 09.08.06 Silverlink Trains Services Network Code, Part E – oil contamination at Barking station platform
ADP19 ADP19 11.10.06 First ScotRail Delay Attribution for an incident at Croy on 26.09.05
ADP20 ADP20 24.1.07 First Great Western Interpretation of Schedule 4 of First Great Western’s Track Access Agreement
ADP21 ADP21 16.11.06 First Capital Connect Whether a programme of East Coast Main Line rewiring works should be classified as a Major Project. ADP 21 Joint Reference Index of Joint Reference The Panel’s determination was appealed to the Office of Rail Regulation by First Capital Connect. In July 2007 ORR delivered its judgement. Appendices 1 & 2 ORR’s appeal determination Appendices 4 & 5 First Capital Connect subsequently pursued the matter of compensation to arbitration – see arbitration A23 for Award as to Jurisdiction – after which the parties settled the issue between themselves. Appendix 3 Part 1
ADP22 (Oct.06) Network Rail Network Change – referred under Condition G2.4(a) – reinstatement of Rail Crossing at Porthmadog (withdrawn by Network Rail after Arriva Trains Wales confirmed it had received sufficient information about the proposed Network Change)
ADP23 ADP23ADP23 Link to Annexe to Determination 07.08.07 Network Rail
ADP24 (June 07) First Great Western Contention that proposed possessions at Airport Jn warrant the issue of a Possession Strategy Notice (settled out of court)
ADP25 (June 07) Network Rail Part J; Changes to Access Rights, Flows to Ratcliffe and Ironbridge PS (settled out of court)
ADP26 (July 07) Network Rail Part J; Changes to Access Rights, Peak Forest to Attercliffe and Hitchin (settled out of court)
ADP27 (Mar. 07) Silverlink Train Services Level of compensation payable in connection with possessions at Stratford (change of Panel jurisdiction from TTP126) (settled out of court)
ADP28 (Oct. 07) Network Rail Part J; Surrender of Access Rights, Lawley Street – Tilbury (settled out of court)
ADP29 (Oct. 07) Network Rail Part J; Surrender of Access Rights, Grain – Crewe (settled out of court)
ADP30 ADP30 13.02.08 First Capital Connect Delay Attribution for an incident at Elstree on 24.04.07
ADP31 ADP31 01.02.08 First Greater Western Vehicle Change: Costs and payment method for utilisation of Class 142 units in the Bristol and Exeter areas
ADP32 (June 08) New Southern Railway Station Access Conditions: Responsibility for settlement of charges arising out of leaks from the water supply to Arundel, Chichester and Lewes stations (withdrawn by referrer)
ADP33 Hearing commenced 29.10.08 and was adjourned 29.10.08 New Southern Railway Network Rail’s Offer for the Principal Timetable, December 2008 (change of Panel jurisdiction from TTP243) (withdrawn by the referrer following ORR decision in respect of section 22A Railways Act application, which removed the need for this matter to be determined by a Panel)
ADP34 (Jan.09) First Capital Connect Non payment by NXEC Trains of Station Access charges for use of Stevenage station (settled out of court)
ADP35 14.09.09 New Southern Railway 2006/07 Access charging at certain Major Stations Panel hearing held jointly with ADP36 and ADP38
ADP36 14.09.09 London & South Eastern Railway 2006/07 Access charging at certain Major Stations
ADP37 (Apr. 09) First Capital Connect Provision of access to information regarding 2008/09 utilities charging at certain Major Stations (settled out of court)
ADP38 14.09.09 First Capital Connect, First Greater Western, First/Keolis TransPennine, First ScotRail & Hull Trains 2006/07 Access charging at certain Major Stations Hull Trains subsequently withdrew from the dispute Panel hearing held jointly with ADP35 and ADP36
ADP39 ADP39 08.07.09 First ScotRail Delay Attribution for reduced speed running during fog on 13.04.07
ADP40 ADP40 14.10.09 First ScotRail Whether new engineering works policy for the West Coast Main Line should be classified as Network Change Network Rail appealed to ORR against the determination of the Panel hearing ORR’s directions following appeal determination ORR’s reasons for directions issued following appeal determination
ADP41 ADP41 11.11.09 First ScotRail Part J; use of Train Slots across the Forth Bridge
ADP42 ADP42 25.11.09 Network Rail Part J; Change to Access Rights, Mossend Euroterminal to Georgemas Jcn (train 4H44) DB Schenker Rail (UK) lodged an appeal with ORR against the determination of the Panel hearing
ADP43 (Oct. 09) Network Rail Part J; Change to Access Rights, Daventry to Grangemouth (Settled out of court)
ADP44 ADP44 25.11.09 Network Rail Part J; Change to Access Rights, Mossend Euroterminal to Georgemas Jcn (train 6H44) DB Schenker Rail (UK) lodged an appeal with ORR against the determination of the Panel hearing
ADP45 (Nov 09) Arriva Trains Wales Network Change: Cardiff Area Signalling Renewal (Settled out of court)
ADP46 21.01.10 Network Rail Delay Attribution for an incident in the Swanwick - Hamble area on 28.11.08 (Settled out of court)
ADP47 ADP47 11.02.10 GB Railfreight Access charges in relation to the approach to Doncaster Railport
ADP48 (Dec 09) Network Rail, First Capital Connect, First Greater Western and First ScotRail Interpretation of “repair” and “maintenance” in relation to Retail Telecomms (CIS and CCTV) at Franchised Stations where First Capital Connect, First Greater Western and First ScotRail are SFOs
ADP49 25.02.10 XC Trains Diversionary arrangements via Lichfield
ADP50 ADP50 24.03.10 Rail Express Systems Refusal of Access to Wembley Central station
ADP51 (Feb 10) Network Rail Part J; changes to Access rights, mail trains (Settled out of court)
ADP52 ADP52 14.04.10 GB Railfreight Part J; changes to Access rights GB Railfreight submitted an appeal to ORR in relation to this reference but this was done outside the prescribed time limit so not accepted
ADP53 (Apr 10) Network Rail Part J; Change to Access Rights, Mossend Euroterminal to Georgemas Jcn/Inverness (trains 4H44 and 6H44) (Settled out of court)