The Network Code Part J   Changes to Access Rights

This Page Was Last Updated on 20 July 2015

 

Part J: Changes to Access Rights

Part J relates to the extent of rights to train slots held under a Track Access Contract, and how, where commercial or other considerations supporting a given set of rights change, those rights can be varied, surrendered or transferred to another Train Operator.   These were initially not processes where the Access Disputes Panels were given any jurisdiction.   Further subsequent revisions to the whole of Part J have the consequence that all disputes arising out of the operation or interpretation of Part J are to be referred initially “for determination in accordance with the ADRR”, with, where a party “is dissatisfied with the decision reached” a right to appeal to the ORR in accordance with Condition M.   It should be noted that any process that relates to the definition of the Access Rights held by any party must result in changes to the relevant Track Access Agreement; part of the function of all such changes to be subject to the formal approval by the ORR.

In August 2007 ADP23 considered certain fundamental aspects of Conditions J7 and J8.   The determination was subsequently appealed to the Office of Rail Regulation.   In its Determination of the appeal, (published in January 2008) ORR “set aside” Determination ADP23 in its entirety.   The text of ADP23 is accessible on this website, but, in view of the range of the ORR’s criticisms of the Panel’s determination, the relevant parts of this Directory include only the findings of the ORR, and do not quote from that determination.

 

J1 Introduction

Network Code Section

Determination

Date of Hearing

Points made within Determination  (Verbatim extracts given in Italics, or between quotes)

J1.2 Interpretation - “Y-Path”

ADA21

March 2015

“ORR considers that the definitions in the Network Code and in the track access contracts are not inconsistent.  A QAR [“Quantum Access Right”] with a Y-Path in the Rights Table should appear as a Y-Path in the Working Timetable, assuming that the Train Operating Company has made an access proposal for both.  The track access contract concerns the allocation of QARs.  The Working Timetable is how those rights are expressed in a timetable period as Train Slots.”

[ORR determination of appeal against determination ADA21, para. 70]

 

J1.2 Interpretation  - “Primary Purpose Customer”

ADA21

March 2015

“The definition of a Primary Purpose Customer is a customer(s) other than the third party referred to in Condition J7.1.2(a).  ….  ORR considers that this must be the customer where the QAR [“Quantum Access Right”] concerned relates to transport services provided to that customer.  It cannot be just any other customer of the Incumbent reliant on another QAR.  The Primary Purpose rule relates to the transport service using a specific QAR.”

[ORR determination of appeal against determination ADA21, para. 63]

 

 

J4 Failure to Use

Network Code Section

Determination

Date of Hearing

Points made within Determination  (Verbatim extracts given in Italics, or between quotes)

J4.8 Counter Notice

ADP42 & 44

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ORR Appeal

November 2009

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

March 2010

37.    “….the Panel also finds that Condition J4.9.1 [now J4.8.1] states that when serving any Counter Notice, the Train Operator must provide evidence with the Counter Notice in support of its contentions.”….

38.    The Panel was advised, by the Disputes Chairman that a requirement that a proposition be supported by evidence is, in this particular instance, not legally satisfied merely by an assertion made without support of evidence.

39.    The Panel considered the Counter Notices as served by DBS, and concluded that, notwithstanding such other background information that it might have been given, such as the letter from Stobart supplied to Network Rail on 11th November 2009, and representations made at the hearing, its mandate to consider whether or not DBS had a “reasonable on-going commercial need” had to be determined on the evidence, as opposed to any assertion, provided “with the Counter Notice in support of its contentions”.

40.    After careful consideration the Panel concluded that DBS had not supplied any evidence of “reasonable on-going commercial need” with its Counter Notice, and that neither an assertion, nor a letter (that of 28th September) sent on November 11th (four weeks after the Counter Notice), fulfils that requirement.  Failure to comply with such an unequivocal formulation as “must provide evidence with the Counter Notice in support of its contentions” has therefore to imply that

40.1.     the Counter Notice does not have effect;

40.2.     the Panel has no basis or requirement to consider the merits of any arguments brought by DBS in relation to “reasonable on-going commercial need”;   and

40.3.     Network Rail is entitled to proceed as if, in accordance with J4.9.2 [now J4.8.2],

  no [valid] Counter Notice is served within 10 Working Days of receipt of a Failure to Use Notice:

(a)     the Train Operator [now Part J Access Beneficiary] will be deemed to have agreed to the surrender specified in the Failure to Use Notice;” and therefore

40.4Network Rail shall be entitled to proceed to carry out the processes for “Surrender of Access Rights” as prescribed in Conditions J4.12 and J5.4(d) [now J5.3.1(f)], and their transfer to the Applicant…”

The logic of the arguments addressed in the immediate foregoing paragraphs were considered by the ORR, to be “correct in terms of DBS' challenge on the grounds of reasonable on-going commercial need”.   This endorsement, which may be of value in other instances, was rendered irrelevant by the ORR’s other findings in respect of the proper interpretation of J5.3 (qv).   The adequacy or otherwise of the form of a Counter Notice, is of but academic interest, where the initial Notice has been deemed to have been inadequately formulated.  [THE OFFICE OF RAIL REGULATION'S DETERMINATION OF THE APPEAL BY DB SCHENKER RAIL (UK) LIMITED ("DBS") PURSUANT TO CONDITION J13.3 AND PART M OF THE NETWORK CODE AGAINST DETERMINATIONS ADP42 AND ADP44 OF THE ACCESS DISPUTES PANEL (THE "PANEL") OF THE ACCESS DISPUTES COMMITTEE IN RESPECT OF A JOINT REFERENCE BY DBS AND NETWORK RAIL INFRASTRUCTURE LIMITED ("NR") CONCERNING THE VALIDITY OF TWO THIRD PARTY FAILURE TO USE NOTICES SERVED BY NR ON DBS.]

J4.3 Failure to Use

ADA05

March 2011

“….acceptable reasons for a Failure to Use all revolve around a factor which is quite clearly outside the control of the train operator – a commodities fluctuation, a fire, a strike.  In these cases, the cessation of use follows directly from a decision or action which was taken by someone other than the train operator.  …. though the list is non-exhaustive we consider it would be wrong, having regard to the intention of Part J, to allow reasons which do not share that characteristic.  It logically follows then, that a Failure to Use which flows from an action taken by the train operator and which is within its control is not an acceptable reason for a Failure to Use.

In ORR’s view, a Failure to Use arising out of the decision (taken here for economic reasons) to close the … terminal is a classic example of a decision within the control of the operator.  As such it is not an acceptable reason for a Failure to Use.  The economic nature of the decision is not the decisive factor in considering acceptable reasons for a Failure to Use.”   [ORR determination of appeals against ADA05 determination, paras. 84 & 85]

 

J5 Failure to Use:   third party application

Network Code Section

 

Determination

Date of Hearing

 

Points made within Determination  (Verbatim extracts given in Italics, or between quotes)

J5.1    Third Party Failure to Use Notices

 

ADP41

November 2009

The Panel was asked to determine when, (i.e. what were the preconditions to be met) Network Rail could issue a Third Party Failure to Use Notice.

19.   .  The Panel …. construed J5.1 on the following basis.

20.   The issuing of a Third Party Failure to Use Notice by Network Rail to an Incumbent is dependent upon the fulfilment of four specific stated pre-conditions:  as these pre-conditions are all linked by “and”,  the Panel considered that all four must be met or no notice can be issued.

21.   J5.1 (a) states that the route to the issuing of a notice starts with “an application from …. (the “Applicant”) for a Quantum Access Right to a Train Slot”; this means that the Applicant (in this case FSR) is seeking (i.e. does not already possess) Rights such that it may become the Train Operator authorised to make use of a specific Train Slot; this in itself implies that the Train Slot sought is one that pre-exists the application and is not a Train Slot already secured by the Applicant (i.e. FSR);

22.   “Train Slot” is itself a defined expression, (“a train movement or a series of train movements, identified by arrival and departure times at each of the start, intermediate (where appropriate) and end points of each train movement”  [Network Code Part D]) and relates to the totality of the capacity Network Rail is required to allocate for the complete passage of the relevant service.

23.   In J5.1(b) [now J5.1.1(b)] this definition is further qualified, in relation to both the Applicant and the Incumbent,  viz

(b)      the Train Slot: [i.e. the Train Slot that is the subject of the application]

(i)                   is one in respect of which the Applicant can demonstrate a reasonable commercial need; and

(ii)                 was secured in exercise of a Quantum Access Right of another …. (the “Incumbent”); and

(iii)                is one in respect of which there is a …. Failure to Use by the Incumbent,

24.    The Panel noted that the parties had focussed their disagreement upon the meaning of Condition J5.1(b) (ii), and the Panel considered this first, as failure to fulfil any one of the four pre-conditions would validate Network Rail’s decision to decline to issue a Third Party Failure to Use Notice.

24.1.     J5.1 (b) (ii) makes clear that the Train Slot that is the subject of an application needs to derive from the Quantum Access Right of …. the “Incumbent”, which cannot therefore be FSR “the Applicant”.   Furthermore, as a Train Slot has no substance other than when incorporated as an entry in a Working Timetable, “was secured in exercise of a Quantum Access Right” can only mean that the Right was converted by the Incumbent from latent obligation to practical reality by the process of Bidding and Offering prescribed in Part D (Timetable Change).   Had DBS, the Incumbent, made a bid, the Train Slot that would have been secured would have been one permitting the passage of a Freight train over the Forth Bridge en route between Hunterston and Longannet (or vice versa).

24.2.     FSR did not make explicit precisely what Train Slot(s) it currently has “secured in exercise of” its Contingent Rights; however, to the extent that those Train Slots relate to services between Edinburgh, Fife and Aberdeen, FSR’s Train Slots have very little in common with the Quantum Firm Rights to move coal from Hunterston to Longannet held by DBS (at most no more than timings between Dalmeny Junction and Inverkeithing or Charlestown Junctions);   therefore

24.2.1.   it would not be reasonable to equate a Train Slot between Hunterston with Longannet with one between Edinburgh and Aberdeen, and

24.2.2.   the common fragment of both Train Slots (i.e. across the Forth Bridge) does not qualify to fulfil the definition of a Train Slot;    therefore

24.3.     FSR’s case falls because

24.3.1.   DBS has not secured a Train Slot, and even if it had

24.3.2.   the Train Slot secured in relation to movements between Hunterston and Longannet, would not have sufficed for a passenger service between Edinburgh, Fife and Aberdeen.

25.    On the basis of this construction of Condition J5.1(b) (ii) the Panel questions Network Rail preparedness to concede that FSR fulfilled Condition J5.1(b) (i).  Whilst  FSR has a “reasonable commercial need” for paths across the Forth Bridge to operate passenger services between Edinburgh, Fife and Aberdeen ,FSR’s “commercial need” cannot be fulfilled in terms of the Train Slots that might be “secured in exercise of” DSB’s Level 1 Rights.

26.    As FSR does not fulfil either of J5.1 pre-conditions (b) (i), or (b) (ii), a consideration of (b) (iii) might be considered superfluous.  In the event, the parties and the Panel were agreed that there was no Failure to Use by the Incumbent as the Incumbent, for responsible and previously tested reasons, had elected not to exercise the right to secure a Train Slot between Hunterston and Longannet via the Forth Bridge in the December 2009 Working Timetable.  The Panel therefore concluded that, because of its failure to meet the requirements of J5.1(b)(ii), by extension FSR’s notice did not meet the requirements of J5.1(b)(iii).  [ADP41]

 

 

J7 Freight transfer mechanism

Network Code Section

Determination

Date of Hearing

Points made within Determination  (Verbatim extracts given in Italics, or between quotes)

J7.1.2(a)

ADA21

March 2015

“… for Condition 7.1.2(a) parties must look at the transport services actually provided and not entirely rely on what is in the contract with the customer.”

[ORR determination of appeal against determination ADA21, para. 61]